overview of the south west peninsula
play

Overview of the South West Peninsula Regional Development Programme - PowerPoint PPT Presentation

Overview of the South West Peninsula Regional Development Programme Clive Goodman Network Strategy Engineer Background Significant increase in the connection of Distributed Energy Resources (DER) in the South West has made long term


  1. Overview of the South West Peninsula Regional Development Programme Clive Goodman Network Strategy Engineer

  2. Background • Significant increase in the connection of Distributed Energy Resources (DER) in the South West has made long term forecasting more complex • Regional Development Plans (RDPs) aim to analyse areas of large DER and network issues in accommodating DER • The idea of the RDPs is to use analysis to innovate and push the boundaries of current thinking ( new asset build) towards Distribution System Operator (DSO) type solutions • The RDP used a ‘whole system’ approach by approaching technical issues as a single entity (System Operator, Transmission Owner and Distribution System Operator/ Distribution System Owner) • The objective is to find the most economical and efficient solution for the energy customer.

  3. South West Peninsula Map

  4. South West Network Model ALVE1 GALASWORTHY PYWO1 TAUN4 HINB NORTHMOOR ALVE4 CREDACOTT CANWORTHY OTTERHAM STUD1 ABHA4 AXMI INDQ4 LAND4 LAGA4 EXET4 INDQ1 CHIC PLPT1 SAUS1 SGER1 LAND1 PLYM1 EXET1 ABHA1 ERNE1 MILH1 NEWA1

  5. Future Energy Scenarios (July 2016)

  6. South West Renewable DER Growth

  7. Results • Studies undertaken for intact network and credible maintenance outage and fault conditions for 2020, 2025 &2030 • Potential network issues have been identified beyond 2020 if the growth in DER progresses under the most extreme ‘gone green’ scenario. • Many generation dispatch conditions cause ratings to be exceeded on both the Distribution & Transmission networks. Therefore any investment decisions must be linked to achieve the most economic whole system outcomes. • Credible non-build/build solutions have been identified and National Grid have undertaken a cost benefit analysis to investigate the most economic whole system recommendation to future network challenges

  8. Summary • Cumulative impact of new connections indicates a risk of insufficient transmission capacity to cope with peak intermittent generation • Costs and timescales to reinforce the transmission system prior to connection are not necessarily the most appropriate solution • WPD and National Grid are working collaboratively to find alternative solutions to ‘conventional’ reinforcement

  9. Future Connections A Connect and Manage approach has been adopted on the principle to: • Maintain system integrity & security • Operate an efficient, economic and coordinated system • Manage constraints at least cost to customers • Support customer investment decisions • Provide customers access to new and existing markets to allow them to build a viable business case

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend