Overview of the South West Peninsula Regional Development Programme - - PowerPoint PPT Presentation

overview of the south west peninsula
SMART_READER_LITE
LIVE PREVIEW

Overview of the South West Peninsula Regional Development Programme - - PowerPoint PPT Presentation

Overview of the South West Peninsula Regional Development Programme Clive Goodman Network Strategy Engineer Background Significant increase in the connection of Distributed Energy Resources (DER) in the South West has made long term


slide-1
SLIDE 1

Overview of the South West Peninsula Regional Development Programme

Clive Goodman Network Strategy Engineer

slide-2
SLIDE 2

Background

  • Significant increase in the connection of Distributed Energy Resources (DER) in the

South West has made long term forecasting more complex

  • Regional Development Plans (RDPs) aim to analyse areas of large DER and network

issues in accommodating DER

  • The idea of the RDPs is to use analysis to innovate and push the boundaries of current

thinking ( new asset build) towards Distribution System Operator (DSO) type solutions

  • The RDP used a ‘whole system’ approach by approaching technical issues as a single

entity (System Operator, Transmission Owner and Distribution System Operator/ Distribution System Owner)

  • The objective is to find the most economical and efficient solution for the energy

customer.

slide-3
SLIDE 3

South West Peninsula Map

slide-4
SLIDE 4

South West Network Model

HINB AXMI CHIC EXET4 TAUN4 LAGA4 ABHA4

EXET1 ABHA1 NEWA1

LAND4 INDQ4 ALVE4

LAND1 PLPT1 PLYM1 MILH1 ERNE1 ALVE1 INDQ1 PYWO1 STUD1 SAUS1

GALASWORTHY NORTHMOOR CANWORTHY OTTERHAM CREDACOTT

SGER1

slide-5
SLIDE 5

Future Energy Scenarios (July 2016)

slide-6
SLIDE 6

South West Renewable DER Growth

slide-7
SLIDE 7

Results

  • Studies undertaken for intact network and credible maintenance outage and fault

conditions for 2020, 2025 &2030

  • Potential network issues have been identified beyond 2020 if the growth in DER

progresses under the most extreme ‘gone green’ scenario.

  • Many generation dispatch conditions cause ratings to be exceeded on both the

Distribution & Transmission networks. Therefore any investment decisions must be linked to achieve the most economic whole system outcomes.

  • Credible non-build/build solutions have been identified and National Grid have

undertaken a cost benefit analysis to investigate the most economic whole system recommendation to future network challenges

slide-8
SLIDE 8

Summary

  • Cumulative impact of new connections indicates a risk of insufficient

transmission capacity to cope with peak intermittent generation

  • Costs and timescales to reinforce the transmission system prior to

connection are not necessarily the most appropriate solution

  • WPD and National Grid are working collaboratively to find alternative

solutions to ‘conventional’ reinforcement

slide-9
SLIDE 9

Future Connections

A Connect and Manage approach has been adopted on the principle to:

  • Maintain system integrity & security
  • Operate an efficient, economic and coordinated system
  • Manage constraints at least cost to customers
  • Support customer investment decisions
  • Provide customers access to new and existing markets to allow them to build a viable

business case