Overcoming Design and Construction Challenges in a Former Military - - PDF document

overcoming design and construction challenges in a former
SMART_READER_LITE
LIVE PREVIEW

Overcoming Design and Construction Challenges in a Former Military - - PDF document

Overcoming Design and Construction Challenges in a Former Military Base Marina Coast Water District Regional Urban Water Augmentation Project Presented to: Presented by: Michael Wegley, MCWD Jon Marshall, Carollo May 14, 2019 Filename.ppt/1


slide-1
SLIDE 1

1

Filename.ppt/1

Overcoming Design and Construction Challenges in a Former Military Base

Marina Coast Water District Regional Urban Water Augmentation Project Presented to: Presented by:

Michael Wegley, MCWD Jon Marshall, Carollo

May 14, 2019

Filename.ppt/2

Presentation Outline

  • MCWD and Project Overview
  • Former Fort Ord
  • Design and Construction Challenges
  • Lessons Learned
  • Construction Pictures (time permitting)
slide-2
SLIDE 2

2

Filename.ppt/3

Marina Coast Water District

  • Formed in 1960 to serve

the City of Marina

− Provided potable water supply and wastewater conveyance and treatment − In 1993 wastewater treatment transferred to a regional plant operated by MRWPCA (now M1W)

Filename.ppt/4

Marina Coast Water District

  • Formed in 1960 to serve

the City of Marina

− Provided potable water supply and wastewater conveyance and treatment − In 1993 wastewater treatment transferred to a regional plant operated by MRWPCA (now M1W)

  • In 2001 Fort Ord transferred

water/wastewater to MCWD

  • 8,000 connections with

40,000 residents

slide-3
SLIDE 3

3

Filename.ppt/5

Regional Urban Water Augmentation Project

  • Planning began in 2006

− Secondary treated and disinfected wastewater to MCWD customers − M1W concurrently planning advanced treated wastewater and groundwater injection

  • MCWD and M1W agreed to

combine projects in 2016

  • Startup of combined projects

planned for summer 2019

Filename.ppt/6

Regional Urban Water Augmentation Project

  • MCWD required recycled

pipelines with development

  • Each agency owns and
  • perates its facilities

− M1W

4.5 MGD pump station at the

regional treatment plant

Injection wells

− MCWD

7.5 mile conveyance main 2.0 MG reservoir 5+ miles of distribution

mains (in design)

slide-4
SLIDE 4

4

Filename.ppt/7

Regional Urban Water Augmentation Project

  • Combining projects

required design coordination

− MCWD’s booster pump station was eliminated to simplify system operation − Tie-in points − Testing and startup − Environmental and regulatory approvals

Filename.ppt/8

Regional Urban Water Augmentation Project

  • Funded through a

Proposition 1 SRF loan

− Cost sharing with M1W − Low Bid $22.6M

  • Bid opening July 2017,

NTP in August 2017

  • Substantially complete

January 2019

slide-5
SLIDE 5

5

Filename.ppt/9

Former Fort Ord

  • United States Army Post

established in 1917

  • Housed up to 50,000 troops
  • Trained mobile combat units

such as tanks, armored personnel carriers and movable artillery

  • Self contained water and

wastewater system

Filename.ppt/10

Former Fort Ord

  • Closure process began in

1989 and completed in 1994

  • Fort Ord Reuse Authority

(FORA) responsible for and reuse planning and property distribution to local agencies

  • MCWD began operating

water/wastewater system in 1994

− Ownership transferred to MCWD in 2001

slide-6
SLIDE 6

6

Filename.ppt/11

Challenges – Property Ownership

  • During design, property

was continually being transferred to local agencies

  • Created challenges

identifying the boundaries

  • f each agency
  • A long time local land

surveying firm was used to help establish ownership

− County mapping research − Local agency knowledge − Familiar with developments

Filename.ppt/12

Challenges – Property Ownership

  • General Jim Moore Blvd

− FORA constructed road improvements in 2003 − Land transferred from Army to Seaside − During construction, Seaside indicated it never accepted the road after construction − Army had no record of the land transfer, still owned − Add’l paving required per Army standard (v Seaside)

slide-7
SLIDE 7

7

Filename.ppt/13

Challenges – Property Ownership

  • General Jim Moore Blvd

Filename.ppt/14

Challenges – Military Munitions

  • History of munitions use was

well known during project planning

− FORA responsible for munitions removal

  • No work planned in locations

with potential unexploded

  • rdinance
  • Drawing review by FORA and

Army office to confirm work in areas cleared of munitions before construction

slide-8
SLIDE 8

8

Filename.ppt/15

Challenges – Military Munitions

  • Contractor attend Munitions

and Explosives of Concerns training

  • Restrict public access

(fencing and/or barricade)

  • Army approved monitor

present where excavation exceeds 2 feet

  • No munitions discovered

during construction

Filename.ppt/16

Safety training examples of ordnance found at Fort Ord

Challenges – Military Munitions

slide-9
SLIDE 9

9

Filename.ppt/17

Challenges – Tank Crossings

  • Throughout the Fort there

is a trail system for tanks

  • Maps of these locations

were not found, known from other past experience

  • n other projects
  • Some can be identified by

looking for them

  • Generally 3’ thick

unreinforced concrete road sections

Tank Crossing

Filename.ppt/18

Find the Tank Crossing

Challenges – Tank Crossings

Tank Crossing Tank Crossing

slide-10
SLIDE 10

10

Filename.ppt/19

Challenges – Tank Crossings

  • Found to be 4” of AC

above 1’ of concrete

  • Road section was saw cut
  • Some undermining of

road section occurred during trench excavation

  • Trench was backfilled

with slurry cement to fill voids

Filename.ppt/20

Challenges – Existing Utility Information

  • Fort Ord land transfers

included all utilities

− Water, wastewater, storm power, gas, comm. − No utility records − MCWD acquired water / wastewater infrastructure “as is, where is”

  • MCWD developed GIS

mapping

− Many alignment followed former base roads

slide-11
SLIDE 11

11

Filename.ppt/21

Challenges – Existing Utility Information

  • Strategies to identify and

mitigate utility conflicts

− Use local land surveyor − Potholing known / suspected crossings

130 potholes during

design (2007)

Required contractor to

pothole prior to commencing work

− Other utility owners performed review / signoff at each design stage

Filename.ppt/22

Challenges – Existing Utility Information

  • During construction 3

unidentified utilities found

− Fiber optic conduit installed without records − Sewer pipeline with a curved alignment − Storm drain pipeline with buried manholes

  • In each case, the pipeline

alignment / depth was modified to avoid conflict

slide-12
SLIDE 12

12

Filename.ppt/23

Challenges – Existing Utility Information

  • Required existing pipelines

to be pressure tested early in construction

  • Portion of the RUWAP

pipeline constructed in 2009 with CSUMB roadway improvement failed

  • Found that none of the

mechanical joint restraints (megalug) twist-off nuts had been turned

Filename.ppt/24

Challenges – Existing Utility Information

  • Fort Ord transferred an

existing 1.0 MG concrete tank to MCWD

− Tank was in poor condition with significant leakage − Structural cracking and safety concerns made the tank inaccessible − Design was to demolish the tank and rebuild a new 2.0 MG tank

slide-13
SLIDE 13

13

Filename.ppt/25

Challenges – Existing Utility Information

  • Approach to mitigating

unknowns for tank demolition

− Tested concrete for asbestos (negative) − Anticipated tank floor covered in coal tar mastic (not found) − Told Contractor to assume roof, wall, and slab thicknesses for bidding purposes

Filename.ppt/26

Tank Demolition

Challenges – Existing Utility Information

slide-14
SLIDE 14

14

Filename.ppt/27

Challenges – Existing Utility Information

  • Found the inlet / outlet

pipe (inside tank) asbestos cement

  • Roof, walls, and slab

thinner than Contractor told to anticipate

− Debris off-haul used to quantify credit

Filename.ppt/28

Challenges – Differing Agency Requirements

  • The project is located in

6 different agencies and private property

  • Biggest differences were

requirements for backfill, paving, and quality control testing

slide-15
SLIDE 15

15

Filename.ppt/29

Challenges – Differing Agency Requirements

  • Trench backfill

− Agency standards varied from no requirement to 95% compaction − Design goal was a uniform compaction requirement − Borings and lab analysis performed every 1,000’

Recommended 90%

compaction

− Agencies agreed because recommendations were site specific with lab data

Filename.ppt/30

Challenges – Differing Agency Requirements

  • Roadway paving

− Agency standards included repaving trench width, slurry seal half street, to mill and overlay entire street. − Paving requirements were not negotiable − Bid items were included for various types of paving

slide-16
SLIDE 16

16

Filename.ppt/31

Challenges – Differing Agency Requirements

  • Quality Control Testing

− Agency standards varied between Caltrans and ASTM − Carollo had additional req’s − Caused a challenge for the CM to practically implement QC testing − To provide consistency, a single set of tests was performed covering all req’s

Cross walk table created to

  • btain buy-in on testing

Filename.ppt/32

Challenges – Designing for High Pressure

  • Eliminating the booster

pump station simplified

  • peration, but created

areas with high (260 psi) pressure

  • Surge analysis

performed and control facilities limit maximum surge to below 300 psi

slide-17
SLIDE 17

17

Filename.ppt/33

Challenges – Designing for High Pressure

  • High Pressure Butterfly

Valves

− Rated to 350 psi − 45 week lead time − American Iron and Steel (AIS) created challenges

No domestic

manufacturer had a listed valve at the time

− Factory pressure testing was required and took additional time

Filename.ppt/34

Challenges – Designing for High Pressure

  • Pressure Testing

− Maximum 1 mile sections − Pressure depended on elevation of section

Up to 300 psi Components on the

appurtenances were the limiting factor

− Contractor had many concerns − Manufacturer of each component consulted − No issues with testing

slide-18
SLIDE 18

18

Filename.ppt/35

Challenges – Sandy Soil

  • Entire alignment underlain by

Stabilized Dune Deposits

  • Geotechnical Engineer wrote a

trenching evaluation supplemental report

− Talked with local Contractors − Reviewed projects in construction − Test pits and trenches − Contractor told that trench stability is unpredictable and to anticipate sloping

Filename.ppt/36

Challenges – Sandy Soil

  • Trench slope stable in some locations
slide-19
SLIDE 19

19

Filename.ppt/37

Challenges – Sandy Soil

  • Trench slope unstable in other locations

− Resulted in wide trench and pavement sections

Filename.ppt/38

Challenges – Sandy Soil

− Required wide spans of temporary utility support

Contractor used wide

flanged beams to allow for increased span length where needed

− No change orders submitted for trenching

slide-20
SLIDE 20

20

Filename.ppt/39

Challenges – Sandy Soil

  • Thrust restraint

− Soil bearing and friction capacity was difficult to estimate with confidence − Thrust blocks not practical for 24-inch pipeline − Pipeline designed as entirely self-restrained

American DIP selected by

Contractor

Flex Ring Joint specified

− Connections to MJ fittings used tandem restraints

Filename.ppt/40

Challenges – Sandy Soil

  • Cathodic Protection

− Corrosivity evaluation found soil to be mildly to non- corrosive − O&M preference not to install polyethylene wrap

Based on a past experience

finding a leak that travelled in the wrap

− To mitigate no wrap, a zinc coating was factory installed

  • n the pipeline
slide-21
SLIDE 21

21

Filename.ppt/41

Challenges – Sandy Soil

  • Trench dams

− Concern with potential for water to migrate in sandy trench section

From rain or other

utility breaks

− Called out in locations with steep slopes − Adjacent to large water pipelines

Filename.ppt/42

Challenges – Sandy Soil

  • Tank Over-Excavation

− Geotechnical concern for settlement beneath tank − Recommended 20 ft

  • ver excavation

− Native material removed and replaced

slide-22
SLIDE 22

22

Filename.ppt/43

Lessons Learned - Successes

  • US Army coordination for complying with

unexploded ordinance requirements,

  • Using a local land surveying company to establish

property boundaries and existing underground utility locations

  • Extensive potholing of existing utilities to confirm

their size and location

  • Where agencies have different requirements, use site

specific recommendations of a professional engineer (backfill compaction)

Filename.ppt/44

Lessons Learned – Opportunities

  • Continually confirming property ownership through

the project bidding with all agencies

  • During design, confirm the pavement sections of

areas that appear to be pedestrian crossings

  • Provide information on laterals which cannot be

located by USA and direction for the contractor to physically locate them

slide-23
SLIDE 23

23

Filename.ppt/45

Acknowledgements

  • Patrick Breen – MCWD, Project Manager
  • Jaron Hollida – MCWD, Assistant Engineer
  • Anne Prudhel – Carollo, Principal Engineer
  • Kathleen Mannion – Carollo, Engineer
  • Brian Jensen & Sam Hawkins – Stantec,

Construction Manager

  • Travis Headon – Mountain Cascade, Project Manager
  • Denise Duffy & Matt Johnson – Denise Duffy &

Associates, Environmental Compliance

Filename.ppt/46

Questions

slide-24
SLIDE 24

24

Filename.ppt/47

Construction Pictures

Filename.ppt/48

Construction Pictures

slide-25
SLIDE 25

25

Filename.ppt/49

Construction Pictures

Filename.ppt/50

Construction Pictures

slide-26
SLIDE 26

26

Filename.ppt/51

Construction Pictures

Filename.ppt/52

Construction Pictures

slide-27
SLIDE 27

27

Filename.ppt/53

Construction Pictures

Filename.ppt/54

Construction Pictures

slide-28
SLIDE 28

28

Filename.ppt/55

Construction Pictures

Filename.ppt/56

Construction Pictures

slide-29
SLIDE 29

29

Filename.ppt/57

Construction Pictures

Filename.ppt/58

Construction Pictures