Outage Management System Customer Partnership Group February 2018 Customer Partnership Group Scope and Objective Created in response to customers request to have more involvement in the planning, design and usability validation phases


slide-1
SLIDE 1

Outage Management System Customer Partnership Group February 2018

slide-2
SLIDE 2

Customer Partnership Group Scope and Objective

  • Created in response to customer’s request to have more

involvement in the planning, design and usability validation phases

  • f ISO application development
  • Provide an open interactive partnership forum to identify potential
  • pportunities to improve the overall customer experience
  • Share ideas, opinions and provide feedback
  • Discuss issues and concerns, and answer customer questions
  • All ideas are welcome and will be considered based upon feasibility,

prioritization and timeline constraints. Not all ideas may be feasible to implement

  • Meetings vary in frequency to review progress, provide feedback on

design and usability and discuss implementation approaches

  • Active participation is critical to the CPG success and to improve our

customer’s experience interacting with ISO applications

Page 2

slide-3
SLIDE 3

OMS Customer Partnership Group

Agenda

  • Schedule/roadmap update
  • Generation Outage Report discussion

Page 3

slide-4
SLIDE 4

OMS Customer Partnership Group

February Release

Page 4 Type of Change Short Description All Update to Version Comparison screen to fix word wrap functionality Generation Update to Version Comparison screen to fix missing MSG configuration data Generation MF ramp rate changes will only impact outages with “RAMP_RATE” Nature of Work. Generation Allow submission of overlapping AS outages. Generation Adding additional resource type for Generic Non-Generator Resource (NGRG) Generation Missing PMin validation when resource is Out of Service (OOS) Generation CIDI 196221 Technical issue accessing MSG resource data in the “Outage View” Generation Update B2B retrieve service to retrieve the RA Replacement ID tag Generation Incorrect Total Curtailment is showing after cancelling outage Transmission API issue with equipment where the RDFID changes but the Transmission Registry ID remains the same

slide-5
SLIDE 5

OMS Customer Partnership Group 2018 OMS Roadmap Ranking

Page 5

Summary

  • The CAISO is seeking participant feedback on a number of OMS

enhancements we hope to develop in the next few development cycles. Action

  • Provide rankings and any additional enhancement requests to Justin Wong

(jwong@caiso.com) by e-mail with the following header: 2018 OMS Roadmap Ranking

slide-6
SLIDE 6

OMS Customer Partnership Group Roadmap

Page 6

Roadmap Item Description Target Transmission/Generation: Broadcast version updates CAISO to broadcast when an outage is updated and a new version is created within the OMS system. TBD Transmission: Trumping Allows the system to apply the switch configuration of an outage if its priority trumps

  • ne or more existing outages.

TBD Generation: Overlapping PMIN Cards Allow overlapping PMIN rerates. TBD Generation: Overlapping NGR Outage Cards Allow Non-Generator Resources to submit

  • verlapping outage cards.

TBD Transmission/Generation: Recurring Outages Allow participants to submit and manage recurring outages. TBD

slide-7
SLIDE 7

OMS Customer Partnership Group

Generation Outage Report

Summary

  • The Generation Outage Report is currently posted daily at 3:15. A request

has been made to move this to the morning prior to 10:00 A.M. Action

  • Report will post at 8:30am beginning on 02/23/2018

Page 7

slide-8
SLIDE 8

Page 8

OMS Customer Partnership Group Wrap Up

  • Open Topics Q&A