OMI Novitiate, Godfrey, IL

1

slide-2
SLIDE 2

Participants

  • Fr. Art Flores, OMI

Vicar Provincial & Director of Personnel Owner Contact United States Province

Jasmine Azima, P.E., CxA

Principal-in- Charge – Jasmine Engineering

Coy L. Ballard, MLA

Project Manager – Jasmine Engineering

Sarah Sepulveda

Project Engineer – Jasmine Engineering 2

slide-3
SLIDE 3

3

RFQ For Architectural Design & Construction Administration Services Pre-Submittal Conference July 9, 2019 2:00 PM

slide-4
SLIDE 4

RFQ Timeline

4

July 9, 2019 at 2:00PM

Pre-Submittal Conference (Non-Mandatory) Location: OMI Area Office Second Floor Conference Room 323 Oblate Drive San Antonio, TX 78216

July 18, 2019 at 2:00PM

QUALIFICATION STATEMENTS DUE – Must be received at the OMI Area Office, 323 Oblate, San Antonio, TX 78216 no later than 2:00 PM on Thursday, July 18, 2019. Statements of qualifications must be submitted in a sealed envelope or box plainly marked: “OMI NOVITIATE – GODFREY RENOVATION, RFQ-001-Architectural Services: Design and Construction Administration.”

slide-5
SLIDE 5

5

Renovation of the historic Levis House and associated additions:

Original Levis Residence – c. 1916 2,440 GSF footprint – Basement + 2 stories Approximately 7,300 GSF total (Klipstein & Rathmann, Architects) Original Levis House Garage – c. 1916 1,610 GSF footprint Partial Second Floor (Klipstein & Rathmann, Architects) Addition and Hall – c.1926 320 GSF – 2 stories; 700 GSF Approximately Levis House Porch Addition – c. 1926 (Chester H. Walcott, Architect – 740 GSF Chapel / Library / Classroom Addition

  • c. 1959

1,425 – GSF footprint (approximately) 2 stories – Approximately 2, 855 GSF Bell Tower & Stair Addition – c. 1961 935 GSF footprint; 2 stories Approximately 1,870 GSF total (Architect: Leo Henry Track) Dormitory – c . 1958 – 1960 (To Be Demolished) 3,055 GSF footprint – 3 stories Approximately 9,165 GSF total (Architech: Leo Henry Track)

slide-6
SLIDE 6

Original Levis Residence – 1916

6

Renovation of the OMI Novitiate – Godfrey, to facilitate the operation and goals of the on-going Novitiate Program. The Novitiate is situated on a 256 acre tract of land overlooking the Mississippi River and surrounding landscape. The property was originally assembled by the Levis Family as “La Vista Estate.” Dating back to the early 20th Century when the Levis Family assembled the La Vista property for their estate, the site has been a natural and historic resource for the local community.

slide-7
SLIDE 7

Terrace Overlook - 1917

7

Since OMI’s involvement with the property beginning in 1950, OMI has continued the proud tradition caring for La Vista – adding to the important history of the site the use of the property and buildings by OMI as the Immaculate Heart of Mary Novitiate and other OMI programs and

  • activities. The tradition continues in the 21st Century under the stewardship and guidance OMI –

the Novitiate, Oblate Ecological Initiative, and the OEI Learning Center, La Vista.

slide-8
SLIDE 8

Levis House Porch Addition - 1927

8

slide-9
SLIDE 9

Chapel/Library/Classroom - 1959

9

slide-10
SLIDE 10

Dormitory Addition - 1958- 1960

10

To be demolished

slide-11
SLIDE 11

Bell Tower & Stair Addition - 1961

11

Connecting Chapel, Dormitory, Garage/ TV room

slide-12
SLIDE 12

12

General Information

  • The Owner will provide facility program for the Novitiate project to the

architectural firm selected by the Owner for services.

  • The delivery method for construction of this project will be Construction

Manager at Risk (CMAR).

  • The Owner has hired Jasmine Engineering, Inc. as the Owner’s Project

Representative & Commissioning Agent for the OMI Novitiate Renovation.

  • It is the Owner’s intent to higher an architectural firm for this project. The

Owner reserves the right to make no award in connection with solicitation.

slide-13
SLIDE 13

Point-of-Contact/Restriction on Communication:

Point-of-Contact/Restriction on Communication: The Owner designates the following person as its representative and Point-of-Contact for this RFQ. Respondents shall restrict all contact with the Owner and direct all questions regarding this RFQ, including questions regarding terms and conditions, to the Point-of-Contact person.

Note: Do not contact members of the Missionary Oblates of Mary Immaculate. Contact with any of these prohibited individuals after issuance of the RFQ and before selection is made, may result in disqualification of your Qualifications Statement.

Jasmine Azima ,P.E. , CxA Principal- in- Charge Jasmine Engineering, Inc. 115 E. Travis Street, Suite 1020 San Antonio, Texas 78205 PHONE (210) 227-3000 CELL (210) 669-1616 FAX (210)229-1999 E-mail: jasmine@jasmineengineering.com 13

slide-14
SLIDE 14
  • Renovations to existing upper, lower and Basement levels
  • f existing facility to accommodate the programming items.
  • Add a new elevator with small lobby additions to connect

the different floor levels of the existing facility.

  • Add interior ramps to provide wheelchair access to the main areas
  • f the facility.
  • Upgrade existing mechanical, electrical and plumbing.
  • Site improvements
  • Demolish the existing Dormitory Wing

14

Scope of Work

slide-15
SLIDE 15

15

Qualifications

REQUIRED:

  • Firms submitting statements for qualifications must be represented by a

professional Architect licensed to practice in the State of Illinois and be able to provide a professional Architect to attend meetings of any official nature concerning the Project, including but not limited to Scope of Meetings, Review Meetings, and other meetings as may be required for the Project. Firms submitting statements must have been in business for a minimum of 10 years. DESIRED:

  • Demonstrated firm experience in the design of high quality and cost-effective

renovation and addition projects involving existing historic or vintage facilities.

  • Strong team work ethic and cooperation both within the firm and outside the firm

with contractors, consultants, and Owner Representatives.

slide-16
SLIDE 16

16

Qualifications

  • Proven firm and/or team capable of providing creating, functional, flexible and

technologically sound design solutions with an economy of means and within the project budget.

  • Proven firm and/or team experience with sustainable design and construction, such as

completed project which incorporated energy conservation and energy efficient design solutions.

  • Proven firm and/or team experience with religious worship or retreat facilities.
  • Outstanding experience and reputation, based upon information provided by the

Respondent as well as information obtained by references; past experience of the Owner with the firm; past experience on similar projects for other clients; record for delivery of design documents within schedule, and other similar factors reflecting the experience and reputation of the Architect and its firm.

slide-17
SLIDE 17

17

Qualifications

  • Experienced and capable key personnel to be used on the project(s), including

principals of the firm and the proposed internal project manager.

  • Proven past experience on similar projects coordinated by an Owner’s Project

Representative

  • Proven past experience on similar projects using the Construction Manager at Risk

delivery method.

slide-18
SLIDE 18

18

Form of Qualification Statements

  • To achieve a uniform review process and obtain the maximum degree of

comparability, it is required that Statements of Qualification be organized in the manner specified.

  • Ten (10) sets of the Qualifications Statement are required.
  • (1) original copy labeled “ORIGINAL” and containing original signatures,

preferably in blue ink.

  • (9) Copies Marked “COPY”
  • Submitted in 3-ring binder or spiral wire or plastic binding with tab dividers.
  • Electronic PDF format on a USB drive.
  • Respondents are expected to examine this RFQ carefully, understand the terms and

conditions for providing the services listed herein and respond completely. FAILURE TO COMPLETE AND PROVIDE ANY OF THE REQUESTED ITEMS MAY RESULT IN THE RESPONDENT’S QUALIFICATIONS STATEMENT BEING DEEMED NON-RESPONSIVE AND THEREFORE DISQUALIFIED FROM CONSIDERATION.

slide-19
SLIDE 19

19

Form of Qualification Statements

TAB 1: COVER LETTER TAB 2: EXECUTIVE SUMMARY TAB 3: INFORMATION REGARDING SIMILAR WORK TAB 4: SERVICES TAB 5: PROJECT TEAM AND EXPERIENCE TAB 6: PAST LITIGATION AND CLAIMS HISTORY Please refer to SECTION 4 – FORM OF QUALIFICATION STATEMENTS for detailed descriptions of the required documentation that is to be submitted in each tab.

slide-20
SLIDE 20

20

Selection Criteria

  • Prior experience in connection with projects of a similar size and nature to the

Projects noted herein, commitment to quality, overall experience of the lead Architects assigned to this Project, reputation of the firm and past performance, including past litigation and claims associated with past projects.

  • Capability of the firm in the areas of support personnel, technical staff and the

spectrum of services to be offered to Owner.

  • The firm’s overall plan for meeting the Owner’s needs and requirements,

management ability and demonstrated ability to effectively serve its clients on prior projects/

  • Clarity and quality of Qualifications Statement and supporting data.
  • Resources and support services provided by the firm to the Owner.
slide-21
SLIDE 21

21

Award of Contract / Form of Contract

Award of Contract

  • The Owner reserves the right to reject any or all Qualifications Statements.
  • Based on the evaluation criteria, the Owner’s Committee will evaluate the Respondents

based solely on the qualifications of each Respondent.

  • The Owner’s Committee may elect to interview or receive presentations from one or

more of the Respondents prior to approval of the rankings, but will base its evaluation

  • n the same criteria set forth herein. (July 19, 2019 – July 26, 2019)

Form of Contract

  • The form of Architect Agreement utilized for this Project shall be the Standard Form of

Agreement Between Owner and Architect (AIA Document B133-2014) as amended by Owner.

  • The Architect will be required to provide administration of the Contract between the Owner and

the Contractor in AIA Document A201-2007, General Conditions of the Contract for Construction, as amended by Owner.

  • AIA Document B133-2014 (RFQ Exhibit D).
slide-22
SLIDE 22

Project Status:

  • Site Visits & On-Site Analysis
  • Facility Assessment
  • Several Options have been developed and reviewed by the
  • wner.
  • Facility Programming approved 04/23/19

22

slide-23
SLIDE 23

La Vista Estate Site

23

OMI Novitiate

slide-24
SLIDE 24

Dormitory Garage Carport La Vista, Walled Terraces Levis House Addition Terrace Overlook Classroom/Chapel/ Library Wing Footprint of Proposed Elevator and Lobby Addition PARTIAL SITE PLAN – NOT TO SCALE

24

slide-25
SLIDE 25

Functional Space Size of Each Space Location Quantity of Each Novice Rooms w/baths 4 - 174 S.F. 2 - 184 S.F. 2 -213 S.F. Lower and Mid Levels Levis House. 8 Formator Suites w/baths 3 - 250 S.F. Upper Level-Levis House 3 Guest Bedrooms w/baths 309 S.F. Upper Level-Levis House 1 Chapel 894 S.F. Upper Level

1 Space for 25 Occupants

Multi-Use Room/Classroom 680 S.F. Upper Level adjacent to Chapel

1

Sacristy 50 SF In Chapel

1

25

Program Elements: Functional Spaces Matrix

slide-26
SLIDE 26

Functional Space Size of Each Space Location Quantity of Each Spirit Rooms 1-97 S.F. 2- 48 S.F. Lower Level Levis House 3 Business office w/photocopy and Printer Area 365 S.F. Lower Level 1 Arts and Crafts/Music 315 S.F. Basement Level 1 W/Storage Storage Room/Work Room 272 S.F. Basement Level No Office Staff Lounge 496 S.F. Upper Level New Addition 1 Dining/Community Space 328 S.F. Lower Level Levis House 1 Ecological Learning Center 376 SF Lower Level 1 26

Program Elements: Functional Spaces Matrix - Continued

slide-27
SLIDE 27

Functional Space Size of Each Space Location Quantity of Each Dining Room/Kitchen 891 S.F Lower Level Levis House 1 Dining Space for 30 Occupants Laundry 170 S.F. Basement Level W/2 Washers and 2 Dryers TV/Recreation Room 974 S.F. Lower Level 1 Interior Circulation 640 SF Upper and Lower Levels 27

Program Elements: Functional Spaces Matrix - Continued

slide-28
SLIDE 28

Functional Space Size of Each Space Location Quantity of Each Mechanical Rooms 100 SF Upper and Lower Levels 4 Electrical Rooms 50 SF Upper and Lower Levels 4 Janitorial 25 SF Lower and Upper Levels 2 Carport/Paved Parking Cost for these items are included in the Construction Cost, Reference Statement of Probable Cost, Div. 32 – Site Improvements Outside Recreation Facilities Outdoor Prayer Grotto Outdoor Patio W/Fire BBQ Storage Shed Outdoor Focused Prayer Space 28

Program Elements: Functional Spaces Matrix - Continued

slide-29
SLIDE 29

MATCH LINE

OVERALL FLOOR PLAN – LOWER LEVEL – EXISTING RENOVATED WITH ELEVATOR & LOBBY ADDITION FOOTPRINT OF DORMITORY TO BE DEMOLISHED

COMMON AREAS

PUBLIC TOILETS BEDROOMS W/BATHS OFFICE AREAS UTILITY SPACES CIRCULATION

LEGEND FLOOR PLAN – OFFICE ABOVE E.L.C. EXISTING RENOVATED FLOOR PLAN – BASEMENT LEVEL EXISTING RENOVATED

29

slide-30
SLIDE 30

FOOTPRINT OF DORMITORY TO BE DEMOLISHED

PUBLIC TOILETS BEDROOMS W/BATHS

FLOOR PLAN –MID LEVEL BEDROOMS EXISTING RENOVATED

MATCH LINE

OVERALL FLOOR PLAN – UPPER LEVEL – EXISTING RENOVATED WITH ELEVATOR &,LOBBY ADDITION

COMMON AREAS

LEGEND

OFFICE AREAS UTILITY SPACES CIRCULATION

30

slide-31
SLIDE 31

31

  • EXIST. BLDG. RENOVATIONS & ELEVATOR ADDITION

2,373,138 $ 83,060 $ 15,425 $ 18,273 $ Owners Allowance 100,000 $ Owners Contingency 100,000 $ 316,758 $ 2,689,896 $ $210.94 CONSTRUCTION COST SUBTOTAL 0.65% 0.77% 5% of Construction Cost 5% of Construction Cost SQUARE FOOT COST TOTAL COST OF CONSTRUCTION SUB TOTAL Insurance Mark Up Bond 3.50%

Statement of Probable Cost

slide-32
SLIDE 32

Novitiate Renovation Timeline

  • JE Began Review of Existing Material

10/05/2018 thru 10/29/2018

  • Initial Site Visit to Survey Existing Facilities

10/30/2018

  • Programming Kick off Meeting

10/31/2018

  • Subsequent Site Visit & Local Code Authorities

11/02/2018 thru 01/07/2019

  • Present Programming to Committee

01/22/2019

  • Develop Programming (continues)

11/02/2018 thru 02/20/2019

  • Approval of the Programming by Committee

02/17/2019

  • Approval of the Final Programming

04/23/2019

  • Finalize Final Programming Report

04/24/2019 thru 05/28/2019

  • Distribution of Final Programming Report

05/30/2019

  • Preparation of RFQ for Architect

04/24/2019 thru 05/15/2019

  • Issue RFQ to Architects

06/24/2019 thru 07/18/2019

  • Pre-submittal Conference for Architects

2:00 PM - 07/09/2019

32

Revised 06/21/2019

slide-33
SLIDE 33

Novitiate Renovation Timeline

33

  • Architects’ Responses Due 2:00PM - 07/18/2019
  • Selection of the Architect by Committee 07/19/2019 thru 07/26/2019
  • Contract Negotiation between Architect & 07/29/2019 thru 08/12/2019

Project Manager

  • Review of the Architect’s Contract with Legal 08/13/2019 thru 08/27/ 2019
  • Execution of Architect’s Contract

08/28/2019

  • Notice to Proceed to the Architect

08/28/2019

  • Project Design Phases & Construction

08/29/2019 thru 05/29/2020 Documents Phase

  • Topo & SUE Survey

09/09/2019 thru 10/14/2019

  • Geotechnical Investigation 09/09/2019 thru 10/14/2019
  • Issue RFQ for Construction Manager

09/30/2019 thru 10/24/2019 At Risk (CMAR)

  • CMAR Qualifications Responses Due

2:00 PM – 10/22/2019

Revised 06/21/2019

slide-34
SLIDE 34

Novitiate Renovation Timeline

34

  • Issue RFPs to Shortlisted CMARs

10/24/2019 thru 11/13/2019

  • CMAR RFP Response Due

11/20/2019

  • CMAR Interviews

12/04/2019

  • Selection of CMAR

12/05/2019

  • CMAR Pre-Construction Services

12/09/2019 thru 05/29/2020

  • CMAR’s Guaranteed Maximum Price GMP

06/11/2020

  • GMP Negotiation between CMAR 06/12/2020 thru 06/19/2019

and Project Manager

  • GMP Approval by Committee

06/24/2020

  • Notice to Proceed to CMAR for Construction

06/25/2020

  • Substantial Completion of Construction

07/01/2021

Revised 06/21/2019

slide-35
SLIDE 35

Overall Project Concept

Guided at all times by OMI’s basic philosophies:

Journey of Discipleship… Spiritual Human Intellectual Pastoral

To achieve the established goals for the Novitiate…...

35

slide-36
SLIDE 36

Novitiate Goals:

 Create a quiet, contemplative setting for the prayerful nature of the experience of the Novitiate  Offer settings for community and solitude  Respect the environment and relate to nature  Create supportive, functional and efficient facility

36

slide-37
SLIDE 37

Thank You! Blessings!