GWENT LOCAL RESILIENCE FORUM
OLDBURY EXTENDIBILITY ARRANGEMENTS
IAN HARDMAN EMERGENCY PLANNING MANAGER MONMOUTHSHIRE COUNTY COUNCIL
SLIDE 2 BACKGROUND
EXISTING OLDBURY OFF-SITE PLAN FINDINGS FROM OFF-SITE EXERCISES REQUIREMENT FOR ENHANCED EXTENDIBILITY ARRANGEMENTS
SLIDE 3
AIM / SCOPE
OUTLINE CROSS BORDER COMMAND & CONTROL STRUCTURES REINFORCE EXISTING ARRANGEMENTS TO ENSURE RESPONSE AGENCIES IN THE GWENT LOCAL RESILIENCE FORUM CAN DEAL WITH AN OFF-SITE NUCLEAR INCIDENT ADDRESS COUNTERMEASURES THAT CAN BE IMPLEMENTED SET OUT ARRANGEMENTS FOR WARNING & INFORMING THE PUBLIC REVIEW IN LIGHT OF OLDBURY DECOMMISSIONING
SLIDE 4
RISKS
OVERALL RISK IS LOW ON-SITE RISKS DETAILED EMERGENCY PLANNING ZONE – IMMEDIATE OFF-SITE RISK - (1KM / 4KM) EXTENDIBILITY RISK - (OUT TO 15KM)
SLIDE 5 4km zone
15km Extendibility zone
OFF-SITE EXTENDIBILITY RISK
SLIDE 6
ACTIVATION
SLIDE 7
COMMAND & CONTROL
SLIDE 8
COUNTERMEASURES Within 15km Zone
SHELTER POTASSIUM IODATE TABLETS
SLIDE 9
WARNING & INFORMING THE PUBLIC
WARNING & INFORMING PLAN COMMUNICATIONS & MEDIA COORDINATING GROUP INFORMATION STRATEGY - NATIONAL & LOCAL KEY MESSAGES LEAD RESPONDER – AVON & SOMERSET CONSTABULARY & GWENT POLICE IMMEDIATE MESSAGE / MEDIA STATEMENT
SLIDE 10 RECOVERY PHASE
RECOVERY COORDINATING GROUP
HEALTH & WELFARE GROUP INFRA- STRUCTURE GROUP ECONOMIC & ENVIRON
GROUP COMMUNI
&
COMMUNITY
LIAISON
SLIDE 11
FUTURE OF THE SITE? DECOMMISSIONING NEW BUILD
SLIDE 12
QUESTIONS ?