OKI - SNK Workshop - March 8, 2016 Daniel Menetrey, P.E. Kentucky Transportation Cabinet District 6 Federal Funding Flow Reimbursement Process LPA pays for project first, then seeks reimbursement from KYTC. (80% reimbursement) LPA


slide-1
SLIDE 1

OKI - SNK Workshop - March 8, 2016 Daniel Menetrey, P.E.

Kentucky Transportation Cabinet District 6

slide-2
SLIDE 2

Federal Funding Flow

LPA

2

Reimbursement Process

LPA pays for project first, then seeks reimbursement from KYTC. (80% reimbursement)

(80%)

slide-3
SLIDE 3

Administering Office

KYTC District 6 Office

Administers State Funded Projects (SPP), and MPO (OKI)

delegated Federal Funds (SNK)

Daniel Menetrey – D6 LPA Coordinator

3

slide-4
SLIDE 4

Getting Started

Contact Administering Office

Get funds authorized Get MOA signed 20% local match required for all Federal Funds

4

Contact District LPA Coordinator

Schedule a Project Team Meeting early in the process Federal Funded Projects require an Environmental

Document to be completed

slide-5
SLIDE 5

Professional Services

Professional Services Procurement

QBS Process – Advertise for at least 21 days In House Staff Engineer on retainer contract Statewide Contracts – Contact Amanda Spencer

5

slide-6
SLIDE 6

Design

Design must follow KYTC Standards

Standard Drawings can be found on KYTC’s Highway

Design website

Submit all Plan submittals to the D.O. LPA Coordinator Traffic Management Plan (TMP) Design Review Checklist (LDRC)

6

slide-7
SLIDE 7

Right of Way & Utilities

Right of Way Certification required

Environmental Document is required before R/W can be

acquired

LPAs are required to follow the Uniform Act

Must be offered just compensation for their property If the value is less than $10,000 – Minor Acquisition Review

(MAR)

7

Utility Relocation

Contact Utility Companies early in project Provide to bidders Utility Impact Notes

slide-8
SLIDE 8

Utilities

8

slide-9
SLIDE 9

Construction Procurement

Construction Procurement Packet

LPA must obtain an Engineering Estimate from the Designer DBE Goal (Disadvantaged Business Enterprises) Bid Advertisement, Bid Proposal & Design Plans LDRC & LPA-PDC

9

Construction Notice to Proceed

Project Development Checklist (LPA-PDC) Funding Authorization & MOA for Construction

slide-10
SLIDE 10

Project Letting

LPA must advertise for at least 21 days before the bids are

  • pened

Contract is to be awarded to the lowest responsive bidder Contractor must be prequalified with KYTC (List found

  • n KYTC’s website)

Send bid tabs to Administering Office (AO) Have contractor sign contact Notice to proceed from AO

10

slide-11
SLIDE 11

Construction & Inspection

LPA must inspect the contractor’s work Inspector must be onsite at some time every day Verify that DBEs working on the project Inspector must give a copy of all inspection reports to the

LPA

Inspector or contractor must do materials testing

11

slide-12
SLIDE 12

Construction & Inspection

Inspector helps LPA determine whether milestones are met

for progress payments

LPA is required to promptly pay the contractor LPA must notify the AO when the project is completed for

Final Inspection and Acceptance & Project Closure

Change Orders

12

slide-13
SLIDE 13

Reimbursement

Costs directly related to the project are reimbursable LPA pays project expenses up front, then submits a

request for reimbursement from Administering Office

Use Reimbursement Request Form Include contractor invoices & cancelled checks (front and

back)

LPA will be reimbursed 80% (Fed Funded)

13

slide-14
SLIDE 14

Completed SNK LPA Projects

14

Newport Carothers Road (KY 1892) Reconstruction

slide-15
SLIDE 15

Completed SNK LPA Projects

15

Covington Russell Street Resurfacing

slide-16
SLIDE 16

Completed SNK LPA Projects

16

Covington Caroline Ave Railroad Underpass

slide-17
SLIDE 17

Completed SNK LPA Projects

17

Covington – Latonia & Southern Ave Reconstruction (SNK)

slide-18
SLIDE 18

Current SNK LPA Projects

Covington

6th Street Reconstruction Riverfront Commons Trail (multi-city project) Latonia Avenue Reconstruction Johnson Street & Rivercenter Blvd Reconstruction

18

Edgewood

Dudley Road Reconstruction (Phase II & III)

Newport

Carothers Road Reconstruction (Phase II) Riverfront Commons Trail Bridges

slide-19
SLIDE 19

Current SNK LPA Projects

Crestview Hills

Thomas More Parkway Widening

19

Kenton County

Bromley Crescent Springs Road Reconstruction (Phase I & II)

Villa Hills

Buttermilk Pike Reconstruction

Ludlow

Riverfront Commons Trail

slide-20
SLIDE 20

Current SNK LPA Projects

Kenton County Airport Board

Wendell Ford Boulevard Extension

Boone County

Longbranch Road Widening Camp Ernst Road Turn Lane at Longbranch Road Veterans Way Extension

20

slide-21
SLIDE 21

Questions?

http://transportation.ky.gov/Pages/default.aspx