NSW Plumbing and Drainage Regulations National Backflow Prevention - - PowerPoint PPT Presentation

nsw plumbing and drainage regulations
SMART_READER_LITE
LIVE PREVIEW

NSW Plumbing and Drainage Regulations National Backflow Prevention - - PowerPoint PPT Presentation

NSW Plumbing and Drainage Regulations National Backflow Prevention Conference 28 th July 2016 Key topics for discussion are; Plumbing and drainage regulation in NSW Consistent regulation approach Codes and Standard Licensee


slide-1
SLIDE 1

NSW Plumbing and Drainage Regulations

National Backflow Prevention Conference 28th July 2016

slide-2
SLIDE 2

Key topics for discussion are;

 Plumbing and drainage regulation in NSW  Consistent regulation approach  Codes and Standard  Licensee responsibilities  Point of connection  Alternative Solution  How to keep up to date

slide-3
SLIDE 3

Regulation in NSW

Under the Plumbing and Drainage Act 2011, and the Plumbing and Drainage Regulation 2012,

  • Fair Trading is the single plumbing and drainage regulator for NSW
  • Fair Trading conduct on-site Plumbing and Drainage inspections in the Sydney,

Illawarra, Blue Mountains and parts of the Hunter area (properties serviced by either Hunter or Sydney Water)

  • Outside these areas Fair Trading have delegated regulatory powers to local

Council/County Councils

  • All requirements of the Act are enforced, as such the work must:
  • be carried out only by authorised persons
  • be supported with correct paperwork to the regulator and the owner
  • comply with the Plumbing Code of Australia.
slide-4
SLIDE 4

Consistent Regulation Approach

The introduction of a single plumbing regulator for NSW, implemented a consistent regulatory approach such as;

  • 1. Introduction of Plumbing Code of Australia (PCA) volume 3 of the National

Construction Code 2016, replacing the NSW Code of Practice

  • 2. Removal of local requirements
  • 3. Consistent approach to interpretation of codes and standards
  • Technical notes
  • Inspector forum
  • Enewsletter
  • 4. Clarification of the point of connection, consistency across NSW
  • 5. Consistent approach to administrative requirements
slide-5
SLIDE 5

CODES AND STANDARDS

slide-6
SLIDE 6

Current Codes and Standards

Plumbing Code of Australia 2016 Volume 3 of the National Construction Code AS/NZS 3500 National Plumbing and Drainage Standard 2015 edition was adopted in May this year Part 1 Water Services Part 2 Sewer Part 4 Hot Water Critical Note: - In NSW Part 3 Stormwater is regulated under the Local Government Act

  • Part 5 Domestic Installations Does Not Apply in NSW
slide-7
SLIDE 7

Current Codes and Standards cont.…

Note: The NSW Code of Practice is no longer enforced by the plumbing regulator for onsite plumbing and drainage work. The following Clause is no longer enforceable by the plumbing regulator. 2.2.9 Cross-connection control and backflow prevention devices 3) The maintenance and testing of backflow prevention devices shall be carried out only by authorised persons, who are accredited to carry out testing procedures. The accredited person shall ensure that backflow testing gauges/test units are certified every year by a qualified instrument maker and details are affixed to the test unit.

slide-8
SLIDE 8

LICENSEE’S RESPONSIBILITY

slide-9
SLIDE 9

Licensee’s responsibilities

It is the licensee responsibility to:

  • Ensure the appropriate Inspection fee have been paid
  • Book the appropriate inspections
  • Submission of paper work;
  • Notice of Work must be submitted at least two working days prior to starting work.
  • Sewer Service Diagram (SSD) submitted on completion of the drainage works to the

inspector or within 7 working days if no inspector attends the site.

  • Certificate of Compliance (COC) submitted on completion of the Final inspection to

the inspector or within 7 working days if no inspector attends the site.

slide-10
SLIDE 10

Standard Documents

Notice of Work (NoW) Regulator Copy only – Blue Certificate of Compliance (CoC) Regulator Copy – Olive Licensee’s Copy – Green Owners Copy – Lime Note: copies produced through MyInspections are not coloured

slide-11
SLIDE 11

Sewer Service Diagrams

A Sewer Service Diagram (SSD) must be supplied to the PIAS inspector at the time of the final drainage inspection, as per the requirements of the NSW Plumbing and Drainage Act 2011

slide-12
SLIDE 12

POINTS OF CONNECTION

slide-13
SLIDE 13

Point of Connection – Water Supply

Ground Level Water Meter Backflow Prevention Device Isolation Valve Garden Tap to premises Property Boundary Potable Water Main Recycled Water Main Recycled Meter Isolation Valve to accepted fixtures only Backflow Prevention Device Recycled Tap Vacuum Breaker

Property Service Water Service

Ground Level

Point of Connection @ Outlet of Meter Point of Connection @ Outlet of Meter

Main Tap Main Tap

Produced by Fair Trading Plumbing Inspection and Assurance Services May 2013

slide-14
SLIDE 14

Point of Connection – Rainwater Tank

Property Boundary Rain Water Tank

From Roof Catchment

Pump Optional Potable Interconnection With Backflow

Point of Connection

Produced by Fair Trading Plumbing Inspection and Assurance Services May 2013

slide-15
SLIDE 15

Point of Connection - Sewer

Property Boundary Sewer Main

Upstream Vent IO IO IO IO IO IO IS TR WC WC BTH SHR FWG S Drain Overflow Relief Gully Drain Legend FWG = Floor Waste Gully IO = Inspection Opening IS = Inspection Shaft S = Sink SHR = Shower TR = Trough WC = Water Closet BTH = Bath IO IO

Sewer Service

Drain

Point of Connection a) Point of Connection b)

Produced by Fair Trading Plumbing Inspection and Assurance Services May 2013

slide-16
SLIDE 16

Trade Waste - Roles and Responsibilities

Property Boundary

Overflow Relief Gully Upstream Vent Arrestor Vent Trade Waste Vent Trade Waste Drainage Pre Treatment Device (Grease Arrestor) Boundary Trap

IPMF

Sanitary Drainage Fixtures Trade Waste Fixtures

IO IO IO IO IO IO

Point of Connection (Sanitary Drainage) Outlet from Pre-Treatment Device Inlet to Pre-Treatment Device

NUO FT/PIAS

REGULATED BY

Produced by Fair Trading Plumbing Inspection and Assurance Services May 2013

slide-17
SLIDE 17

Alternative Solution

  • Under the PCA, industry has the option of installing plumbing and drainage work

under an Alternative Solution.

  • The use of an alternative solution will require planning, research and

documentation by the applicant. The applicant will need to ensure that it complies with all parts of the PCA as required by Section A. For full details go to Fair Trading web site Guideline for plumbing and drainage: Installing Code Compliant Work and Alternative Solutions

  • All proposed alternative plumbing or drainage solutions are to be sent to Fair

Trading, Plumbing Inspection Assurance Service (PIAS), Technical Support for an initial review of the information provided and must be made via email or in an electronic format (large files can be provided on digital media);

  • Email to be sent to PCA@finance.nsw.gov.au
slide-18
SLIDE 18

This is not an example of an alternative solution

slide-19
SLIDE 19

Keeping up to date with the changes

www.fairtrading.nsw.gov.au Click on tradespeople Click on plumbing

AND

Register to ‘Keep Up To Date’

slide-20
SLIDE 20

Contact Details

Email - piasstrategy@finance.nsw.gov.au Senior Project Officer Shane Dalton Email – shane.dalton@finance.nsw.gov.au 0418121982