NPCC VISIT THE POWER SYSTEM OPERATOR OF PAKISTAN National Power - - PowerPoint PPT Presentation

npcc visit
SMART_READER_LITE
LIVE PREVIEW

NPCC VISIT THE POWER SYSTEM OPERATOR OF PAKISTAN National Power - - PowerPoint PPT Presentation

SAARC TRAINING FOR PROFESSIONALS OF AFGHANISTANS POWER REGULATORY SYSTEM NPCC VISIT THE POWER SYSTEM OPERATOR OF PAKISTAN National Power Control Centre Presented by: Salman Gul Deputy Manager NPCC National Transmission and Despatch


slide-1
SLIDE 1

SAARC TRAINING FOR PROFESSIONALS OF AFGHANISTAN’S POWER REGULATORY SYSTEM

NPCC VISIT

slide-2
SLIDE 2
slide-3
SLIDE 3

National Transmission and Despatch Company Ltd.

THE POWER SYSTEM OPERATOR OF PAKISTAN

National Power Control Centre

Presented by:

Salman Gul

Deputy Manager NPCC

slide-4
SLIDE 4

INTRODUCTION TO NPCC

 National

Power Control Center (NPCC) is part

  • f

National Transmission and Despatch Company (NTDC) which is a corporate entity unbundled from WAPDA power wing

 NTDC

constructs,

  • perates,

maintains primary transmission network (i-e 500,220 kV transmission lines & 500/220 kV grid stations), provides wheeling facility to CPPA-G for purchase of power from generators and selling to DISCOs

 DISCOs construct, maintain secondary transmission network (i-e

132,66 kV transmission lines & 132/11 kV grid stations) and 11/0.4 kV distribution system

 NPCC is responsible for operation, monitoring of generation , both

primary and secondary transmission system and coordination with all Power sector stake holders (i-e MOE, NTDC head and field offices, DISCOs, GENCOs, CPPA-G & IPPs

slide-5
SLIDE 5
slide-6
SLIDE 6
slide-7
SLIDE 7

MD NTDC DMD (P&E) General Manager (SO) Chief Engineer (Op’n Planning) Manager PPC Chief Engineer (Network Op’n) Manager Power Control Manager RCC-N Manager RCC-S Manager Database

NPCC-Employees Yardstick Total Employees : 389

slide-8
SLIDE 8

SYSTEM OPERATION HIERARCHY

  • Generation Control
  • Switching & Operating

Control of 500 & 220 kV Network Switching & Operation of 132 & 66 kV Southern Network

RCCS

(Regional Control Centre South) Jamshoro

Switching & Operation of 132 & 66 kV Northern Network

RCCN

(Regional Control Centre North) Islamabad

NCC

(National Control Centre)

slide-9
SLIDE 9

OBJECTIVES OF NPCC

➢ Reliability & Security of power system

  • Smooth Supply
  • Minimum Interruptions

Quality of Electric Power Supply

  • Standard Voltage and Frequency

➢ Safety

  • Personnel.
  • Equipment.

➢ Economy

  • Minimum Generation Cost
  • Minimum Losses
slide-10
SLIDE 10

MAJOR FUNCTIONS OF NPCC

  • 1. National Power Control Centre, commonly known as

NPCC, is the nerve centre of Power Sector. Entire power generation and its transmission to the load centres is controlled and coordinated from its National and Regional Control Centres. 2. Maintaining balance between Supply & Demand. 3. Frequency , voltage control and equipment loading within permissible limits.

  • 4. Maintaining security & stability of network.
slide-11
SLIDE 11

MAJOR FUNCTIONS OF NPCC

  • 6. Month-wise & Annual Energy Estimation.
  • 7. Economic Dispatch.
  • 8. Switching operations of Power Network.
  • 9. Scheduling of maintenance shut-downs on power-

plants & Transmission network elements. 10.Short to medium term operational planning.

  • 11. Advance notifications to thermal plants regarding

energy (Year Ahead, Quarter Ahead, Week Ahead and Day Ahead).

  • 12. Collection of system data and preparation of reports
slide-12
SLIDE 12

ADMINISTRATIVE FUNCTION

 NPCC is headed by General Manager (System Operation)

in main NPCC Building Islamabad.

 GM

(SO) is assisted by Chief Engineer (Network Operation) & Chief Engineer (Network Planning).

 GM(SO) reports and coordinates with all Stakeholders

regarding Power system.

 NPCC is a control and command body and for smooth

  • peration of system, pass-on instructions to GENCOS,

IPPs, DISCOs and Hydro Stations from its Control rooms which function round the clock in 3 shifts with Shift Engineers on duty.

slide-13
SLIDE 13

SYSTEM OPERATION & CONTROL

slide-14
SLIDE 14

NPCC CONTROL ROOM

slide-15
SLIDE 15

PRESENT OPERATIONAL STRATEGY

 System Security and Reliability are issues of top priority

  • nature. This is a technical urgency recognized by utilities

all over the world and may demand out of merit operation

  • f some of the generating units in the system.

 The provision of spinning reserve is equal to the 1/3rd of

the one biggest generator capacity in system according to grid code.

 500 and 220 KV transmission lines/ transformers are

  • perated with single contingency compliance.

 Thermal Generators are dispatched in order of economic

merit order considering security and stability of system.

 Hydel, Nuclear, REs (Wind, Solar) are operated as must

run

slide-16
SLIDE 16

Security Constrained Economic Dispatch

Merit Order Plant Avail.

Congestion and Losses Fuel Avail. & Contracts Ramping Rates Startup / down Decision Stability, Reserves Etc…

slide-17
SLIDE 17

GENERATION PLANNING & DESPATCH

Procedure and steps.

 Demand forecasting/estimation on historical trends  Generation forecasting/estimation keeping in view:

➢ Irrigation indents of Hydel stations ➢ Schedule outages ➢ Forced outages ➢ Weather/ Season. ➢ Special Events. ➢ Constraints if any

 Dispatch of available thermal generation as per merit order.

slide-18
SLIDE 18

OPERATIONAL CONSIDERATIONS FOR DISPATCH (PLANNED)

 System Stability.  Transmission/ Transformation constraints.  Reactive power support for regulating system voltages.  Planned and scheduled shutdowns on a)

Transmission Lines

b)

Transformers.

c)

Generating Plants.

 Limitations on No. of starts of steam turbines.  Testing of generating Plants.

slide-19
SLIDE 19

OPERATIONAL CONSIDERATIONS FOR DISPATCH (UN-PLANNED)

 Change in Water indents.  Change in Gas quota allocations.  Load restrictions on generating plants.  Tripping of equipment/ Major Outages.  Difference in Forecasted and actual load due to

abrupt weather change.

 Reactive

power support for regulating system voltages.

slide-20
SLIDE 20

NEPRA GRID CODE

slide-21
SLIDE 21

NEPRA GRID CODE

Operation of power system regulated

under NEPRA’s Grid Code

 OC-1 : General operating principles  OC-2 : Demand Forecast

Input from all stakeholders for different time

horizons consolidated by NPCC

 OC-3 : Demand Management

slide-22
SLIDE 22

NEPRA GRID CODE

 OC-4: Operational Planning

Network

  • peration

and

  • utage

planning/ coordination

Generation dispatch and outage coordination Insufficient power operating margin Frequency and voltage control and operating

margins

slide-23
SLIDE 23

NEPRA PERFORMANCE LIMITS

 Frequency  Frequency Sensitive Mode (Normal Range)

49.8-50.2 Hz

 Contingency Frequency Band (Load Shedding Threshold)

49.4-50.5 Hz

 Voltage  N-0 Contingency

N-1 Contingency

+8 % and -5 %

± 10 %

slide-24
SLIDE 24

TRANSMISSION OPERATION & CONTROL

Operational objectives of NPCC are:

  • Keeping balance between demand and supply all

the time

  • Maintaining stable frequency
  • Maintaining system security and reliability
  • Keeping stable voltages over primary network
  • Monitoring of transmission & transformer

parameters

slide-25
SLIDE 25

SWITCHING OPERATIONS

NPCC performs switching operation on transmission network in following scenarios:

  • Planned shutdowns for maintenance, cleaning and

washing activities

  • Emergent shutdowns in case of abnormal situations.
  • Transmission lines and transformers tripping.
  • 132 kV switching for optimal configuration of radial

network

slide-26
SLIDE 26

GENERATION MIX

slide-27
SLIDE 27

GENERATION SOURCES

ABSTRACT OF POWER PLANTS

Generation Type

INSTALLED CAP AS PER LICENCE (MW) DERATED CAPACITY (MW) NO OF UNITS

TOTAL WAPDA HYDEL (22)

9,387 9,387 97

IPP HYDEL (5)

382 379 18

TOTAL HYDEL (27)

9,770 9,767 115

GENCO-I (3)

1,174 860 14

GENCO-II (3)

2,457 1,552 17

GENCO-III (4)

2,051 1,765 17

TOTAL GENCO (10)

5,682 4,177 48

IPP-THERMAL (37)

17,166 15,883 210

NUCLEAR (4)

1,345 1,246 4

SOLAR (4)

400 400 4

WIND (24)

1,235 1,235 718

TOTAL VRE'S (28)

1,635 1,635 722

BAGASSE (9)

363 353 13 TOTAL PLANTS (115) 35,961 33,060 1,112

slide-28
SLIDE 28

GENERATION SOURCES (Derated Capacity)

Type Derated Percentage Share MW %age Total Hydel (Wapda + IPPs)

9,767 29.5%

Gencos Fossil Fuel

4,177 12.6%

IPPs Fossil Fuel

15,883 48.0%

Bagasse

353 1.1%

Nuclear

1,246 3.8%

Solar

400 1.2%

Wind

1,235 3.7%

Total

33,060 100.0%

slide-29
SLIDE 29

BREAKUP OF MAX RECORDED GENERATION DURING PEAK HOURS

22,601 MW on 04 Sept 2019 Wapda-Hydel 7,937 Gencos 2,290 IPPs 12,374 Total 22,601

slide-30
SLIDE 30

23,056 MW on 04 July 2019 @ 14:18 Hours

ABSOLUTE MAX RECORDED GENERATION DURING 24 HOURS

slide-31
SLIDE 31

LOAD MANAGEMENT

slide-32
SLIDE 32

GENERATION / DEMAND BALANCE

SYSTEM FREQUENCY = 50 HZ

GENERATION

DEM EMAND

The primary function of NPCC is to keep balance between demand and supply & to ensure system security and

  • reliability. In balanced condition system frequency is 50 Hz.
slide-33
SLIDE 33

GENERATION / DEMAND BALANCE

SYSTEM FREQUENCY < 50 HZ DEM DEMAND AND

GENERATION

When demand exceeds generation, frequency depreciates below 50 Hz and in order to maintain balance between demand and generation, load management has to be carried out.

slide-34
SLIDE 34

GENERATION DEMAND BALANCE

Load is continuously varying in time and so the generation has to be varied in order to keep frequency in permissible limits

Variation in generation

  • Hydel (Fastest ramping rates)
  • Thermal
  • Steam Turbines
  • Gas Turbines
  • DG Sets
slide-35
SLIDE 35

GENERATION DEMAND BALANCE

In case of deficit in generation capacity, balance between demand and generation has to be maintained through load management

Therefore a multi tier strategy has been adopted for this balance through load management

Scheduled load management

System security load management

Emergency (Forced) Load Management

slide-36
SLIDE 36

36

SCHEDULED LOAD MANAGEMENT

Scheduled load management is carried out by DISCO’s, keeping in view the following factors.

 Load demand of respective DISCO.  Generation share allocated to DISCO by NPCC.  Constraints like voltage drop, transmission and

transformer loading including 11 kV & below system.

slide-37
SLIDE 37

37

SYSTEM SECURITY LOAD MANAGEMENT

➢ Under Voltage, Under Frequency & Cross Trip

Protection schemes have been installed for System Security Load Management

slide-38
SLIDE 38

EMERGENCY LOAD MANAGEMENT

Emergency load management (Forced LS) is carried out by NPCC by opening 132kV transmission lines in case

  • f extreme system emergencies.

Examples are:

1.

Un-foreseen generating unit outages

2.

Non implementation of schedule load management by DISCOs

3.

Rupturing of gas lines

4.

Non availability of fuel

5.

Sabotage activities on transmission lines

6.

Transmission and transformation problems

slide-39
SLIDE 39

MERIT ORDER

slide-40
SLIDE 40

MERIT ORDER APPROVAL COMMITTEE

 Power Plants are operated on the basis of Despatch Merit

Order which is approved by a committee of the following members.

 General Manager (SO) NPCC, Convener.  General Manager (PSP) NTDC, Member.  Chief Technical Officer CPPA-G, Member.  Chief Financial Officer CPPA-G, Member.  Chief Technical Officer GENCO, Member.

 Standard Operating Procedure SOP exists for the process of

preparing and revision of merit order for operation of power plants.

slide-41
SLIDE 41

PROCEDURE OF MERIT ORDER FORMATION

➢Procedure

1) Chief Technical Officer CPPA-G will intimate the revised

applicable fuel prices and variable O&M Cost fortnightly in respect of Gencos and IPPs Plants comprising of the following components: i) Fuel Price, ii) Calorific value of fuel, iii) Net Heat Rate, iv) Variable O&M cost, v) Index Premium, vi) Ratio of fuel mix gas and furnace oil, vii) Environment Consideration, viii) Utilization of local gas and RLNG. ix) International contract by GoP for purchase of RLNG. 2) On receipt of information from CTO CPPA-G, office of GM (SO) NPCC shall consolidate/ prepare the revised merit order and put up immediately to all merit

  • rder

committee members for final approval.

slide-42
SLIDE 42

IMPLEMENTATION OF MERIT ORDER

 As per Clause SDC 1.4.3.2 of NEPRA Grid Code, NPCC

always operates the plants without any discrimination. Cheaper plants take the lead in despatching. In prevailing situation of shortfall of power in the country, most of the time in the year, all available plants have to be operated and therefore question of any discrimination of despatch does not arise.

 However during short period of lean demand ,Merit order is

strictly followed by NPCC keeping in view the technical constraints of Gencos along with voltage transmission issues if any.

 Plants under annual maintenance outages according to

planned programs and hydel generation drops during lean period of system demand.

slide-43
SLIDE 43

OPERATION PLANNING

slide-44
SLIDE 44

OPERATION PLANNING

Pre Dispatch Functions

 Annual Production Plan  Calculation of future fuel requirements  Year/Quarter/Month/Week Ahead Planning

Post Dispatch Functions

 Event/NPMV Verification  Liquidated Damages  Operating Committees

slide-45
SLIDE 45
slide-46
SLIDE 46

CLOSING REMARKS

BY GM NPCC