npcc visit
play

NPCC VISIT THE POWER SYSTEM OPERATOR OF PAKISTAN National Power - PowerPoint PPT Presentation

SAARC TRAINING FOR PROFESSIONALS OF AFGHANISTANS POWER REGULATORY SYSTEM NPCC VISIT THE POWER SYSTEM OPERATOR OF PAKISTAN National Power Control Centre Presented by: Salman Gul Deputy Manager NPCC National Transmission and Despatch


  1. SAARC TRAINING FOR PROFESSIONALS OF AFGHANISTAN’S POWER REGULATORY SYSTEM NPCC VISIT

  2. THE POWER SYSTEM OPERATOR OF PAKISTAN National Power Control Centre Presented by: Salman Gul Deputy Manager NPCC National Transmission and Despatch Company Ltd.

  3. INTRODUCTION TO NPCC  National Power Control Center (NPCC) is part of National Transmission and Despatch Company (NTDC) which is a corporate entity unbundled from WAPDA power wing  NTDC constructs, operates, maintains primary transmission network (i-e 500,220 kV transmission lines & 500/220 kV grid stations), provides wheeling facility to CPPA-G for purchase of power from generators and selling to DISCOs  DISCOs construct, maintain secondary transmission network (i-e 132,66 kV transmission lines & 132/11 kV grid stations) and 11/0.4 kV distribution system  NPCC is responsible for operation, monitoring of generation , both primary and secondary transmission system and coordination with all Power sector stake holders (i-e MOE, NTDC head and field offices, DISCOs, GENCOs, CPPA-G & IPPs

  4. MD NTDC NPCC-Employees Yardstick Total Employees : 389 DMD (P&E) General Manager (SO) Chief Engineer Chief Engineer (Network ( Op’n Op’n ) Planning) Manager Manager Manager Manager Manager PPC Database Power Control RCC-N RCC-S

  5. S YSTEM O PERATION H IERARCHY NCC (National Control Centre) • Generation Control • Switching & Operating Control of 500 & 220 kV Network RCCN RCCS (Regional Control Centre North) (Regional Control Centre South) Islamabad Jamshoro Switching & Operation of 132 & 66 Switching & Operation of 132 & 66 kV Northern Network kV Southern Network

  6. O BJECTIVES OF NPCC Reliability & Security of power system ➢ o Smooth Supply o Minimum Interruptions Quality of Electric Power Supply ➢ Standard Voltage and Frequency o ➢ Safety Personnel. o Equipment. o ➢ Economy Minimum Generation Cost o Minimum Losses o

  7. MAJOR FUNCTIONS OF NPCC 1. National Power Control Centre, commonly known as NPCC, is the nerve centre of Power Sector. Entire power generation and its transmission to the load centres is controlled and coordinated from its National and Regional Control Centres. 2. Maintaining balance between Supply & Demand. 3. Frequency , voltage control and equipment loading within permissible limits. 4. Maintaining security & stability of network.

  8. MAJOR FUNCTIONS OF NPCC 6. Month-wise & Annual Energy Estimation. 7. Economic Dispatch. 8. Switching operations of Power Network. 9. Scheduling of maintenance shut-downs on power- plants & Transmission network elements. 10.Short to medium term operational planning. 11. Advance notifications to thermal plants regarding energy (Year Ahead, Quarter Ahead, Week Ahead and Day Ahead). 12. Collection of system data and preparation of reports

  9. A DMINISTRATIVE F UNCTION  NPCC is headed by General Manager (System Operation) in main NPCC Building Islamabad.  GM (SO) is assisted by Chief Engineer (Network Operation) & Chief Engineer (Network Planning).  GM(SO) reports and coordinates with all Stakeholders regarding Power system.  NPCC is a control and command body and for smooth operation of system, pass-on instructions to GENCOS, IPPs, DISCOs and Hydro Stations from its Control rooms which function round the clock in 3 shifts with Shift Engineers on duty.

  10. S YSTEM O PERATION & C ONTROL

  11. NPCC C ONTROL R OOM

  12. P RESENT O PERATIONAL S TRATEGY  System Security and Reliability are issues of top priority nature. This is a technical urgency recognized by utilities all over the world and may demand out of merit operation of some of the generating units in the system.  The provision of spinning reserve is equal to the 1/3 rd of the one biggest generator capacity in system according to grid code.  500 and 220 KV transmission lines/ transformers are operated with single contingency compliance.  Thermal Generators are dispatched in order of economic merit order considering security and stability of system.  Hydel, Nuclear, REs (Wind, Solar) are operated as must run

  13. Merit Order Stability , Plant Reserves Avail. Etc … Security Constrained Economic Startup / Dispatch Congestion down and Losses Decision Fuel Avail. Ramping & Rates Contracts

  14. G ENERATION P LANNING & D ESPATCH Procedure and steps.  Demand forecasting/estimation on historical trends  Generation forecasting/estimation keeping in view: ➢ Irrigation indents of Hydel stations ➢ Schedule outages ➢ Forced outages ➢ Weather/ Season. ➢ Special Events. ➢ Constraints if any  Dispatch of available thermal generation as per merit order.

  15. O PERATIONAL C ONSIDERATIONS FOR D ISPATCH (P LANNED )  System Stability.  Transmission/ Transformation constraints.  Reactive power support for regulating system voltages.  Planned and scheduled shutdowns on Transmission Lines a) Transformers. b) Generating Plants. c)  Limitations on No. of starts of steam turbines.  Testing of generating Plants.

  16. O PERATIONAL C ONSIDERATIONS FOR D ISPATCH (U N -P LANNED )  Change in Water indents.  Change in Gas quota allocations.  Load restrictions on generating plants.  Tripping of equipment/ Major Outages.  Difference in Forecasted and actual load due to abrupt weather change.  Reactive power support for regulating system voltages.

  17. NEPRA GRID CODE

  18. NEPRA G RID C ODE  Operation of power system regulated under NEPRA’s Grid Code  OC-1 : General operating principles  OC-2 : Demand Forecast  Input from all stakeholders for different time horizons consolidated by NPCC  OC-3 : Demand Management

  19. NEPRA G RID C ODE  OC-4: Operational Planning  Network operation and outage planning/ coordination  Generation dispatch and outage coordination  Insufficient power operating margin  Frequency and voltage control and operating margins

  20. NEPRA PERFORMANCE LIMITS  Frequency  Frequency Sensitive Mode (Normal Range)  49.8-50.2 Hz  Contingency Frequency Band (Load Shedding Threshold)  49.4-50.5 Hz  Voltage  N-0 Contingency N-1 Contingency  +8 % and -5 % ± 10 %

  21. T RANSMISSION O PERATION & C ONTROL Operational objectives of NPCC are: • Keeping balance between demand and supply all the time • Maintaining stable frequency • Maintaining system security and reliability • Keeping stable voltages over primary network • Monitoring of transmission & transformer parameters

  22. SWITCHING OPERATIONS NPCC performs switching operation on transmission network in following scenarios: • Planned shutdowns for maintenance, cleaning and washing activities • Emergent shutdowns in case of abnormal situations. • Transmission lines and transformers tripping . • 132 kV switching for optimal configuration of radial network

  23. G ENERATION M IX

  24. GENERATION SOURCES ABSTRACT OF POWER PLANTS INSTALLED CAP AS DERATED Generation Type CAPACITY (MW) NO OF UNITS PER LICENCE (MW) 9,387 9,387 97 TOTAL WAPDA HYDEL (22) 382 379 18 IPP HYDEL (5) 9,770 9,767 115 TOTAL HYDEL (27) 1,174 860 14 GENCO-I (3) 2,457 1,552 17 GENCO-II (3) GENCO-III (4) 2,051 1,765 17 5,682 4,177 48 TOTAL GENCO (10) 17,166 15,883 210 IPP-THERMAL (37) 1,345 1,246 4 NUCLEAR (4) 400 400 4 SOLAR (4) 1,235 1,235 718 WIND (24) 1,635 1,635 722 TOTAL VRE'S (28) 363 353 13 BAGASSE (9) TOTAL PLANTS (115) 35,961 1,112 33,060

  25. GENERATION SOURCES (Derated Capacity) Derated Percentage Share Type MW %age Total Hydel 9,767 29.5% (Wapda + IPPs) Gencos Fossil Fuel 4,177 12.6% IPPs Fossil Fuel 15,883 48.0% Bagasse 353 1.1% Nuclear 1,246 3.8% Solar 400 1.2% Wind 1,235 3.7% Total 33,060 100.0%

  26. BREAKUP OF MAX RECORDED GENERATION DURING PEAK HOURS 22,601 MW on 04 Sept 2019 Wapda-Hydel 7,937 Gencos 2,290 IPPs 12,374 Total 22,601

  27. ABSOLUTE MAX RECORDED GENERATION DURING 24 HOURS 23,056 MW on 04 July 2019 @ 14:18 Hours

  28. L OAD M ANAGEMENT

  29. GENERATION / DEMAND BALANCE The primary function of NPCC is to keep balance between demand and supply & to ensure system security and reliability. In balanced condition system frequency is 50 Hz. SYSTEM FREQUENCY = GENERATION DEM EMAND 50 HZ

  30. GENERATION / DEMAND BALANCE When demand exceeds generation, frequency depreciates below 50 Hz and in order to maintain balance between demand and generation, load management has to be carried out. SYSTEM FREQUENCY < 50 HZ GENERATION DEM DEMAND AND

  31. G ENERATION D EMAND B ALANCE Load is continuously varying in time and so the  generation has to be varied in order to keep frequency in permissible limits Variation in generation  Hydel (Fastest ramping rates) • Thermal • Steam Turbines • Gas Turbines • DG Sets •

  32. G ENERATION D EMAND B ALANCE In case of deficit in generation capacity, balance  between demand and generation has to be maintained through load management Therefore a multi tier strategy has been adopted  for this balance through load management Scheduled load management  System security load management  Emergency (Forced) Load Management 

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend