Northern Line Extension Battersea Community Liaison Group 21 November 2019 1 1 # Actio ion Upda Update Ens nsur ure hi historical CLG m minut nutes This action is in progress and the target is to get website up to 1 and pres an


  1. Northern Line Extension Battersea Community Liaison Group 21 November 2019 1 1

  2. # Actio ion Upda Update Ens nsur ure hi historical CLG m minut nutes This action is in progress and the target is to get website up to 1 and pres an esen entat ations ar are e date by early December upload aded t to t the e TfL web ebsite PM1 0 an and PM2.5 d dust lev evel els 2 Update in today’s presentation for t the B e Bat atter ersea ea site Number er o of veh ehicle e movem emen ents r rel elat ating t to t the e 3 Update in today’s presentation NLE projec ect since e the s e star art o of cons nstruc uction i n in n 201 5 Regular independent monitoring shows that the levels and content of dust in LU’s infrastructure are within Health & Safety Whe hethe her TfL woul uld m moni nitor Executive limits (HSE). Monitoring shows that dust levels are the ai e air qual ality at y at Bat atter ersea ea well below the HSE workplace exposure limits for general dust 4 and nd othe her U Und nderground und (4 mg/m3 ). We also aim to achieve the stricter requirements of stat ations, once t e the s e ser ervice e is the Institute of Occupational Medicine to limit exposures to oper erat ational al respirable dust to below 1 mg/m3, and meet this target at the majority of locations Dat ates es for the n e nex ext f few ew These have been held January; April; July; October 5 Bat atter ersea C ea CLG meet eetings - Is this the right frequency? Should we make them every four circulat ate e to t the C e CLG months instead? Regular reminders are provided to the NLE team on Loit iterin ing outsid ide S Sain insbury’s - maintaining the highest behavioural standards. We expect our 6 rai aised ed at at t the s e site’ e’s reg egular ar team to uphold these high standards and to act as ambassadors ‘T ‘Toolbox’ m ’ meetings for FLO, TfL and the construction industry generally Sen end M May ay H a a copy o y of the e Could not see whether this action was completed so copy sent 7 pres esen entat ation today. Apologies for the delay (if this was not actioned)

  3. 2

  4. Battersea Power Station: Progress Update November 2019 3

  5. Battersea Power Station: Progress Update November 2019 4

  6. Battersea Power Station: Progress Update November 2019 Major Milestone Achieved early November with the handover of the Western Ramp land to Battersea Developers. Within the Western Ramp Structure Fans and large ductwork installed. 5

  7. Battersea Power Station: Progress Update November 2019 Internally • Finishes and Platforms starting to take shape. • Ongoing cladding/finishes , station system and railway systems fit out 6

  8. Battersea Power Station: Progress Update November 2019 Battersea Recognised by The Considerate Constructors Scheme as Excellent . The Team have achieved over 2million man hrs without a reportable injury. 7

  9. Environmental Monitoring Locations Noise Monitoring stations and sensitive receptors 8

  10. BT Monitoring Noise monitoring 9

  11. Environmental Monitoring Locations Glass slide locations 10

  12. BT Monitoring Dust slides results 11

  13. Complaints & Enquiries Summary Stats for Battersea between 16 July and 21 November 2019 Case Status: 3 cases • Active: 0 (0%) • Resolved: 3 (100%) 12

  14. Community Engagement and NLE Skills and Employment Look ahead : we will be supporting a business breakfast event at Sacred Heart 3 students completed work experience on the project from Southwark- 2 from Sacred Heart 1 from St Thomas the Apostle 4 site tours – 2 from St Thomas 2 from Sacred Heart 1 meet the professional event at the Southwark Construction Centre 1 Dragons den activity – Landsdowne school ( Lambeth) 13

  15. Ways to contact us • It is important that calls are logged through the NLE 24/7 helpdesk on 0343 222 2424 (Option 1) • Email nle@tfl.gov.uk • Drop In sessions • Please visit: https://tfl.gov.uk/northern-line-extension 14

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.