Network Code Forum 30 October 2013 CACM & FCA Network Codes - - PowerPoint PPT Presentation

network code forum
SMART_READER_LITE
LIVE PREVIEW

Network Code Forum 30 October 2013 CACM & FCA Network Codes - - PowerPoint PPT Presentation

Network Code Forum 30 October 2013 CACM & FCA Network Codes Mark Lane CACM update 29 October - Cross Border Committee meeting Still no text from EC Key Issues: Enforceability Timelines Intraday Governance


slide-1
SLIDE 1

Network Code Forum

30 October 2013

slide-2
SLIDE 2

CACM & FCA Network Codes

Mark Lane

slide-3
SLIDE 3

CACM update

  • 29 October - Cross Border Committee

meeting

  • Still no text from EC
  • Key Issues:
  • Enforceability
  • Timelines
  • Intraday
  • Governance
  • ENTSO-E working on CACM Early

Implementation (e.g. CCR, CGM, EMF, BZ)

slide-4
SLIDE 4

FCA update

  • 1 October - Network Code submitted to ACER
  • 28 October - ACER Workshop in Lubljana
  • 8 November – Trilateral meeting
  • Early December – ACER Opinion expected
  • Key issues:
  • Firmness & Revenue Adequacy
  • Harmonised Allocation Rules & Single Allocation Platform
  • Capacity Calculation
  • Other work: e.g. Firmness, HAR, Multiannual

Products, Buyback

slide-5
SLIDE 5

Electricity Balancing Network Code

Conor Kavanagh

slide-6
SLIDE 6

6 Months 12 Months 3 Months > 12 Months Framework Guidelines Drafting Internal Approval Public Consultation Updating Internal Approval ACER Opinion Comitology Process …. Scoping Development Approval

NC Electricity Balancing Timeline

7 November 30 October 5 September

slide-7
SLIDE 7

Detailed Steps in the approval process

17 June Public Consultation Start 17 July Public Workshop 16 August Public Consultation End 16 October Release of NC EB v1.30 23 October Public Workshop 7 November Start of internal approval End December Submission to ACER

slide-8
SLIDE 8

ENTSO-E Drafting Team Activity Post Consultation

Review of Public Comments Consolidate comments by article Article by article redraft New versions

  • f NC EB

ACER comments Drafting Team Open Issues

Current Activity

slide-9
SLIDE 9

Information available

  • Material from ENTSO-E Stakeholder workshop

can be found on:

  • https://www.entsoe.eu/major-projects/network-

code-development/electricity-balancing/

slide-10
SLIDE 10

Balancing Process

slide-11
SLIDE 11

Public Consultation - Summary

  • The Public Consultation on the draft Network Code on Electricity Balancing closed
  • n 16 August.
  • 2178 comments received
  • ~144 All-island on 44 of 62 articles on 28 main topics
  • Most public comments concerned Procurement of Balancing Services, Settlement

and General Balancing Principles

slide-12
SLIDE 12

NC EB topics for round table discussions

Formation and Evolution of CoBAs and Targets Products and Gate Closure Times Procurement and Activation of Energy and Reserves Cross Zonal Capacity Reservation Settlement Central Dispatch Systems

slide-13
SLIDE 13

CoBAs & Targets

Main concerns were:

Scope of a CoBA cooperation Improved reference to targets Introduction of intermediate targets

slide-14
SLIDE 14

Coordinated Balancing Area (CoBA)

  • FWGL gives a clear obligation to TSOs:
  • “TSOs are responsible for organising balancing

markets and shall strive for their integration […]”

  • Obligation to cooperate in procurement of Balancing

Energy, however, FGWL do not stipulate by who and how this is done before the target model is implemented, nor how cooperation is established for the Exchange of Reserves  Proposed solution: Coordinated Balancing Area

slide-15
SLIDE 15

New structure for target (1 of 2)

  • Applicability
  • Deadline to implement the intermediate

(regional) model

  • Basics of the intermediate (regional)

model

  • Implementation plan for the intermediate

(regional) model

slide-16
SLIDE 16

New structure for targets (2 of 2)

  • Possibility to modificate the target

(European) model

  • Basics of the target (European) model
  • Implementation plan for the target

(European) model

  • Deadline to implement the target

(European) model

slide-17
SLIDE 17

Products & Gate Closure Times

The main concerns were:

Improve clarity between standard & specific products. Earlier definition of standard products Gate Closure Times are not clear

slide-18
SLIDE 18

Reserve and Energy Products

TSO to balance the system

Standard products Specific products

ENTSO-E wide Defined Characteristics fixed or by range TSO Defined Should be preferably used

If does not match with all needs OR does not allow wide ressources participation

Shared within a CoBA Use as an exception Shared only if SoS is not compromised Respect LFCR & DFD requirements Possible to converted by the TSO

Standard vs Specific Products

slide-19
SLIDE 19

Procurement & Activation

The main concerns were:

14 November 2013 | Page 19

Procurement should be based on market based methods only. Long term contract should not be allowed or should be conditioned by NRA approval TSO-BSP model should be allowed until a “full TSO-TSO model” is implemented Different views on pricing method of balancing energy

slide-20
SLIDE 20

Overview of high-level changes

– Differentiation between Procurement of Balancing Reserves

  • within a Responsibility Area
  • within a Coordinated Balancing Area (CoBA)

– Rename: „Transfer of Obligation“ to „Transfer of a Balancing Capacity“ – Procurement period – TSO-BSP model

slide-21
SLIDE 21

Cross Zonal Capacity

14 November 2013 | Page 21

Need for clarifications, improved definitions and better consistency with other codes Reservation of Cross Zonal Capacities should be prohibited Allocation of Cross Zonal Capacities should be prohibited

The main concerns were:

slide-22
SLIDE 22

Ensuring available CZC for Exchange of Balancing Capacity

  • r Sharing of Reserves

Probabilistic Approach (art. 32) Reservation (art. 38)

Exchange and Sharing of Balancing Services requires available Cross Zonal Capacity

Co-optimisation process (art. 40) Market based reservation process (art. 41.) Socio economic analyses (art. 42) Available CZC for exchange

  • f Balancing Energy

(art. 44) Available after intra day GCT Reserved Available after intra day GCT Reserved

slide-23
SLIDE 23

Settlement

Marginal Pricing. Some stakeholders want to enforce a single price system while others suggest a dual price system with reference to a day ahead price The use of the concept Relevant Area. Many stakeholders suggest to use Bidding Zones in line with NC CACM Settlement Responsibility. The possibility of delegation of Imbalance Settlement to another entity should be enlarged.

The main concerns were:

slide-24
SLIDE 24

Bidding Zone CC/CA Region Internal Energy Market

consists of (one or more) is sub- area of

Synchronous Area LFC Block LFC Area Monitoring Area Scheduling Area

consists of (one or more) (sub) area of consists of (one or more) (sub) area of consists of (one or more) (sub) area of consists of (one or more) (sub) area of consists of (one or more) (sub) area of consists of (one or more) (sub) area of consists of (one or more) (sub) area of consists of (one or more) (sub) area of

Imbalance Price Area Imbalance Volume Area

Area Definitions

slide-25
SLIDE 25

All-island Considerations

a) Synchronous Area Ireland reserve processes & product requirements. b) Balancing after one hour Cross Zonal Intraday Gate Closure Time c) All-island commercial & other aspects d) Balancing in Central Dispatch Systems e) Priority Dispatch f) DS3 System Services g) Ramp Rate Process and product definition with HVDC connection h) BETTA market, Elexon and National Grid engagement. i) DSOs coordination.

slide-26
SLIDE 26

Next steps in the approval process

23 Oct 3rd Public Workshop 24 Oct -1 Nov ENTSO-E Legal review 1 Nov -7 Nov Preparation of final NC EB version 7 Nov -14 Nov ENTSO-E Market Committee Approval 19 Nov -3 Dec ENTSO-E Assembly Approval 31 Dec Submission of NC EB and Supporting Document to ACER

slide-27
SLIDE 27

Operations Network Codes

Glen Flanagan (Operations Engineer, SONI)

slide-28
SLIDE 28

OPS NC overview

  • Data for Operational Security analysis in Operational

Planning

  • Operational Security Analysis in Operational Planning
  • Outage Coordination
  • Adequacy
  • Ancillary Services
  • Scheduling
  • ENTSO-E Operational Planning Data Environment
slide-29
SLIDE 29

Operational Planning and Scheduling, drafting up-date

  • ENTSO-E received ACER’s opinion on OPS NC 19th

July

  • Drafting team, Acer & EC to work together on re-draft
  • Re-drafted by and resubmitted to Acer 24th Sept
  • Acer’s opinion expected soon.
slide-30
SLIDE 30

Timelines for implementation of OPS NC

Article Articles with extended implementation dates; Article 12 Year-Ahead Common Grid Models (6 months after entering into force) Article 19 Methodologies for coordinating Operational Security Analysis (12 months after entering into force) Article 21 Definition of Outage Coordination Regions (15 months after entering into force) Article 23 Methodology for assessing relevance of assets for the Outage Coordination Process (12months after entering into force) Article 24 List of Self-Planned Interconnectors, Relevant Power Generating Modules and Relevant Demand Facilities (15months after entering into force) Article 27 List of Relevant Grid Elements (15months after entering into force) Article 58 General provisions for ENTSO-E Operational Planning Data Environment (24months after entering into force)

slide-31
SLIDE 31

NC OS

  • Stakeholder information session held on 16/9 in

Brussels

  • Internal ENTSOE approvals complete on 23/9
  • Code resubmitted to ACER on 24/9
  • EC Pre Comitology meeting on 29/10
  • Time available to influence change is rapidly

running out at a minimum review Data Exchange Chapter in NC OS

slide-32
SLIDE 32

NC LFCR

  • Positive ACER opinion with three recommendations:

– Sharing of FCR between Synchronous Areas (currently only allowed between SAs IRE and GB) – The Recitals (7) with regard to National Scrutiny (corrected in the most recent version of the Recitals) – The minimum time period of 30 minutes for full activation of continuous FCR (not an issue for SAs IRE and GB)

  • Code now goes to the EC for Comitology
  • EC Pre Comitology meeting on 29/10
  • Time available to influence change is rapidly running out

at a minimum review “NC EB and NC LFCR All-Island Workshop 01-08-13 – Additional Info on NC LFCR” At www.eirgrid.com/europeanaffairs/networkcodes/

slide-33
SLIDE 33

Connection Network Codes

Mark Norton

slide-34
SLIDE 34

Update on Connection Codes

  • Ongoing discussions with EC, driven by KEMA report recommendations
  • Prepare response and changes for comitology in the coming months to

reflect Kema report once fully reviewed

  • Preparation of implementation guidelines of requirements into National Law

DT RfG

  • Ongoing discussions with EC, no equivalent KEMA report for DCC
  • Preparation of implementation guidelines of requirements into National Law
  • Analysis of how and what Europe-wide DSR SFC implementation should be
  • Continuing discussion with SEDC (European assoc. of demand aggregators) to

come to a joint statement on Demand Side Response meeting Nov 7th 2013 DCC

slide-35
SLIDE 35

DT HVDC – general planning

2013 2014

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul

  • Call for Stakeholder Input
  • Drafting NC HVDC
  • Consultation on draft code
  • Finalizing NC HVDC

ENTSO-E publication User Group meeting Public workshop

EC mandate (12 months)

Draft NC to User Group

ACER EC Prep.

14 November 2013 | Page 35

slide-36
SLIDE 36

User Group meetings

slide-37
SLIDE 37

HVDC Solutions in Europe Global challenges and local system needs

Interconnection Ration reflects the % interconnection capability compared to installed power capacity for each country.

  • 1. To connect two or more Synchronous

Areas (SA) to each other. The HVDC link is considered a significant grid user at all connection points.

  • 2. To provide a transfer capability inside

a single synchronous area, called embedded HVDC. The parallel operation

  • f the HVDC with HVAC can

encompassing a single TSO control area

  • r 2 or more control areas.
  • 3. To connect remote generations to the

main AC network. The HVDC connection may or may not be part of the generation facility.

The interconnection with HVDC can be realized in three different ways:

slide-38
SLIDE 38

NC HVDC General Approach

  • Capability of HVDC systems relevant for cross border system security
  • Its inherent capabilities, e.g. fast active and reactive power control,

supplementary control, etc…, support the EU’s energy goals.

  • HVDC connected grid users complement those of generation and demand.
  • Capability of DC connected PPMs and remote end HVDC converter
  • HVDC system in combination to PPMs could bring economic benefits
  • Coordination between capabilities of HVDC system and PPMs
  • Coping with different technologies
  • Requirements should not favour a specific technology
  • Considering potential future DC grids
  • Requirements for HVDC connections and DC connected PPMs should not

be a barrier to future expansion into multi-terminal or meshed DC grids

slide-39
SLIDE 39

Applications of HVDC and DC connected PPMs

Power Park Module(s) AC collected and DC connected to the main electricity system

HVDC connections embedded within one control area HVDC connections between synchronous areas or between control areas including back to back Connection Point(s) HVDC connections between AC collected PPMs and the main electricity system

How to consider TSO-owned HVDC embedded into one control area

  • treated as a significant grid user
  • compliance to HVDC CC
  • compliance simulation
  • compliance testing
slide-40
SLIDE 40

General requirements in HVDC code

slide-41
SLIDE 41
  • DC connected PPMs and remote end HVDC converters need to have

economic consistent coordinated requirements so as not to impair requirements at AC onshore transmission connection point

  • Requirements cover the secure operation of such DC connected AC

collection grids for critical situations inside the AC collection (changes in power flow as required by the mainland side, disturbances, disconnection of one ore more DC connections, …)

  • DC connected PPMs
  • Reference to RfG with possible variation in ranges and settings
  • Remote end HVDC converters
  • Reference to HVDC CC Art. 8 … 36 with possible variation in

ranges and settings

Requirements for DC connected PPMs and remote end HVDC converters

slide-42
SLIDE 42

DC connected PPM development

Power Park Module(s) AC collected and DC connected to the main electricity system

Connection Point(s) HVDC connections between AC collected PPMs and the main electricity system HVDC connections may become DC connected to another synchronous electricity system

Other 3rd party Power Park Module(s) AC collected

AC connection in parallel with HVDC connection to AC collected PPMs

slide-43
SLIDE 43

DC connected PPM development – Characteristics

DEEL111 WYLL111 PENL111 M ULLINGAR ENNIS TURLOUGH HILL THURLES
  • ON-
HILL GILRA ARVA KINNEGAD BALLYBEG NENAGH ARDNACRUSHA CHARLESLAND BALLYRAGGET ORIO211 CKM C111 HUNC111 BALC111 WOOC111 M AYC111 LAOC111 BA1C211 WEM B111 CASTLEBAR GALWAY LANESBORO CLOON IKERRIN DALTON CAM US TYNAGH FLAA111-411 CASA111-411SHAA111-411 OLDB111-411 M ONB111-2 1 1 KELC111 WHRW211

LAMF111 CHEF111

PEWL111 DRX NORTHERN IRELAND ISL0211 WS10211 WS20211 WS50211 ARG0211 WS40211 WS30211 FAGH111 FWIH111 BRDH111 WIG0211 SOL0211 SU4O211 GRNH111 HUTL111 HUSL211 SU8O211 M ANQ211 SU7O211 SHANKILL CUNGHILL BUNBEG TIEVEBRACK SRANANAGH * KIN0211 OM AD111-21 1 STRD211 COLD211 M AGD211 TURD111-211 CACD211 KELD211 BAFD211 TAND211 LOUA211 BALA211 LETA111-41 1 CATA111-411 SLIA111-41 1 BELA111-211
  • 41
1 HAND211 GOLA111-411 WIRW211 WJNW211 WKNW211 MORH211-111 MOSH111-211 PET STEJ111 H QUEL111 THTK1 NURN111 TRAL111 CASL211 PEMM111 BR2O211 ALVN111 INDN111 LAGN111 ABHN111 EXTN111 SWAM111 WALM111 SCIN211 WIWO211 DOON M ALLOW CHARLEVILLE BANDON DUNM ANWAY BRINNY DUNGARVAN KILB111-211 KILBARRY OUGHTRAGH TRALEE CLASHAVOON CULLENAGH TIPPERARY KILLONAN GLENLARA CROSS PROSPECT COOM AGEARLAHY CLAHANE COOM ACHEO BVKB111 WF5O211 GLAO211 KNOB111 AGHB111 KN1B111-41 1 TARB111-21 1 WGRW211 TORH111 STSJ111 DASH211-221 HUEH111-221 AUCH211-221 DOUH211-221 MYBH211-221 INVH111 BEAH111-211 M D1B111-2 11 TRIA111-411 ENND111-411 TASB111-21 1 CAML111 TREL111 LEGL111 AV1W211 AV3W211 AV2W211 OUGB211 CROB211 AF4W211 AF3W211 AF2W211 AF1W211 CAHC111

PLHF111

CHIN111 M YSH211 HARJ111 BR1O211 HUSL212 HAM L211 FORH113 NEAH111 FARH111 BELH111 COCH111 SU5O211 SU6O211 WNAO211 WALO211 WDUO211 WJ1O211 WF1O211 WF2O211 WLAO211 ARKC111 GREC111 LODC211 WF3O211 CODO211 SU1O211 WF4O211 SU2O211 ARKO211 PESM 212 COOD211 SRAA111-411 KIAC111 CAVA111-211 DUNC111 WJ2O211 KISO211 FORH111 WIAO211

NSCOGI/ EirGrid study

  • AC connections may become DC and vice versus
  • DC connected PPMs may become node in

interconnection between synchronous systems

  • AC and DC connections should be interchangeable
  • DC connected PPMs will have low inertia and be more

volatile

  • DC connected PPMs will be required to contribute

system services into the network which they are providing power to

10,000 20,000 30,000 40,000 50,000 60,000 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Synchronous Inertia (MW s) Percentage of hours in the year

Inertia Duration Curves

Inertia 2010 Inertia 2020
slide-44
SLIDE 44

Thanks for your attention

slide-45
SLIDE 45

Frequency requirements for DC connected PPMs and convertors

  • PPMs/convertors to be relied upon must be resilient to

reasonable frequency variations

  • The PPM requirement is proposed to be in line with RFG as DC

connected offshore generation may become AC connected Why is it needed in the NC HVDC?

  • HVDC PPMs shall be capable of staying connected to the Network

and operating within pre-defined frequency ranges and time periods compatible with AC connected as DC may become AC connected and retrofitting is practically impossible

  • Network (Convertors) must be last to disconnect, proposed

consistent with any other convertor requirements What does it aim to achieve?

  • HVDC PPMs may become AC connected and if not DC connected

AC connector network should at least be consistent with AC connected equivalents Important to note:

10 July 2013 | Internal NC HVDC Workshop | Page 45

slide-46
SLIDE 46

ROCOF requirements for DC connected PPMs and convertors

  • Offshore PPMs/convertors are small isolated networks which

may experience high changes in ROCOF

  • Reliance on generation requires reasonable resilience of
  • ffshore network
  • Reliance of station as a link to other synchronous systems for

system services and power transfer requires reasonable resilience of offshore network Why is it needed in the NC HVDC?

  • Retain AC collector networks, and PPMs for reasonable

ROCOF What does it aim to achieve?

  • ROCOF is averaged over 500mS time period not 500mS after

fault

  • PPM manufacturers believe 2Hz/sec for 500mS is achievable

Important to note:

10 July 2013 | Internal NC HVDC Workshop | Page 46

slide-47
SLIDE 47

FSM/LFSM requirements for DC connected PPMs and convertors

  • FSM/LFSM strategy is for entire network not just synchronous

connected

  • Frequency response should be in sync with network which AC

collector network is feeding into

  • DC link should be capable of transferring power in this situation
  • Fast communication of frequency response in less than 1 second

Why is it needed in the NC HVDC?

  • Ensure DC connected PPMs can contribute to entire network

frequency response What does it aim to achieve?

  • AC collector networks may be also transferring power from

remote synchronous network via AC collector network

  • DC connected PPMs could become AC connected

Important to note:

10 July 2013 | Internal NC HVDC Workshop | Page 47

slide-48
SLIDE 48

Voltage requirements for DC connected PPMs and convertors

  • PPMs/convertors to be relied upon must be resilient to reasonable

voltage variations

  • The PPM requirement is proposed to be in line with RFG as DC

connected offshore generation may become AC connected

  • Convertor requirements will be in line with other AC connected

convertors Why is it needed in the NC HVDC?

  • HVDC PPMs shall be capable of staying connected to the Network and
  • perating within pre-defined voltage ranges and time periods

compatible with AC connected as DC may become AC connected

  • Network (Convertors) must be last to disconnect, proposed consistent

with any other convertor requirements What does it aim to achieve?

  • Voltage in DC connected PPMs is likely to be more volatile
  • HVDC PPMs may become AC connected and if not DC connected AC

connector network should at least be consistent with AC connected equivalents Important to note:

10 July 2013 | Internal NC HVDC Workshop | Page 48

slide-49
SLIDE 49

Reactive power requirements for DC connected PPMs and convertors

  • Reactive strategy is required for AC collector network
  • As many parties maybe connected to offshore point , reactive

requirements should be on all users not just convertor – non- discriminatory

  • PPM reactive power range consistent with RfG due to possible

future configurations

  • Without PPMs the convertor[s] should be able to regulate voltage

Why is it needed in the NC HVDC?

  • Ensure DC connected PPMs can contribute to regulate voltage for

AC collector network

  • Future proofed for network development and contingency

What does it aim to achieve?

  • DC connected PPMs could become AC connected
  • A number of circuits maybe connected to one station
  • Do we make an exception to ‘dedicated’ DC connections?

Important to note:

10 July 2013 | Internal NC HVDC Workshop | Page 49

slide-50
SLIDE 50

Synchronising requirements for DC connected PPMs and convertors

  • Transient voltages are minimised during

synchronising of convertors into a DC connection Why is it needed in the NC HVDC?

  • Connecting convertors into DC connected PPMs does

not create voltage related disturbances or cascading

  • utages

What does it aim to achieve?

  • DC connected PPMs could become AC connected
  • A number of circuits maybe connected to one station
  • DC connected AC collector networks are likely to be

more volatile Important to note:

10 July 2013 | Internal NC HVDC Workshop | Page 50

slide-51
SLIDE 51

Power Quality requirements for DC connected PPMs and convertors

  • Power Quality must be maintained to avoid failure or

accelerated aging of equipment Why is it needed in the NC HVDC?

  • Manage power quality to avoid equipment stress, risk of

temporary over voltages and provide users with a quality

  • f supply

What does it aim to achieve?

  • Equipment offshore more difficult to repair/replace
  • A number of circuits maybe connected to one station
  • A number of users maybe connected to one station
  • DC connected AC collector networks are likely to have a

higher harmonic – low resistance, low strength, high risk

  • f resonance conditions
  • TSO defined power quality standard

Important to note:

10 July 2013 | Internal NC HVDC Workshop | Page 51

slide-52
SLIDE 52