Need for Project Class A Sludge Anaerobic Digestion System Heat - - PowerPoint PPT Presentation

need for project class a sludge anaerobic digestion
SMART_READER_LITE
LIVE PREVIEW

Need for Project Class A Sludge Anaerobic Digestion System Heat - - PowerPoint PPT Presentation

Presentation for MWEA Process Committee Seminar November 6, 2013 SCREENING AND CONSEQUENCES Tom Grant, Hubbell Roth and Clark Sandra Diorka, Delhi Charter Township Need for Project Class A Sludge Anaerobic Digestion System Heat Exchangers


slide-1
SLIDE 1

Presentation for MWEA Process Committee Seminar November 6, 2013

SCREENING AND CONSEQUENCES

Tom Grant, Hubbell Roth and Clark Sandra Diorka, Delhi Charter Township

slide-2
SLIDE 2

Need for Project

  • Class A Sludge Anaerobic Digestion System Heat

Exchangers Plugging

slide-3
SLIDE 3

Plugging Heat Exchangers

  • All raw sludge is macerated such that fibers, plastics,
  • etc. are relatively small, about ¼” wide x 3” to 6”

long

  • During sludge recirculation and pumping through 1

1/4” and 3” diameter heat exchanger tubes, small pieces become entwined and form ropes that plug the heat exchangers

  • Heat exchangers required cleaning every other day
slide-4
SLIDE 4

Plugging Heat Exchangers

slide-5
SLIDE 5

Existing Not Effective

  • Existing headworks grinding with capture was not

effectively removing screenable materials from wastewater

  • Requires seasonal cleaning of primary clarifiers and

disposal of wet settlings to drying beds

  • Causing early wear on POTW equipment
  • Excessive labor spent removing rags from all process

equipment

  • Wasting pumps
  • Telescopic valves
  • Decant valves
  • Digester heat exchangers
slide-6
SLIDE 6

Existing Not Effective

slide-7
SLIDE 7

Existing Not Effective

  • Removal of about 40 pounds wet material per day
slide-8
SLIDE 8

New Screen Selection: Site Visits, Round 1

  • Traditional bar screens
  • Visited Michigan WWTPs to view their headworks

screens:

  • South Lyon, ¼” bar
  • Grand Rapids, ¼” bar
slide-9
SLIDE 9

Bar Screen Observations

  • During site visits noticed:
  • Bar screens had excessive pass through
  • Equipment had grease balls and strings hanging
  • Resulting screenings were very dirty
  • Bar screen room and environment was gross
  • Primaries, aeration tanks, and secondaries had floaters
  • Conclusion: Bar screens are not so good. What else

can we get?

slide-10
SLIDE 10

Pilot Testing at POTW

  • How do we pick between round holes and slots (bar

screen)? How big should the holes be?

  • Devised an in house experiment
  • Fabricated a slide gate with four different “screens”

built in

  • 1/8 inch round hole (perforated plate)
  • 1/4 inch round hole
  • 1/4 inch “bar” hole
  • Window screen (around 1mm hole size)
slide-11
SLIDE 11

Pilot Testing at POTW

  • Placed each gate in the influent channel for a

specified time

  • Weighed the material collected
  • Window screen was considered “100%” capture
  • Roughly 8000 pounds per day
  • Round holes collected roughly 4 times the amount of

material as the bar or slot shaped openings

  • Conclusion: We want round holes!!
slide-12
SLIDE 12

New Screen Selection: Site Visits, Round 2

  • North Kent, 1 to 3 mm drum screen
slide-13
SLIDE 13

New Screen Selection: Site Visits, Round 2

  • Kalamazoo, 6 mm

bandscreen

Flow Out

Screen entrance is sealed to channel

Flow In

slide-14
SLIDE 14

Discovered and Purchased U.K. Study

  • Purchased “National Screen Evaluation Facility, Inlet

Screen Comparative Report” performed between 1999 and 2011 by the UK Water Industry Research

  • Installed and compared the performance of 27 different

headworks treatment products

  • Finescreen
  • Stepscreen
  • Combined screen (bar or round with processing)
  • Bandscreen
  • Reported % capture of material
  • Maintenance frequency
slide-15
SLIDE 15

Finescreen

  • Screen rotates

around to carry stuff to the top

  • Can have round
  • r bar openings
slide-16
SLIDE 16

Stepscreen

  • Like a fine screen
  • Steps move and

transport stuff to the top – body of the screen holds still

slide-17
SLIDE 17

Discovered and Purchased U.K. Study

  • Bandscreens showed the best performance
  • Highest screen capture rate
  • Lowest risk of “pass through” or “carry over” because of

seal between opening and the channel

  • Study showed two brands had the highest screen capture

rate

  • Screens incorporating slots or bar spacing showed the

lowest performance

  • Conclusion: We want one of the bandscreens with

the highest capture rate!

slide-18
SLIDE 18

Site Visits Round 3

  • Made a three day trip to visit four additional screens
  • Ishpeming, MI – Jones and Atwood band, 6 mm holes
  • Sheboygan, WI – Brackett Green band, 6 mm holes
  • Madison, WI – Brackett Green band, 6 mm holes
  • Fond du Lac, WI – JWC Fine Screen, 3 mm holes
slide-19
SLIDE 19

Site Visits

  • Ishpeming
slide-20
SLIDE 20

Site Visits

  • Sheboygan
slide-21
SLIDE 21

The Final Decision

  • How did we decide?
  • The cleanest end product
  • 3mm because
  • Madison had 6mm hole size with the same type of heat

exchanger

  • Heat exchangers still plugged
  • Fond du Lac had 3mm hole size with the same type of

heat exchanger

  • Heat exchangers did NOT plug!!
slide-22
SLIDE 22

What Happened After ?

  • Heat exchangers no longer routinely cleaned
  • Primaries have no rags or floating “salad”
  • Grease hauled less often (contains only grease)
  • Aeration tanks do not have to be “skimmed”
  • No more condoms
  • Wasting pumps no longer need to be routinely

cleaned

  • Sludge storage decant valves have remained clean
  • Telescopic valves no longer have to be cleaned
slide-23
SLIDE 23

Screenings Production

200 400 600 800 1000 1200

slide-24
SLIDE 24

70.0 72.0 74.0 76.0 78.0 80.0 82.0 84.0 86.0 88.0

Before After Raw Sludge % Volatile

slide-25
SLIDE 25

50 100 150 200 250 300 350 400 450 500

Grit Production

slide-26
SLIDE 26

Before – NOT Gritty

slide-27
SLIDE 27

After – Actually Grit

slide-28
SLIDE 28

Engineering and Construction Design Engineering

  • 2 screens, each handle 6 mgd, bypass/overflow

manually cleaned channel 5 mgd

  • Tight site – fit between existing influent screw

pumps, grit tank and primary clarifiers

  • Existing hydraulic grade line is fixed
  • Poor soils for building & channels foundation
slide-29
SLIDE 29

Tight Site

slide-30
SLIDE 30

Poor Soils Helical Screw Piles Foundation

slide-31
SLIDE 31

Construction

  • Extended schedule due to piles, originally June 2012

completion, first screen started in October 2012

  • Alternate bypass
slide-32
SLIDE 32

Construction Gravity Bypass

slide-33
SLIDE 33

Construction

slide-34
SLIDE 34

Construction

slide-35
SLIDE 35

Construction

slide-36
SLIDE 36

Construction

slide-37
SLIDE 37

Results

slide-38
SLIDE 38

Results

slide-39
SLIDE 39

Questions??