National Western Center Master Plan Citizens Advisory Committee Meeting July 31, 2014

slide-2
SLIDE 2

NWC Partners / Design Team Work Session Initial Site Options June 2, 2014

National Western Center Master Plan Site Conditions and Precedents

slide-3
SLIDE 3
slide-4
SLIDE 4

SITE ASSETS

slide-5
SLIDE 5
slide-6
SLIDE 6

UNDER I-70

slide-7
SLIDE 7

UNDER I-70

slide-8
SLIDE 8

UNDER I-70

slide-9
SLIDE 9

UNDER I-70

slide-10
SLIDE 10
slide-11
SLIDE 11

PRECEDENTS – PROGRAMMING BENEATH INFRASTRUCTURE

slide-12
SLIDE 12

A8ernA, Netherlands A8ernA, Netherlands BMX Course, Seattle

PRECEDENTS – PROGRAMMING BENEATH INFRASTRUCTURE

slide-13
SLIDE 13

Buffalo Bayou Promenade Washington Avenue Bridge Sydney Harbour Bridge Nanpu Bridge

PRECEDENTS – BENEATH INFRASTRUCTURE

slide-14
SLIDE 14

UNDER BNSF

slide-15
SLIDE 15

NATIONAL WESTERN DRIVE

slide-16
SLIDE 16

FRANKLIN ST. AND RACE COURT

slide-17
SLIDE 17

RACE COURT

slide-18
SLIDE 18

RAIL CORRIDOR ALONG S. PLATTE RIVER

slide-19
SLIDE 19

46th Avenue at National Western Drive

slide-20
SLIDE 20

PRECEDENTS – BRIDGE OVER RAIL

slide-21
SLIDE 21

PRECEDENTS – BRIDGE OVER RIVER

slide-22
SLIDE 22

DELGANY INTERCEPTOR

slide-23
SLIDE 23

PRECEDENTS – TERRACED WATERFRONTS

slide-24
SLIDE 24

PRECEDENTS – TERRACED WATERFRONTS

slide-25
SLIDE 25

NWC Partners / Design Team Work Session Initial Site Options June 2, 2014

National Western Center Master Plan Rail, Circulation and Parking

slide-26
SLIDE 26

NWC RAIL CONSOLIDATION STUDY RIVER RAIL (DRIR) NW DRIVE RAIL (DRIR) JERSEY CUTOFF (BNSF) BNSF MAINLINE / RTD NORTH METRO

slide-27
SLIDE 27

NWC RAIL REGIONAL AREA MAP

slide-28
SLIDE 28

Possible East/West Connections

  • 1. 53rd Ave./Franklin/Race Ct.
  • 2. 51st Ave./49th Ave.
  • 3. 49th Ave./48th Ave.
  • 4. 49th Ave./47th Ave.
  • 5. 46th Ave./46th Ave.
  • 6. 46th Ave./44th Ave.

Existing Connection Possible New Connection Vehicular Structure Rail Crossing Existing River Crossing New River Crossing

Legend

1 1 2 2 4 3 5 5 6

CIRCULATION DISCUSSIONS

slide-29
SLIDE 29
  • 182 acres are devoted to parking for the Stock

Show

  • National Western Owned – 53 Acres
  • National Western Leased – 91 Acres
  • Coliseum – 24 Acres
  • Private – 14 Acres
  • 58% of the parking (106 acres) is for patrons,

employees, media, sponsors and participants.

  • Represents approximately 12,000 spaces
  • 42% (76 acres) is off-site and used for trucks and

trailers

PARKING STUDY UNDERWAY

CURRENT CONDITIONS

slide-30
SLIDE 30

NWC Partners / Design Team Work Session Initial Site Options June 2, 2014

National Western Center Master Plan Program Update

slide-31
SLIDE 31

Vision Statement

The National Western Center celebrates the pioneering spirit and promise of the West through year-round experiential life long leaning, the arts, entertainment, competition and commerce.

slide-32
SLIDE 32

Guiding Principles and Goals

  • Community and Neighborhood Integration
  • Engage the River and Nature
  • Celebrate Western Heritage
  • Inspire Health and Wellness
  • Build Cultural Crossroads
  • Be Pioneering: Break Trail and Foster Innovation
  • Create Fun and Entertaining Experiences
  • Grown Local, Regional and Global Intelligence
  • Embrace an Ethic of Regeneration
slide-33
SLIDE 33

NW PROGRAM UPDATE

slide-34
SLIDE 34

NW PROGRAM UPDATE

slide-35
SLIDE 35

Agricultural Production 3-12 Acres Living Commons 83,480 SF Food Systems Ag Exploritorium/ Conservatory 100,000 SF Classroom/ Conference Center

Colorado Urban Extension Center

Urban Farm 2 Acres Center for Visual & Performing Arts

Rail Station Heritage Center

Business Engineering

Health & Human Sciences

Warner College of Natural Resources Natural Sciences

Art Studio Music Studio

Gallery Community Space Food & Artisan Mart

South Platte River

Performing Arts/ Lecture Hall

CSU PROGRAM RELATIONSHIP DIAGRAM

slide-36
SLIDE 36

PROPERTY OWNERSHIP

Legend

NWSS/CCD Land Ownership

slide-37
SLIDE 37

TOD EXPO HALL/ ARENA

Option X

MULTI-USE LIVESTOCK EQUESTRIAN PARTNERS

slide-38
SLIDE 38

TOD EXPO HALL/ ARENA

Option Y

MULTI-USE LIVESTOCK EQUESTRIAN PARTNERS

slide-39
SLIDE 39

Option CSU

EXPO LIVESTOCK HALL/ ARENA ARENA CROPS EXPO HALL EVENTS PAVILION / YARDS EQUESTRIAN MULTI-USE LIVESTOCK EQUESTRIAN PARTNERS

slide-40
SLIDE 40

NWC PROGRAM LOCATION OPTIONS

slide-41
SLIDE 41

NWC Partners / Design Team Work Session Initial Site Options June 2, 2014

National Western Center Master Plan Public Involvement

slide-42
SLIDE 42

Outreach Objectives

  • To communicate directly with the community

and understand neighborhood needs and interests

  • To introduce the National Western Center

Partners as part of the planning process and “new neighbor”

  • To share the future NWC vision, program and

plan with the region

slide-43
SLIDE 43

Communication with Community

Partner with North Denver Cornerstone Collaborative

  • NDCC Open Houses
  • Website
  • NDCC Newsletter
  • NWC Friday Round-up
  • Community flyers/announcements/comment forms

Coordinate with Globeville & Elyria Swansea Neighborhood Plans

  • Steering Committee meetings/plan coordination
slide-44
SLIDE 44

Community Presence and Partnership

Coordination with CAC and community

  • August 9 - Denver Days Neighborhood Beautification &

Clean up Saturday 9 am -6 pm Argo Park

  • September – Back to School Nights
  • October – Farmer’s Market Fridays or school events
  • November – TBD
  • December – Business Association Holiday Party
slide-45
SLIDE 45

Community Meetings

  • NDCC Public Open Houses
  • July 22, 2014
  • September 23, 2014
  • December 9, 2014
  • NWC Community Meetings
  • Vision, Analysis and Program – August 2014
  • Alternatives – September 2014
  • Final Draft Plan – January 2015

NDCC Open House NWC Public Meeting Community Partnership Event & Community Newsletters

slide-46
SLIDE 46

Next Steps in the Process

  • Finalize Program
  • Test Fit facilities (July)
  • Develop 2 feasible options for review with Partners

and community (August/September)

  • Develop preferred alternative (October)
  • NWC Public Meeting (mid August)
  • Next CAC Meeting August 28, 2014