Municipal Class EA To Address Traffic Congestion On The Ontario - - PowerPoint PPT Presentation
Municipal Class EA To Address Traffic Congestion On The Ontario - - PowerPoint PPT Presentation
Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Council Information Meeting March 27, 2018 Agenda Background Class EA Alternatives Traffic Study Update Preliminary Preferred
Agenda
Background
Class EA Alternatives
Traffic Study Update
Preliminary Preferred Options
Consultation
MTO, Public, Agencies
Next Steps
Questions
Project Timelines
Project Initiated (March 2015) Preliminary Engineering/1st Traffic Study(Winter 2015/16) 1st Presentation to Council (June 28, 2016) Class EA Initiated/PIC #1 (Summer 2016) 2nd Traffic Study/Additional Engineering Review (2017) Additional Consultation with MTO (2017/2018) 2nd PIC Planned (June 4, 2018) Finalize Class EA (Summer 2018)
Traffic Study Update
Paradigm Transportation Solutions
Revised Project Study Limits
bmoss
Original Traffic Study Scope focused on the Main Street Intersection and bridge site
Traffic Study - Paradigm
Traffic Study expanded to look at entire corridor, cross-walks
and to assess the two-way left turning lane.
Cross walks appear to be functioning well. Saw no evidence to
suggest they should be relocated.
Study determined the first priority is to upgrade the capacity
- f the Main St. Intersection. It is backing up traffic through
the Lake St. Intersection.
Lake St. Intersection would perform the same without the left
turning lanes as with the left turning lanes.
Given there is only one northbound through lane at Main St.
the two-way left turning lanes help to keep northbound traffic in a single lane for traffic safety
Traffic Study – Recommendations
BMROSS
Main Street Intersection Upgrades
Add another northbound through lane and keep the shared
through/ right turn lane (5 lanes in total)
Immediately north of Intersection
Converting the two-way left turn lane to a north bound lane
would result in the largest capacity improvements for Main St. Intersection
Lake Road Intersection – Proposed Improvements
Remove the north and south bound left turning lanes at Lake
Road Intersection.
Conversion of the two-way left turn should not occur until
after the bridge and Main St intersection is widened.
Bridge Improvement Alternatives
Bridge Cross-Section - Existing
Alternate #1: New Bridge
Alternate #2: Widen Bridge with New Deck
Review of Bridge Options
Bridge Options New Bridge Widen Bridge Do Nothing Economic Most Expensive $1.6 million less Ongoing Impacts to Community Social Difficult & costly to maintain traffic during construction Will need to be constructed over 2 construction seasons Ongoing traffic impacts to community Environment River would need to be realigned Less disruptive to environment No impacts Transportation New bridge would provide 5 traffic lanes Wider bridge deck would provide 5 lanes Continued traffic back-ups Property Some property impacts north of bridge Some property impacts north of bridge
Bridge Improvement Alternatives
Alternative 1: Replace bridge with a new structure
capable of conveying greater traffic volumes
Alternative 2: Widen the bridge to accommodate
greater volumes of traffic
Alternative 3: Do Nothing
Preferred
Anticipated Costs
Alternative 1 – New Bridge*
$ 6.7 m
Alternative 2 – New Bridge Deck*
$ 5.1 m
* Construction from River Road to approximately 40 metres north of Main Street
intersection, including 5 lanes north of intersection merging in at Municipal
- Drive. An additional $900,000 to reconstruct road to north limits of Town.
**Preliminary Costs include an allowance for engineering and approvals but
not for property acquisition or utility company relocation costs.
Bridge Detailed Design Alternatives
Existing Bridge Cross-Section Option 1 – Multi Use Path on Both Sides
Barrier wall with single hand rail shown
Bridge Cross-Section - Options
Option 3 – Multi Use path on One Side Option 2 – Bike Lanes on both sides of traffic lanes
Bridge Cross-Section
Bridge Improvement Alternatives
Bridge Deck and Corridor Cross-Section Alternatives:
Alternative 1: Provide multi-use lanes on both sides.
Provides consistency with corridor to the south and provides a wider
pedestrian/cycling path along entire corridor
Alternative 2: Bicycle lanes along edge of driving lanes.
Not recommended for high summer time traffic volumes.
Alternative 3: Provide a two way multi-use lane on one side and a
normal sidewalk on the other side.
Forces bicycle traffic to only travel along one side of the road.
Preferred Bridge Cross-Section
Option 1 – Multi Use Path on Both Sides
Class EA Study Alternatives
Corridor Alternatives to Accommodate Vehicle Traffic:
Alternative 1 – Add Another Northbound Lane (5 lanes total) Alternative 2 – Switch the Two Way Turning Lane to
a Northbound Lane (4 lanes total)
Alternative 3 – Construct a By-Pass around Grand Bend to
divert through Traffic around the Community.
Alternative 4: Do Nothing, keep lane configuration the same
*Note: All options above included consideration of bicycle and pedestrian traffic Preferred
Detailed Design Alternatives
Corridor Alternatives
Alternative 1 – Add a multi-use path separate from the
roadway on both sides
Alternative 2 – Add bicycle lanes at the edge of the travelled
roadway, or
Alternative 3 – Add bicycle lanes behind the curb separate
from sidewalks, or
Alternative 4 - Add a multi-use path separate from the
roadway on one side
Alternative 5: Do Nothing, keep lane configuration the same
Corridor Property Limits
Option #1 – Multi-use Lane on Both Sides
Existing x-section width – 18.3 m Option #1 x-section width – 20.7 m
Option #2 – Bike Lanes at Edge of Road
Existing x-section width – 18.3 m Option #2 x-section width – 22.3 m
Option #3 – Separate Bike and Pedestrian Lanes
Existing x-section width – 18.3 m Option #3 x-section width – 22.5 m
Anticipated Costs
Alternative 1 – Multi-Use path both sides
$ 4.4 m
Alternative 2 – Bike lines in road
$ 4.8 m
Alternative 3 – Separate bike lanes
$ 4.5 m
Alternative 4 – Multi-Use path on one side
$4.8 m * Preliminary Costs include an allowance for engineering and approvals but
not for property acquisition or utility company relocation costs.
Comparison of Options
Option #1 – Multi-use Lane both sides
Narrower Option, Will still require some land, Has continuity
with trail to the south, splits up bike traffic
Option #2 – Bike Lanes at Edge of Road
Safety Issue, Most Expensive, No continuity north or south
Option #3 – Separate Bike and Pedestrian Lanes
Safest Option, Widest Option – May not be feasible based on
current corridor limitations
Option #4 – Multi-use Lane on one side only
Provides some continuity with trail to the south, narrowest
- ption, more expensive than 2 & 3, forces bikes to one side
Preferred
Consultation – Agencies & Aboriginal
Ministry of Tourism, Culture and Sport
Must consider potential Impact to Cultural Heritage Features
Ministry of the Environment and Climate Change
Aboriginal Consultation/Source Water Protection
Ministry of Transportation (project partner)
In General Agreement with the Recommendations
Ausable Bayfield Conservation Authority
Hydraulic Impacts at Bridge Opening