Mu2e Remote Handling Shield Door, Air Seal, and Transfer Cart Design - - PowerPoint PPT Presentation
Mu2e Remote Handling Shield Door, Air Seal, and Transfer Cart Design - - PowerPoint PPT Presentation
Mu2e Remote Handling Shield Door, Air Seal, and Transfer Cart Design Status Dave Pushka Mu2e Target, Remote Handling, and Heat & Radiation Shield Review November 16-18, 2015 Items Addressed in this Talk: Shield Door between the
Items Addressed in this Talk:
- Shield Door between the Remote Handling Room and the PS
enclosure.
- Air Seal between the Remote Handling Room and the PS
enclosure.
– Air Seal is part of the shield door assembly.
- Transport Cart Used to Move the Modules into and out of the
Remote Handling Room and the PS enclosure
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 2
Second Draft of Requirements for the Mu2e Remote Handling Room Shield Door and Air Seal
1. Cover an opening 19 feet wide, 13 feet tall, with at least a 6 inch overlap on the top and both sides when closed. 2. Provide shielding equivalent to 2 feet of conventional concrete (150 pound per cubic foot density) 3. Conform to the room and opening geometry as described in Mu2e document 5490v-2 (the In-progress Rev 6 drawings). 4. Open or close Shield Door (not air seal) in less than 10 minutes 5. Air seal to be replaceable within one 8 hour shift (Sealing door time < ½ hour) 6. Provide sealing against airflow between the remote handling room and the PS room when
- closed. Permissible Air leak rate is 130 cfm (this is estimated to be a 1/32 inch wide gap all the way
around the door. Static differential is 0.1 inch water column. Leakage budget for the entire room is 310
- cfm. (note – air seal does not need to be perfect)
7. Air seal on the remote handling room side to facilitate replacement when door is closed. 8. Meet the international building code seismic requirements for the Fermilab site. 9. Locate as much of the moving apparatus on the remote handling room side of the door as is possible.
- 10. Provide loads to the building due to the door to Tom Lackowski, building will be designed to accommodate
the shielding door loads.
- 11. Door will be installed after beneficial occupancy.
- 12. Building dimensions may preclude bringing the entire door in as a single piece. Door may need to be
assembled in place from smaller components.
- 13. Door to accommodate the remote handling cable conveyer system.
- 14. Door to accommodate vacuum pump required space.
- 15. Limit loading to the floor to 1400 psi from the door or from members supporting the door weight.
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 3
Shielding Door is a 24 inch thick concrete block shown in Gray. Shielding Door Moves on an aluminum cart, shown in purple. Air Seal included a fixed side (shown in Pink) and a moveable side (moves with the shield door) shown in Blue From the RH room Side
Isometric View of Shield Door and Air Seal Assembly from inside PS room:
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 4
Door Weight Sits on Floor When Not being moved Commercial Hydraulic Cylinders are Lift the Concrete when Door is moved Shield Door Moves on Commercially Available Crane Truck Wheels Floor Mounted Rails support the Crane Trucks From RH Room Side
Shield Door Cart (Air Seal Omitted in this Slide for Clarity)
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 5
- A single Speed Crane wheel
drive is used to move the door.
- Door Translates at 20 feet per
minute.
- Takes about 1 minute to open or
close.
- Will Use a simple two button
pendant controller to operate.
- Drive Motor to be mounted on
end, near the vacuum pumps.
- A festoon (not yet in the NX
model) will provide power to the door cart.
- Hard Stop to limit transverse
motion in both directions (not shown in NX model yet).
Shield Door Motion
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 6
Gear Motor Used to drive the cart (vacuum pumps and everything else hidden in this image):
Shield Door Cart Drive:
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 7
Overlap between shield door and the building concrete door jam
Shield Door Overlap and Vacuum Pump Clearance:
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 8
- Pink Element is 6 x 6 x
½ “ Aluminum Angle Bolted to the building to provide a smooth, planer surface for the elastomeric seal to press against.
- Considering Closed
Cell LDPE as the seal elastomer
Air Seal (Fixed Portion Attached to the Building Concrete)
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 9
- Aluminum Angle (6 x 6
x ½” ) Picture Frame with sheet aluminum skin and aluminum box section stiffeners.
- Picture Frame mates
with the same frame shown on previous slide.
- Mounted to the Shield
Door Cart (which is
- mitted in this image)
Air Seal (Mounted on the shield Door Cart)
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 10
- Pink is a 6 x 6 angle
frame bolted to concrete (in green) and fixed in place.
- Light Blue is the
moveable seal frame, also a 6 x 6 aluminum angle.
- Dark Blue is a vertical
adjustment mechanism
- Gray is the shield Door.
- Note Small Space
between Picture Frames
- Space above rail
Door Un-Sealed, Side View
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 11
- Light Blue Frame
moves vertically and horizontally on the gray pivot links.
- Moveable seal presses
against vertical surface
- f the fixed seal.
- 0.1 inch w.c. provides
.25 # / linear inch seal compression.
- 4-bar linkage of 2100#
applies 3.75 # / linear inch seal compression at 45 degrees.
Door Sealed:
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 12
Green bracket supports two pulleys used to lift moveable portion of seal and allow it to clear rail and fixed seal surface, prior to moving door. Dark blue allows vertical adjustment of assembly to allow moveable seal to sit
- n rail surface when also
bearing against the fixed seal.
Seal Engagement Mechanism (Concrete Shield Hidden in this image:
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 13
Wire rope (in dark gray) lifts moveable seal assembly when the door is moved. A simple threaded rod in tension is used to lift the blue member (to which the moveable seal assembly is attached) up and down to get the right contact to the rail on the bottom of the seal assembly. This should be a ‘one-time’ adjustment.
Detail of Adjustment Mechanism:
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 14
- Bottom of Moveable
Seal Picture Frame rests on the same rail the door cart rides on.
- This gives a flat,
smooth sealing surface for the bottom of the seal.
- Will need to fill in the
‘corners’ between the fixed seal and the rail with a small horizontal seal
Detail of Bottom Corner of the Air Seal:
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 15
Second Draft of Requirements for the Mu2e Remote Handling Transfer Cart:
1. Fit thru an opening 12 feet wide, 11 feet tall (this does not use the entire width or height of the shielding door to allow room for people or other equipment which is as of yet undefined. 2. Move into the Production Solenoid (PS) room or out of the PS room and into the remote handling room (RH) in less than 10 minutes 3. Carry the weight of a target coffin which is 40,000 pounds 4. Carry the weight of the remote handling modules which is 10,000 pounds 5. Total Load on the transfer cart is less than 50,000 pounds. 6. Limit loading to the floor to 1400 psi. 7. Provide a platform for the remote handling module which is located at an elevation of 32 inches above the floor. 8. Locate to within 5 cm of the PS centerline (10 cm error band). 9. Locate to within 5 of the PS End Cap Flange plane (0 to 5 cm error band).
- 10. Ride of the surface of the PS and RH room concrete floors or on rails as deemed best by the
design
- 11. Concrete floor elevation should be assumed to be accurate to only +/- 1 inch
- 12. Concrete floor surface is assumed dry, smooth but not sealed concrete
- 13. Local floor surface deviation from a plane is +/- 5 mm.
- 14. Activation issues favor fabrication of the transport cart from aluminum as much as is
- practical. Studies to quantify are under way.
- 15. Lift the remote handing modules and lower onto the kinematic mounts.
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 16
- 10,000 pound capacity
- Pneumatic cylinder to
lift remote handling modules.
- Does not lift casks
- Aluminum construction
- Four Commercial crane
wheels for travel.
- Commercial crane drive
- n two wheels to
provide travel motion.
- Rides on surface
mounted Rails, which may be stainless or carbon steel
Transfer Cart:
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 17
- A single Speed Crane wheel
drive is used to move the cart.
- Cart Translates at 15 feet per
minute; takes about 90 seconds to move.
- Hard stop will provide
transverse location alignment with PS.
- Will Use a simple two button
pendant controller to operate.
- Drive Motor to be mounted on
Remote Handling Room end.
- Multiple means exist to provide
power to drive.
- Contactors / controls mounted
in Remote Handling room.
Transfer Cart Motion
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 18
- Based on the method
used to lift boats in a boat lift.
- Uses an Air Cylinder as
the actuator
- Other actuators are possible
including gear drive electric motors, hydraulics, commercial linear actuators, ball screws, etc.
- Air cylinder chosen only because
the modules are using air cylinders and air is presumed to be available.
- Connection between
wire rope and the air cylinder via a guided block.
- Cylinder Pmax = 250
psig
Module Weight 10000pounds Air Cylinder Capacity @ 100 psig 2827pounds MCM 6211K432 Air Cylinder stroke 30in Number of support points 4 number of 'parts' of wire at each support point 2 total number of 'parts' 8 load per 'part' of wire rope 1250pounds pulley capacity, each 1800pounds MCM 3175T45 5/16 inch wire rope capacity 2100pounds MCM 3441T66 Load on cylinder: 2500pounds Maximum Module Vertical Travel: 15inches
Module Lift Mechanism
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 19
Technical Risks for Shield Door, Air Seal and Transport Cart
Risk Mitigation Shield Door Motion Using commercial crane hardware consistent with past experience in radioactive areas. Active components on RH room side of door. Wheels replaceable with Door in any position Air Leakage exceeding Leakage Budget Designed Air Seal from the ground up, not as an afterthought with duct tape and Herculite. Transport Cart Motion Using commercial crane hardware consistent with past experience in radioactive areas. Design allows the addition of a second method to retract cart into RH room, if found necessary in evaluating the FMEA. Transport Cart Lifting of Module Used simplest lifting mechanism possible. Based on commercial method used to lift boats. Unified lift explicit in the design.
Nov 16-18, 2015 Ryan Schultz | Contamination Control, Schedule & Conclusions 20
Transport Cart, Shield Door, and Air Seal Failure Mode Effect Analysis (FMEA):
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 21
- Component orientated (each component is reviewed for
possible failure states).
- Use failure rates for electrical equipment from FESHM 4240
(ODH) Tables 1 and 3.
- Use failure rates for human error from FESHM 4240 table 3
(may be conservative due to continuous radiation safety
- versight of activities).
- Refer to references in FESHM 4240; Some come from NRC
and are applicable to equipment in radiation areas.
- Including only single level failures.
- FMEA for shield door, air seal and transport cart are a work in
progress, being completed with the design effort.
- Rails for the door and
the transfer cart cross at 90 degrees.
- Commercially
manufactured ‘points’ not yet found to be available
- Flanges on the wheels
require a gap in the cross rails.
- A gap on the rail in the
direction of travel is bad.
Rails for the two Carts:
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 22
- Four Small custom
crosses solve the problem.
- Manually turned 90
degrees
- Set for the Transfer
Cart Move:
- Set for the Door Move:
- Can include ‘detents’ to
cause the pivoting section to ‘snap’ in at 90 degrees.
- Assume would be
manipulated from behind the shield door.
Solution for the Crossing of the Rails for the two Carts:
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 23
- Solve Cable Chain
Interferences with Air Seal and Shield Door Structure:
- Work with Radiation Safety
to:
– Address 7Be control measures – Evaluate suitable air seal elastomers – Unsure if the commercial polyethylene sill plate seal material is HDPE or LDPE – Evaluate Wheel Wipe for
7Be control
– Address Air Seal Change procedure.
Remaining Work on Door and Air Seal:
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 24
- Finish FMEA for equipment.
More Remaining Work On Door and Air Seal to Address:
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 25
- Complete calculations to
confirm member and connection sizing calculations.
- Create Hard Stop to prevent
potential for pinch hazard between door and building.
- Verify VSD not needed for
cart to ease against hard stops.
- Develop a back-up seal
clamping device.
- Develop seal install procedure
- Prepare detail fabrication
drawings
- Perform technical review of
each object with technicians, rad techs, and other stake holders as per the FEM
- Prepare cost estimates
- Prototype testing of air seal
- Develop details of the
concrete shielding block to allow assembly from multiple pre-cast sections and clear transfer cart rail.
More Remaining Work On Transfer Cart to Address:
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 26
- Complete calculations to
confirm member and connection sizing calculations.
- Prototype testing of the
transfer cart lift mechanism
- Model Hard Stop in PS room
for transverse transfer cart movement.
- Verify VSD not needed for
cart to ease against hard stops.
- Develop interface between
transfer cart and modules
- Develop interface between
transfer cart and cask(s).
- Prepare detail fabrication
drawings
- Perform technical review of
each object with technicians, rad techs, and other stake holders as per the FEM
- Prepare cost estimates
- Evaluate Rail Wiping fixture
for 7Be control.
Back-Up Slides: Back-Up Slides
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 27
Shield Door and Air Seal EPC Risk Assessment:
Engineering Risk Assessment
Project:Mu2e Target Hall Shield Door Lead Engineer:Dave Pushka Department:AD/ Targets Date:June 8, 2015
Engineering Risk Element High Chapter A B C D E F G Risk Subtotal Assessment 1 Requirements and Specifications 2 1 3 ≥10 6 Standard Risk 3 Requirements and Specification Review 2 1 3 3 3 ≥16 12 Standard Risk 4 System Design 2 1 2 3 3 2 ≥19 13 Standard Risk 5 Engineering Design Review 2 1 2 3 3 2 ≥19 13 Standard Risk 6 Procurement and Implementation 1 3 3 3 2 ≥16 12 Standard Risk 7 Testing and Validation 2 3 3 2 ≥13 10 Standard Risk 8 Release to Operations 3 ≥4 3 Standard Risk 9 Final Documentation 1 3 ≥7 4 Standard Risk Project Risk Element High H I J K L M N O Risk Subtotal Assessment 2 2 2 1 2 2 1 2 ≥25 14 Standard Risk Engineering Risk Elements Project Risk Elements A Technology H Schedule B Environmental Impact I Interfaces C Vendor Issues J Experience / Capability D Resource Availability K Regulatory Requirements E Safety L Project Funding F Quality Requirements M Project Reporting Requirements G Manufacturing Complexity N Public Impact O Project Cost
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 28
Transfer Cart EPC Risk Assessment:
Nov 16-18, 2015 Dave Pushka | Shield Door, Air Seal, and Transfer Cart Design 29
Engineering Risk Assessment
Project:Mu2e Remote Handling Transfer Cart Lead Engineer:Dave Pushka Department:AD/ Target Date:June 8, 2015
Engineering Risk Element High Chapter A B C D E F G Risk Subtotal Assessment 1 Requirements and Specifications 1 1 3 ≥10 5 Standard Risk 3 Requirements and Specification Review 1 1 2 2 3 ≥16 9 Standard Risk 4 System Design 1 1 2 2 3 2 ≥19 11 Standard Risk 5 Engineering Design Review 1 1 2 2 3 2 ≥19 11 Standard Risk 6 Procurement and Implementation 1 2 2 3 2 ≥16 10 Standard Risk 7 Testing and Validation 1 2 3 2 ≥13 8 Standard Risk 8 Release to Operations 3 ≥4 3 Standard Risk 9 Final Documentation 1 3 ≥7 4 Standard Risk Project Risk Element High H I J K L M N O Risk Subtotal Assessment 2 3 2 1 2 2 1 2 ≥25 15 Standard Risk Engineering Risk Elements Project Risk Elements A Technology H Schedule B Environmental Impact I Interfaces C Vendor Issues J Experience / Capability D Resource Availability K Regulatory Requirements E Safety L Project Funding F Quality Requirements M Project Reporting Requirements G Manufacturing Complexity N Public Impact O Project Cost