Morgan State University Campus-Wide Utilities s Phase se IV, Part - - PowerPoint PPT Presentation
Morgan State University Campus-Wide Utilities s Phase se IV, Part - - PowerPoint PPT Presentation
Morgan State University Campus-Wide Utilities s Phase se IV, Part 2 Chiller Replacement BP #1.03 & 1.04 (re-bid) Pre-Proposal Conference May 14, 2018 Updated as of Friday, May 18, 2018 Project Team Owner: Morgan State University
Updated as of Friday, May 18, 2018
- Owner: Morgan State University
–Procurement Office: Cynthia Cureton and Juanita Singletary –Deputy Director: Julie Wilson –Project Manager: Bill Bolling
- Engineering Team: Kibart (Mechanical and Electrical)
–Civil Consultants: Carroll Engineering, Inc. –Structural Consultants: Columbia Engineering, Inc. –Geotechnical Consultant: Hillis-Carnes Engineering Associates, Inc.
- Construction Manager: Barton Malow Company
–Vice President: Ben Morgan –Project Manager: Paul Grossman –Superintendent: Rick Roberts
Project Team
Updated as of Friday, May 18, 2018
- Approx. $7 Million Construction Budget
- Major Mechanical Upgrades
–Alternate 1: Add VFD to existing pump –Alternate 2: Steam boiler
- Integration into Existing Systems
- Occupied Facility
- DLLR Prevailing Wage
- Sales Tax Must be Included
- Construction Begins: October 1, 2018
- Substantial Completion: April 15, 2019
Project Overview
Updated as of Friday, May 18, 2018
- 1.03 Metals
–Structural steel demolition and new work –Misc. metals
- 1.04 General Trades
–Temporary fencing –Minor demolition –Excavation and placement of concrete footers –Masonry demolition and remediation –Painting –Construction signage –Exterior Repairs/Weatherproofing
Proposal Categories
Updated as of Friday, May 18, 2018
- Spencer Hall
–Occupied Facility –Constrained Site:
- No parking
- Minimal laydown
Location
Updated as of Friday, May 18, 2018
Site Logistics
Material Deliveries from
- E. Cold Spring Lane
Updated as of Friday, May 18, 2018
- SAFETY
–PPE: 100% hats, gloves, boots, reflective vests, eye protection –Badging ($25/worker) –Stretch & Flex Program
- Prolog Converge
- Pay Application Process – MBE Paperwork & Releases must accompany pay
application
- Technology – Paperless Job
–Box.com –iPads/tablets
Unique Conditions
Updated as of Friday, May 18, 2018
- Complete by May 21st, allow time for system & review
- http://contractors.bartonmalow.com
- Supplemental instructions emailed with Bid Package Announcement
On-line Prequalification
Updated as of Friday, May 18, 2018
- Bid Forms have been issued in Advertisement to Bid
- Proposal Forms
–Base Bid (excluding bond) –Alternates –Voluntary Alternates –Labor Rates –MBE/WBE –Safety Certifications
Bid Proposal due May 22, 2018 @ 3:00 p.m.
Originals are to be submitted in triplicate to: Barton Malow Company 300 West Pratt Street, Suite 310 Baltimore, MD 21201 Attn: Paul Grossman, Project Manager
Updated as of Friday, May 18, 2018
- Read Scopes of Work
- MBE/WBE Utilization (35%)
–7% Hispanic –4% Women-Owned –2% African American
- Prevailing Wage
- Include MD sales tax
- Buy U.S. Steel
- Submission Dates
– May 22, 2018 @ 3:00 p.m. EMAILED PROPOSALS WILL NOT BE ACCEPTED.
Bid Reminders
Updated as of Friday, May 18, 2018
- Pre-proposal conference meeting minutes and attendance log
- Bidder RFI’s
- Scopes of Work
- Bid Package No. 1 Bid Schedule
Upcoming Addenda
Updated as of Friday, May 18, 2018
- Questions and Answers
–Please follow all specific questions up with formal RFIs – use the excel form provided in the Bid Advertisement
- Follow-up questions in writing by 3:00 PM on May 17, 2018.
- Prequal Status must be current
- Site walk