Morgan State University Campus-Wide Utilities s Phase se IV, Part 2 Chiller Replacement BP #1.03 & 1.04 (re-bid) Pre-Proposal Conference May 14, 2018 Updated as of Friday, May 18, 2018 Project Team Owner: Morgan State University


slide-1
SLIDE 1

Updated as of Friday, May 18, 2018

Morgan State University

Campus-Wide Utilities s – Phase se IV, Part 2 Chiller Replacement

BP #1.03 & 1.04 (re-bid) Pre-Proposal Conference

May 14, 2018

slide-2
SLIDE 2

Updated as of Friday, May 18, 2018

  • Owner: Morgan State University

–Procurement Office: Cynthia Cureton and Juanita Singletary –Deputy Director: Julie Wilson –Project Manager: Bill Bolling

  • Engineering Team: Kibart (Mechanical and Electrical)

–Civil Consultants: Carroll Engineering, Inc. –Structural Consultants: Columbia Engineering, Inc. –Geotechnical Consultant: Hillis-Carnes Engineering Associates, Inc.

  • Construction Manager: Barton Malow Company

–Vice President: Ben Morgan –Project Manager: Paul Grossman –Superintendent: Rick Roberts

Project Team

slide-3
SLIDE 3

Updated as of Friday, May 18, 2018

  • Approx. $7 Million Construction Budget
  • Major Mechanical Upgrades

–Alternate 1: Add VFD to existing pump –Alternate 2: Steam boiler

  • Integration into Existing Systems
  • Occupied Facility
  • DLLR Prevailing Wage
  • Sales Tax Must be Included
  • Construction Begins: October 1, 2018
  • Substantial Completion: April 15, 2019

Project Overview

slide-4
SLIDE 4

Updated as of Friday, May 18, 2018

  • 1.03 Metals

–Structural steel demolition and new work –Misc. metals

  • 1.04 General Trades

–Temporary fencing –Minor demolition –Excavation and placement of concrete footers –Masonry demolition and remediation –Painting –Construction signage –Exterior Repairs/Weatherproofing

Proposal Categories

slide-5
SLIDE 5

Updated as of Friday, May 18, 2018

  • Spencer Hall

–Occupied Facility –Constrained Site:

  • No parking
  • Minimal laydown

Location

slide-6
SLIDE 6

Updated as of Friday, May 18, 2018

Site Logistics

Material Deliveries from

  • E. Cold Spring Lane
slide-7
SLIDE 7

Updated as of Friday, May 18, 2018

  • SAFETY

–PPE: 100% hats, gloves, boots, reflective vests, eye protection –Badging ($25/worker) –Stretch & Flex Program

  • Prolog Converge
  • Pay Application Process – MBE Paperwork & Releases must accompany pay

application

  • Technology – Paperless Job

–Box.com –iPads/tablets

Unique Conditions

slide-8
SLIDE 8

Updated as of Friday, May 18, 2018

  • Complete by May 21st, allow time for system & review
  • http://contractors.bartonmalow.com
  • Supplemental instructions emailed with Bid Package Announcement

On-line Prequalification

slide-9
SLIDE 9

Updated as of Friday, May 18, 2018

  • Bid Forms have been issued in Advertisement to Bid
  • Proposal Forms

–Base Bid (excluding bond) –Alternates –Voluntary Alternates –Labor Rates –MBE/WBE –Safety Certifications

Bid Proposal due May 22, 2018 @ 3:00 p.m.

Originals are to be submitted in triplicate to: Barton Malow Company 300 West Pratt Street, Suite 310 Baltimore, MD 21201 Attn: Paul Grossman, Project Manager

slide-10
SLIDE 10

Updated as of Friday, May 18, 2018

  • Read Scopes of Work
  • MBE/WBE Utilization (35%)

–7% Hispanic –4% Women-Owned –2% African American

  • Prevailing Wage
  • Include MD sales tax
  • Buy U.S. Steel
  • Submission Dates

– May 22, 2018 @ 3:00 p.m. EMAILED PROPOSALS WILL NOT BE ACCEPTED.

Bid Reminders

slide-11
SLIDE 11

Updated as of Friday, May 18, 2018

  • Pre-proposal conference meeting minutes and attendance log
  • Bidder RFI’s
  • Scopes of Work
  • Bid Package No. 1 Bid Schedule

Upcoming Addenda

slide-12
SLIDE 12

Updated as of Friday, May 18, 2018

  • Questions and Answers

–Please follow all specific questions up with formal RFIs – use the excel form provided in the Bid Advertisement

  • Follow-up questions in writing by 3:00 PM on May 17, 2018.
  • Prequal Status must be current
  • Site walk