moorpark pardee 230 kv no 4 circuit project
play

Moorpark-Pardee 230 kV No. 4 Circuit Project Nebiyu Yimer Regional - PowerPoint PPT Presentation

Moorpark-Pardee 230 kV No. 4 Circuit Project Nebiyu Yimer Regional Transmission Engineer Lead 2017-2018 Transmission Planning Process Stakeholder Call January 11, 2018 This review is taking place in light of: The announced/expected


  1. Moorpark-Pardee 230 kV No. 4 Circuit Project Nebiyu Yimer Regional Transmission Engineer Lead 2017-2018 Transmission Planning Process Stakeholder Call January 11, 2018

  2. This review is taking place in light of: • The announced/expected retirement of more than 2000 MW of generation in the Moorpark area including Mandalay Unit 3 • CEC’s announced intention to issue a proposed decision that recommends denial of NRG’s application for the Puente Power Project and its subsequent decision to suspend the proceedings in response to NRG’s request • The procurement plan for Moorpark local capacity and Goleta resiliency needs SCE submitted to the CPUC for approval Page 2

  3. Project overview • The project is proposed by SCE to address the local capacity deficiency in the Moorpark subarea and involves: – stringing a fourth Moorpark-Pardee 230 kV circuit approximately 26 miles on existing structures – installing terminal equipment at Moorpark and Pardee Substations and – relocating existing circuit terminations in the 230 kV switchrack at Moorpark Substation. Slide 3

  4. Project overview – cont’d • The project has an estimated cost of $45 million. • The required in service date is 12/31/2020 to coincide with the retirement of OTC generation in the area • SCE has requested ISO approval by March 2018 in order to meet the required in service date. Slide 4

  5. Current projection of post-2020 local capacity need in the Ventura Area Moorpark Santa SCE’s Goleta LCR Clara Resiliency LCR Needs 2022 LCR (Note 1) 554 MW 289 MW Resources available post 2020 (Note 2) 236 MW 203 MW Existing generation 2336 MW 808 MW N/A Announced/expected retirements (2076) MW (560 MW) Ellwood assumed unavailable (Note 3) (54 MW) (54 MW) Existing/approved preferred resources 30 MW 9 MW Deficiency w/o Moorpark-Pardee No. 4 ~318 MW ~86 MW 105 MW Deficiency with Moorpark-Pardee No. 4 0 MW ~86 MW 105 MW Note1: LCR is dependent on location, reactive power capability and other characteristics of the resources that fill the need and is subject to change in the future due to changes in the CEC load forecast. Note 2: Amount does not include the 10 MW energy storage contract SCE submitted to the CPUC for approval. Note 3: SCE’s contract with NRG to refurbish the Ellwood generating station, which is 43 year old, was denied by the CPUC. Slide 5

  6. Alternatives considered • Alternative 1 – Pardee-Moorpark project to address Moorpark LCR need coupled with 86 MW to 105 MW (NQC) of local capacity located downstream of Goleta to address Santa Clara LCR and SCE’s Goleta resiliency needs • Alternative 2 – Approximately 318 MW (NQC) of local capacity to address Moorpark LCR need of which 105 MW is located downstream of Goleta to address Santa Clara LCR and SCE’s Goleta resiliency needs • Alternative 3 – 240 Mvar dynamic reactive power support coupled with 135 MW (NQC) of local capacity to address Moorpark LCR need of which 105 MW is located downstream of Goleta to address Santa Clara LCR and SCE’s Goleta resiliency needs Slide 6

  7. Comparison of effectiveness in addressing Moorpark local capacity need Moorpark Subarea P-V Analysis for the Critical Contingency 230.0 225.0 MOORPARK 230 kV VOLTAGE, KV 220.0 215.0 210.0 AREA PEAK LOAD 1733 MW 1723 MW 205.0 200.0 1739 MW 195.0 1439 MW 190.0 2355-2367 MW 185.0 180.0 1390 1490 1590 1690 1790 1890 1990 2090 2190 2290 2390 MOORPARK AREA LOAD, MW STATUS QUO ALTERNATIVE 1 ALTERNATIVE 2 ALTERNATIVE 3 Note: Due to run-time limitation of resources such as demand response and energy storage, diurnal variability of solar PV and charging requirements of energy storage, an hour by hour analysis is needed to confirm whether such a resource mix meets LCR criteria in addition to the NQC-based analysis performed here. The ISO Moorpark Sub-Area Local Capacity Alternative Study (http://www.caiso.com/Documents/Aug16_2017_MoorparkSub-AreaLocalCapacityRequirementStudy- PuentePowerProject_15-AFC-01.pdf) provides such analysis and examples of validated resource portfolios along with very high level cost estimates. Slide 7

  8. Comparison of alternatives Criteria Alternative 1 Alternative 2 Alternative 3 (Tx + 86 MW to (318 MW LC) (240 Mvar + 135 105 MW LC) MW LC) Increase in post 916-928 MW 300 MW 294 MW contingency voltage stability area load limit Maximum thermal loading <100% 159% (Pardee- 189% (Pardee- under critical contingency Santa Clara 230 kV) Santa Clara 230 kV) Grid resiliency Neutral Better Neutral Operational complexity Lower Higher Lower due to variability, run-time limitation and charging needs of local capacity resources Capital cost Lower Much higher Higher Required 12/31/2020 in- Achievable Highly aggressive Achievable service date Slide 8

  9. Conclusion • ISO will include a recommendation in the draft transmission plan to be issued on January 31st, 2018 Slide 9

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend