Monitoring Framework for Regulatory Compliance by Power - - PowerPoint PPT Presentation

monitoring framework
SMART_READER_LITE
LIVE PREVIEW

Monitoring Framework for Regulatory Compliance by Power - - PowerPoint PPT Presentation

Designing Management & Monitoring Framework for Regulatory Compliance by Power Transmission Utilities in the SAARC Region RAJENDRA SINGH, MINISTRY OF POWER, INDIA DILIP ROZEKAR, POWERGRID, INDIA 1 Indian Power System : A Glimpse Growth


slide-1
SLIDE 1

Designing Management & Monitoring Framework for Regulatory Compliance by Power Transmission Utilities in the SAARC Region

RAJENDRA SINGH, MINISTRY OF POWER, INDIA DILIP ROZEKAR, POWERGRID, INDIA

1

slide-2
SLIDE 2

Indian Power System : A Glimpse

Total Installed Capacity - 258 GW

Renewable:

31 GW Peak Demand: 140 GW

Growth Rate: 8–9 % p.a.

Coal 156.2,60.4% Gas 23,8.9% Diesel 1.2,0.5% Nuclear 5.8,2.2% Hydro 40.9,15.8% Renewable 31.7,12.2%

Generation Mix

Figures in GW (as on 31.01.2015)

Transmission line Existing (Dec’14) By 2016-17* ckm 1200 kV 363 765kV 16,292 32,250 400kV 133,042 144,819 220kV 147,919 170,980 HVDC Bipole (±500kV) 9,432 16,872 HVDC Bipole (±800kV)

  • 1,728

Total 306,685 367,012 Transformation capacity Existing (Dec’14) By 2016-17* MVA 765kV 103,500 174,000 400kV 190,242 196,027 220kV 265,103 299,774 HVDC 13,500 MW 225,000 MW Total 572,345 692,301

slide-3
SLIDE 3

NEW Grid

South Grid South

West North

East Northeast

Five Regional Grids Five Frequencies

October 1991 East and Northeast synchronized March 2003 West synchronized With East & Northeast

August 2006 North synchronized With Central Grid

Central Grid

Five Regional Grids Two Frequencies

SR Synch By 2013-14

Inter – Regional Capacity: 44850 MW

3

slide-4
SLIDE 4

Transmission System – As of Today

  • Strong back bone of 400 kV – Overlay of 765 kV & high capacity

HVDC under Implementation

  • All India synchronous grid – One of the largest in the World
  • Thriving Pan-India Single Market enabled
  • Under new concept of planning, 10 nos. of high capacity corridors

evolved - to reduce the dependency on a particular generation

  • No congestion in LTA, Congestion only in STOA & MTOA : Total

congestion in 2013-14, about 5.6 BU (0.6%) as against annual generation of about 950 BU

  • Most Advance Load Despatch Centre in Operation
slide-5
SLIDE 5

Earlier

  • Generation is licensed
  • Regional self sufficiency

with limited inter- regional allocation

  • Predictable Transmission

Change in Paradigm

Now

  • De-licensed/Uncertainty in

generation

  • Connectivity to Generators

without PPA/Direction

  • Open access across the

nation

  • Long term Access on Target

Region

  • Economic

despatch

  • f

generation

slide-6
SLIDE 6

6

All Figures in GW

Plan-wise Growth in Generation and Demand

slide-7
SLIDE 7

Growth of Generation in Past years

9263 3453 9585 12160 20501 20622 17825 12510 5000 10000 15000 20000 25000 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15

* 2014-15 – UPTO 15th Jan, 2015

Cumulative Capacity Addition in last 8 years : about 106 GW

7

slide-8
SLIDE 8

Voltage (kV) 1977 1990 2000 2002 2012 2017-18 Year

220kV 400kV 500kV HVDC 765kV 800kV HVDC 1200kV

Pursuing Higher Voltage Levels

765kV D/C - AC World’s Highest Voltage level – Test station Charged in Oct.’12 World’s longest multi-terminal HVDC to harness renewable Hydro Power from North-east

slide-9
SLIDE 9

❖World’s highest voltage, 1200kV UHV AC, test charged at Bina, Madhya Pradesh in October 2012. ❖Has been Developed Indigenously through Public Private Partnership (PPP) with 35 Indian manufacturers in

  • pen collaboration.

INDIGENOUS DEVELOPMENT OF 1200KV UHVAC

slide-10
SLIDE 10

Road Map for Indian Power System

RoW (m) Capacity (MW) MW/m RoW 400kV S/c 52 500 9.6 400kV D/c 46 1000 21.8 765kV S/c 64 2500 39 765kV D/c 67 4000 60 800kV HVDC 69 6000 87

69 m

176 m

High Power Intensity Corridors

slide-11
SLIDE 11

11

Growth in Inter-Regional Transmission Capacity

slide-12
SLIDE 12

Renewable Pockets

SHP Wind Solar

Scenario Energy Penetration (%) Capacity Penetration (%) Present 6 13 2017 >13 >21 2030 >21 >35 2050 >33 >50

Renewable Energy Scenario

slide-13
SLIDE 13

Green Energy Corridor : Integration of Renewables

  • About 33GW capacity addition

envisaged through wind & solar in next 4-5 years

  • The Plan includes

– Transmission strengthening(s) – Dynamic reactive compensation, – Energy Storage, – Smart grid applications, – Establishment of Renewable Energy Management Centre enabling forecasting of renewable generation, real time monitoring, etc.

slide-14
SLIDE 14

NLDC Ensure integrated operation of National Grid RLDC Ensure integrated operation of Regional Grid SLDC Ensure integrated operation of State Grid

31 5

Grid Management Hierarchy

14

slide-15
SLIDE 15

15

Inter Interconnection connection with with SAAR SAARC Count C Countries ries

slide-16
SLIDE 16

16

Interconnection between India & Bangladesh Grids

  • Purpose :

–Exchange of Power between India and Bangladesh

  • Interconnection :

– Baharampur(India)- Bheramara(Bangladesh) 400kV D/c line

–500MW HVDC B/b stn at Bheramara(Bangladesh)

  • Type of connection :

–Asynchronous(HVDC)

  • Transfer Capacity :

– 500MW (upgradable to 1000MW)

GOALPARA 33.2 MVA KHULNA DOMJUR LILUAH HOWRAH(WB) JOKA BUDGE BUDGE SOUTHERN BARIPADA HALDIA TAMLUK FALTA KOLAGHAT KRG'PUR(D) ULUBERIA KOLAGHAT(D) HWH(D) HM LEGEND BHOLA GALLAMARI LAKSHMIKANTOPUR SUBHASGRAM BASIRHAT SONARPUR KASBA MANGLA 13.3 MVA SOUTH SATKHIRA BHANDARIA 13.3 MVA 26.6 MVA BAGERHAT KAWKHALI PATUAKHALI 40 MVA BARISAL 82 MVA 230/220kV EXISTING 132kV FUTURE BANDARBAN 20 MVA COX'S BAZAR RAUJAN JULDAH SHAHMIRPUR 126 MVA

Bay of Bengal

HALISHAHAR 167 MVA BURHANUDDIN 63 MVA 82 MVA HATHAZARI BAROAULIA KULSI SIKALBAHA 80 MVA 41 MVA DOHAZARI CHANDROGHONA 26.6 MVA MADANHAT 82 MVA KAPTAI LUNGSEN TENGA NBU LD TEESTA RAIGANJ GANGARAMPUR DALKHOLA(WBSEB)
  • CH. NAWABGANJ
40 MVA SAGARDIGHI RAGHUNATHGANJ DEBAGRAM KRNAGAR RANAGHAT TITAGARH DPL ARAMBAG ARAMBAG BURDWAN RISHRA BELMURI KHANYAN BTPS DURGAPUR NAGAR BIDHAN MANKAR BOLPUR SATGACHIA KATWA DHULIAN RAMPURHAT BAKRESHWAR SAITHIA GOKARNA FARRAKA KHEJURIA PURNEA KAHALGAON MALDA SAMSI DALKHOLA KATIHAR PURNEA(BSEB) (WBSEB) DALKHOLA LEBONG RAMMAM JOYDEVPUR GHORASAL ASHUGANJ MEGHNAGHAT MAGURA 40 MVA KHULNA CENTRAL 192 MVA NOAPARA BONGAON JEERAT ASHOKNAGAR DHRMPR BARASAT KALYANI JESSORE 80 MVA CHUADANGA JHENAIDA 40 MVA BOTTAIL 82 MVA MADARIPUR 26.6 MVA GOPALGANJ CHANDPUR 40 MVA AMINBAZAR FARIDPUR 40 MVA MANIKGANJ 41 MVA HASNABAD MIRPUR KALYANPUR TONGI ULLON BASUNDHARA BOGRA 82 MVA 40 MVA SHAHJAD SIRAJGANJ PUR 40 MVA BHERAMARA 16.6 MVA ISHURDI BEHRAMPUR BEHRAMPUR 53 MVA RAJSHAHI 82 MVA PABNA NATORE 40MVA NIAMATPUR NAOGAON 82 MVA BOGRA SOUTH SRIPUR(MODHUPUR) TANGAIL 82 MVA BAGHABARI KABIRPUR 82 MVA 68 MVA JAMALPUR 82 MVA 82 MVA MYMENSINGH JIRIBAM KOLASIB 100 MVA KHOWAI

TRIPURA

CHOWMOHANI 82 MVA COMILLA 82 MVA SOUTH FENI 40 MVA 40 MVA COMILLA NORTH AGARTALA HARIPUR SIDDHIRGANJ RAMPURA GPP AGARTALA AMBASSA W.PHAILENG RANGAMATI KHAGRACHARI LUNGLEI MARPARA SERCHIP (ZEMABAWK)

MIZORAM

AIZWAL AIZWAL EAST KANCHANBARI KISHORGANJ 20 MVA SHAHJIBAZAR 50 MVA
  • B. BARIA
B BARIA 40 MVA KAMALPUR SREEMONGAL 40 MVA NETROKONA 40 MVA SYLHET DULLABCHERA KAILASHAHAR KUMARGHAT DHARMNAGAR BADARPUR PANCHGRAM FENCHUGANJ 33 MVA SYLHET 40 MVA JIRIBAM PILAPOOL BONGAIGAON

ASSAM

BORNAGAR 40 MVA LALMONIRHAT PALASHBARI JOYPURHAT BALURGHAT 40 MVA 82 MVA SAIDPUR 33.4 MVA BOROPUKURIA PURBASADIPUR (2x41+1x20) MVA THAKURGAON RANGPUR 82 MVA TURA ALIPURDUAR SILIGURI MOINAGURI PANCHAGARH BIRPARA MELLI BIRPARA(WB) GOSAIGAON DHALIGAON AGIA SALAKATI SINGIGAON CHUKHA GUWAHATI NEHU KYRDEMKULAI UMIAM-4

MEGHALAYA

NANGAL BIBRA 40 MVA CHATTAK CHERRAPUNJI SHILLONG LONGPI UMTRU UMIAM CHANDRAPUR KHLIEHRIAT KHLIEHRIAT KHANDONG HAFLONG KOPILI BYRNIHAT JAGIROAD UMRANGSO NECHIPHU RANGIA AMINGAON ROWTA TEJPUR SAMAGURI MARIANI BALIPARA GOHPUR

POWER MAP OF BANGLADESH AND INDIA

GANGTOK RANJIT TEESTA-V TALA LHAO KAMENG KHUPI SURYAMANINAGAR SILCHAR 400kV at 132kV PALLATANA AZARA
slide-17
SLIDE 17

17 BOGRA SOUTH

BHERAMARA

NAOGAON NIAMATPUR FARRAKA SUBHASGRAM KATWA GOKARNA JEERAT KHULNA (SOUTH) BOTTAIL

BAHARAMPUR

  • CH. NAWABGANJ

RAGHUNATHGANJ KAHALGAON SAGARDIGHI RAJSHAHI BAHARAMPUR ISHURDI NATORE KHEJURIA FARIDPUR BAGHABARI GHORASAL MADHOPUR SHAHJAD PABNA PUR SIRAJGANJ BOGRA

INTERCONNECTION BETWEEN INDIA AND BANGLADESH GRIDS

400 kV 230 kV 132 kV THE PROJECT LEGEND BAKRESHWAR KOLAGHAT

BANGLADESH INDIA

400kV D/c (400 KV)

MALDA DHULIAN DURGAPUR Existing Under Constr. / Future JAYPURHAT BARAPUKURIA

slide-18
SLIDE 18

India - Bhutan : Existing Interconnections

For import of power from following Projects

  • Chukha HEP (4x84 = 336 MW)

– Chukha – Birpara 220kV 3 ckts

  • Kurichu HEP (4x15 = 60 MW)

– Kuruchu - Geylegphug(Bhutan) – Salakati(NER) 132 kV S/c

  • Tala HEP (6x170 MW = 1020 MW)

– Tala – Siliguri 400kV 2x D/c line

18

slide-19
SLIDE 19

India - Bhutan : On Going Trans. System

❑ Tr. System for Punatsangchu-I (1200 MW)

  • Interconnection (Bhutan Portion) : Punatsangchu-I HEP – Lhamoizingkha

(Bhutan Border) 400 kV 2xD/c line with twin moose Conductor.

  • Interconnection (Indian Portion) : Lhamoizingkha (Bhutan Border) –

Alipurduar 400kV D/c (Quad)

  • Other Major Transmission System in India

– New + 800kV, 3000MW HVDC pooling station at Alipurduar. – Extn. of + 800kV, 3000MW HVDC station at Agra – LILO of Bishwanath Chariali – Agra 800kV, 6000MW HVDC line at Alipurduar – LILO of Bongaigaon – Siliguri 400kV D/c line(quad) at Alipurduar – LILO of Tala-Siliguri 400kV D/c line at Alipurduar.

❑ Estimated Cost (Indian Part) : Rs. 4400Cr. (USD 978 million)

19

slide-20
SLIDE 20

20

India - Nepal : Interconnection

slide-21
SLIDE 21

130 Kms 120 Kms 110 Kms Proposed Route for Interconnection

Madurai-New

Panaikulam

New Anuradhapura

Taliamannar Thirukketiswaram *

48 Kms

Madurai

India – Sri Lanka Interconnection

slide-22
SLIDE 22

22

Transmiss ansmission ion - Regula gulator tory y Com Compliance pliance

slide-23
SLIDE 23

Salient Provisions in Electricity Act, 2003

23

Provisions Article Intra-State and Inter-State Transmission System 2(36), 2(37 Duty of generating company include laying dedicated transmission lines 10 Transmission, Distribution and Trading are licensed activities 14 CTU/STU shall be the deemed licensees 14 Transmission licensee to comply with the directions

  • f RLDCs

29 Transmission licensee to comply with technical standards of CEA 34

slide-24
SLIDE 24

Salient Provisions in Electricity Act, 2003

  • Section – 40 : Duties of Transmission licensee -

(a) to build, maintain and operate an efficient, co-ordinated and economical inter-State transmission system or intra- State transmission system, as the case may be; (b) to comply with the directions of the Regional Load Despatch Centre and the State Load Despatch Centre as the case may be; (c) to provide non-discriminatory

  • pen

access to its transmission system

24

slide-25
SLIDE 25

Salient Provisions in Electricity Act, 2003

  • Section – 41 : Other business of transmission licensee

A transmission licensee may, with prior intimation to the Appropriate Commission , engage in any business for optimum utilisation of its assets: Provided that a proportion of the revenues derived from such business shall, as may be specified by the Appropriate Commission, be utilised for reducing its charges for transmission and wheeling: Provided further that the transmission licensee shall maintain separate accounts for each such business undertaking to ensure that transmission business neither subsidises in any way such business undertaking nor encumbers its transmission assets in any way to support such business: Provided also that no transmission licensee shall enter into any contract or otherwise engage in the business of trading in electricity :

25

slide-26
SLIDE 26

Transmission – 45 nos Conduct of Business – 24 nos Grid Operations – 16 nos Renewable Energy – 11 nos Power Trading – 6 nos Power Markets – 2 nos

CERC Regulations

Total 104 Nos

26

slide-27
SLIDE 27

Open Access Grant of License Tariff Determination Transmission Charges Sharing Power Supply Regulation Regulator approval Revenue from Other Business Standard of Performance Power System Development fund Filing of Annual Report

Transmission Regulations

27

slide-28
SLIDE 28

Grant of Transmission Licensee

  • Eligibility : No person shall be eligible for grant
  • f licence unless it is–

a) selected through the process under the guidelines for competitive bidding, or b) a state owned or controlled company identified as a project developer on or before 5.1.2011, or c) a generating company which has established the dedicated transmission line, and intends to use such dedicated transmission line as the main transmission line and part of the inter-State transmission system:

28

slide-29
SLIDE 29

Obligation of Transmission Licensee

1) Maintain Insurance 2) Build Project- Time bound, Efficient, Coordinated and Economical manner 3) Establish, Operate and Maintain - Prudent utility practices and the agreements. 4) Comply with directions of NLDC 5) Comply with all laws in force and, in particular,

a) the Act, b) the rules and regulations framed pursuant to the Act, c) the Grid Code, d) the standards, e) orders and directions issued by the Commission.

29

slide-30
SLIDE 30

Obligation of Transmission Licensee

1) Provide non-discriminatory open access to its transmission system 2) Pay the licence fee 3) Comply with all other regulations, including the regulations specified by the Commission regarding utilisation of the transmission assets for a business

  • ther than transmission of electricity

30

slide-31
SLIDE 31

Other Conditions

1) Not to enter into any contract or otherwise engage in the business of trading of electricity 2) In case of default by the licensee in debt repayment, the Commission may, on an application made by the lenders, assign the licence to a nominee of the lender

31

slide-32
SLIDE 32

32