Mock Stress Event

ESC with EMRS and National Grid 26 April 2018

slide-2
SLIDE 2

ELECTRICITY SETTLEMENTS COMPANY (ESC)

Nathalie Welch Senior Financial Analyst

26 April 2018

slide-3
SLIDE 3

3 www.lowcarboncontracts.uk

Contents

Electricity Settlements Company (ESC): 1. Introduction to Mock Stress Event (MSE) 2. Roles of the Delivery Partners 3. Key dates of the MSE Process National Grid (NG) 4. Mock Stress Activities 5. Mock Stress Tools 6. Overview of Mock Stress Event 7. Key Reminders EMRS 8. Timeline 9. Metering Pathway

  • 10. Where will the Capacity Volume Register be published
  • 11. What is Volume Reallocation?
  • 12. What will happen during the Volume Reallocation window?
  • 13. Timeline
  • 14. More information
slide-4
SLIDE 4

www.lowcarboncontracts.uk 4

Introduction to MSE

slide-5
SLIDE 5

Introduction to a MSE

What are we doing? We are conducting a full end to end test, this includes:

  • Multiple warnings will be sent from the System Operator (SO)
  • Evaluate and validate data submissions from Capacity Providers (CP)
  • Run the Volume Reallocation process
  • Test settlement calculations and penalty invoices

We will also test our published Working Practices (WP). Why are we doing this? To test all our processes to ensure we (both the Delivery Partners and Capacity Providers) are operationally ready in the event of a Stress Event occurring.

www.lowcarboncontracts.uk 5

?

slide-6
SLIDE 6

www.lowcarboncontracts.uk 6

Roles of the Delivery Partner

slide-7
SLIDE 7

Delivery partners: Roles and responsibilities

7 www.lowcarboncontracts.uk

The below table describes the individual roles of each Delivery Partner:

Electricity Settlements Company (ESC)

 Responsible for co-ordinating the

  • verall event, communication and

webinar  Responsible for communication to Industry partners (letter circulated and included signatories from EMRS and NG)  Share webinar plan and work with Delivery Body to finalise content  Run webinar for participants  Lessons learned workshop for Delivery Partners  Responsible for sharing the conclusion letter post workshop to Industry Partners

National Grid (NG)

 Responsible for issuing the MSE notification communication and in the Stress Event process  Responsible for issuing MSE notification email to participants  Responsible for Balancing Services  Lessons learned workshop for Delivery Partners

EMR Settlement Limited (EMRS)

 Responsible for managing the

  • peration of the Stress Event

Process.  Responsible for Data Submissions  Run Volume Reallocation process  Lessons learned workshop for Delivery Partners

slide-8
SLIDE 8

www.lowcarboncontracts.uk 8

Overview of our Processes

slide-9
SLIDE 9

Key dates of the MSE Process

www.lowcarboncontracts.uk 9

30 April: MSE notification sent to CP 14 May: Last day for CP to submit data 31 May: Mock penalty invoice issued Late June: Conclusion letter sent to CP

9 WDs after end

  • f the month

CVR published everyday from WD10-WD19

15 May: Volume Reallocation window opens – CVR published 29 May: Final day of Volume Reallocation 3 May: CP to submit their Balancing Service information to DB

slide-10
SLIDE 10

Any questions? Please email: Info@lowcarboncontracts.uk

10 www.lowcarboncontracts.uk

slide-11
SLIDE 11

11

EMR Delivery Body

Mock Stress event activities Ian Nicholas, Auction Delivery Manager

11

slide-12
SLIDE 12

Contents

Mock Stress Activities Mock Stress Tools Overview of Mock Stress event Key reminders to success

slide-13
SLIDE 13

Mock Stress Activities

  • EMR Delivery Body sends email to inform participants of the settlement

periods for the historic stress event

  • Participants that have a CM agreement in the current delivery year and were

carrying out a relevant balancing service need to send information to DB and EMRS

  • A tool will be provided for the both the Transitional Auction and the Early

Auction. https://www.emrdeliverybody.com/CM/DSR-Transitional-Auction-2016.aspx https://www.emrdeliverybody.com/CM/Early-Auction-2017.aspx

  • Participants need to fill in the details requested
  • Participants return template to DB within 3WD of Mock notice.
slide-14
SLIDE 14

Mock Stress Tool

The tool comes with guidance and a step through on its use

slide-15
SLIDE 15

Mock Stress Activities continued..

  • DB receives the data via the system stress event data capture tool and

carries out a data validation exercise

  • EMR DB deliver the data obligation to EMRS
  • DB submit this file to EMRS
  • SO submit data files to EMRS.

Volume reallocation DB manage the contact details (link) DB keeps the register for VR (link)

slide-16
SLIDE 16

Mock Notice +3 WD +5WD +9WD

EMRS carry out the settlement process

  • f over/under

delivery DB emails CPs confirming the historic Mock stress event periods affecting TA2 and EA DB create and send files to EMRS DB verify the data received against existing data; balancing services Participants start to collate the information required to send to DB Participants fill in provided tool and return to DB by WD3 SO create files for EMRS based on

  • ther data

requirements

slide-17
SLIDE 17

Key reminders to success

  • Participants fill in the correct tool as required
  • The data provided is real not mock data
  • The tool is returned within 3WD
  • The DB carry out the checking activity, and carry out data obligations for

EMRS

slide-18
SLIDE 18

Electricity Market Reform

DELIVERY BODY

Metering Assessments

If you have any questions about please contact the EMR team at: emr@nationalgrid.com +44 (0) 1926 655 300

Contact

Electricity Market Reform

DELIVERY BODY

slide-19
SLIDE 19

Mock Stress Event Webinar

26 April 2018 Hannah Pargeter

Public

slide-20
SLIDE 20

Timeline

30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12

Metered data submission window WD1 to WD9 Volume Reallocation window WD11 to WD19 Under-Delivery Penalty Invoice issued WD21 Capacity Volume Register published 5pm WD10 Final Capacity Volume Register published 5pm WD20 End of the month following System Stress Event Under-Delivery Payments Due WD26

slide-21
SLIDE 21

Metering Pathway

These are:

  • Balancing Mechanism Units (BMU)
  • Supplier Settlement (MPAN)
  • Self submission CSV (Balancing

Services and Bespoke)

ACTION: Submit your metered data by your elected pathway to EMRS from 1 May 2018 and no later than 14 May 2018. WP195: Capacity Market and CFD Metered Data

https://www.emrsettlement.co.uk/publications/ working-practices/

Illustrates the process steps for the submission of metered data:

System Operator and EMR Delivery Body interfaces

  • Monthly Capacity Market Warning & Stress Event Data
  • Monthly Involuntary Load Reduction Data
  • Monthly Interconnector Data during Stress Events
  • Monthly Stress Event Data
slide-22
SLIDE 22

Where will the Capacity Volume Register be published?

slide-23
SLIDE 23

What is Volume Reallocation?

Volume Reallocation and parameters are covered in Chapters 8 and 10 of the Capacity Market Rules.

  • A process where Capacity Providers may reallocate volume (in MWh) for any Settlement Period

that is part of a Stress Event from one over-delivering CMU to another under-delivering CMU.

  • Capacity Providers have the opportunity to reduce the amount of Penalty Charges they owe.
  • Volume Reallocation window opens 11 Working Days after the end of a month in which a Stress

Event occurs.

  • Capacity Providers who have over or under delivered may trade volume between each other.
  • Capacity Providers submit Capacity Market Volume Reallocation Notification (CMVRN) to EMRS

during the Volume Reallocation window.

slide-24
SLIDE 24

What will happen during the Volume Reallocation window?

Volume Reallocation webinar: https://www.emrsettlement.c

  • .uk/stakeholder-

support/emr-webinars/ WP48 - Volume Reallocation: https://www.emrsettlement.c

  • .uk/publications/working-

practices/

  • Volume Reallocation – 16 May 2018 to 29 May

2018

  • Contact details to trade between Capacity

Providers are available on the Volume Reallocation Register

  • Submit completed CMVRNs to EMRS from an

authorised contact with EMRS

  • CMVRNs received between 8:30am - 4pm will

be reflected in the CVR published by 5pm on that same day

  • CMVRNs received after 4pm will be processed

the following day

  • At 5pm on Working Day 19 EMRS will publish

the CVR with all trades received up to 4pm

slide-25
SLIDE 25

Timeline

30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12

Metered data submission window WD1 to WD9 Volume Reallocation window WD11 to WD19 Under-Delivery Penalty Invoice issued WD21 Capacity Volume Register published 5pm WD10 Final Capacity Volume Register published 5pm WD20 End of the month following System Stress Event Under-Delivery Payments Due WD26

slide-26
SLIDE 26

More information

Working Practices

  • WP48 - Volume Reallocation
  • WP195 – Capacity Market and CFD Metered Data

https://www.emrsettlement.co.uk/publications/working-practices/ Webinar

  • Volume Reallocation Process

https://www.emrsettlement.co.uk/stakeholder-support/emr-webinars/ Capacity Volume Register https://www.emrsettlement.co.uk/settlement-data/settlement-data- capacity-providers/ EMRS Service Desk