Missouri Residential Energy Code Baseline Study Update Meeting - - PowerPoint PPT Presentation

missouri residential energy code baseline study update
SMART_READER_LITE
LIVE PREVIEW

Missouri Residential Energy Code Baseline Study Update Meeting - - PowerPoint PPT Presentation

Missouri Residential Energy Code Baseline Study Update Meeting June 1, 2016 1 Welcome Brenda Wilbers, DED/DE 2 Presentation Topics Meeting Goals Review Goals & Rationale of Study Data Collection Update Overview of


slide-1
SLIDE 1

Missouri Residential Energy Code Baseline Study

Update Meeting June 1, 2016

1

slide-2
SLIDE 2

Welcome

Brenda Wilbers, DED/DE

2

slide-3
SLIDE 3

Presentation Topics

  • Meeting Goals
  • Review Goals & Rationale of Study
  • Data Collection Update
  • Overview of Preliminary Results
  • Sampling Plan Updates
  • Group Discussion
  • Next Steps / Collaboration

3

slide-4
SLIDE 4

Meeting Goals

  • Review the study and data collection plan with key

energy code stakeholders

  • Provide an update on preliminary findings, logistics
  • f data collection, and experiences in the field
  • Facilitate an efficient data collection process for the

remaining counties through stakeholder collaboration

4

slide-5
SLIDE 5

Overview of Project

  • DED/DE contracted with MEEA to conduct residential

study to determine current construction practices relative to 2009 IECC

  • Results from this study will be used to determine

statewide compliance with ARRA requirements

  • New single-family homes throughout Missouri

5

slide-6
SLIDE 6

Goals & Rationale of Study

  • Collect in-field construction data from random

sample of homes across Missouri

  • Obtain statistically-significant observations of 9 key

measures

  • All data collected will be anonymous and only

analyzed on statewide level

  • Use collected data as a basis to determine statewide

compliance with ARRA requirements

– The collected data will be analyzed by the Pacific Northwest National Laboratory on an energy use basis

6

slide-7
SLIDE 7

9 Key Items

  • Envelope Tightness

(ACH50)

  • Window U-Factor
  • Ceiling Insulation
  • Foundation Insulation
  • HVAC Right Sizing

(Manual J Block Load)

  • Window Solar Heat

Gain Coefficient (SHGC)

  • Exterior Wall

Insulation

  • High Efficacy Lighting
  • Duct Leakage

(CFM25)

7

slide-8
SLIDE 8

Study Structure and Timeline

  • DED/DE: Funding and general oversight of study
  • MEEA: Management of study & subcontractors
  • Matt Belcher: Outreach to builders & code officials

and coordinating site access

  • The Cadmus Group: On-site data collection

Data collection began April 6th and ends June 30th

8

slide-9
SLIDE 9

Map of where we have been so far

9

Data collection is 70% complete as

  • f 5/26/16
slide-10
SLIDE 10

Matt Belcher (Data Collection Facilitator)

10

slide-11
SLIDE 11

The Cadmus Group (Data Collector)

11

slide-12
SLIDE 12

Overview of Preliminary Results

12

slide-13
SLIDE 13

6 10 7 1 1 2 4 6 8 10 12 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39

Frequency ACH50

Preliminary - Blower Door Results (ACH50)

Orange Line = 2009 IECC (7 ACH50 maximum)

13

slide-14
SLIDE 14

1 4 2 1 1 2 9 1 2 3 4 5 6 7 8 9 10 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80

Frequency CFM25

Preliminary - Duct Leakage - Conditioned Space (CFM25)

Orange Line = 2009 IECC (12 CFM25 maximum)

14

slide-15
SLIDE 15

1 1 1 1 1 1 1 2 3 4 5 6 7 8 9 10 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80

Frequency CFM25

Preliminary - Duct Leakage - Unconditioned Space (CFM25)

Orange Line = 2009 IECC (12 CFM25 maximum)

15

slide-16
SLIDE 16

19 4 1 1 1 2 4 6 8 10 12 14 16 18 20 10 20 30 40 50 60 70 80 90 100

Frequency Percentage

Preliminary - High Efficacy Lighting (%)

Orange Line = 2009 IECC (50% minimum)

16

slide-17
SLIDE 17

22 1 2 5 10 15 20 25 12 13 14 15 16 17 18 19

Frequency R-Value

Preliminary - Wall Insulation - R-Value

Orange Line = 2009 IECC (R-13 minimum)

17

slide-18
SLIDE 18

Insulation Installation Grades

18

Diagrams from the HERS Standards

slide-19
SLIDE 19

7 15 3 2 4 6 8 10 12 14 16 1 2 3

Frequency Insulation Quality

Preliminary - Wall Insulation Quality

1 is the highest insulation quality, and 3 is the lowest insulation quality

19

slide-20
SLIDE 20

13 16 2 4 6 8 10 12 14 16 18 29 30 31 32 33 34 35 36 37 38 39

Frequency R-Value

Preliminary - Ceiling Insulation - R- Value

Orange Line = 2009 IECC (R-38 minimum)

20

slide-21
SLIDE 21

26 3 5 10 15 20 25 30 1 2 3

Frequency Insulation Quality

Preliminary - Ceiling Insulation Quality

1 is the highest insulation quality, and 3 is the lowest insulation quality

21

slide-22
SLIDE 22

20 8 2 5 10 15 20 25 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

Frequency R-Value

Preliminary - Basement Wall Insulation - R-Value

Orange Line = 2009 IECC (R-10 continuous minimum or R-12 cavity minimum)

22

slide-23
SLIDE 23

23

16 11 3 1 3 4 2 4 6 8 10 12 14 16 18 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100

Frequency AFUE

Preliminary - Furnace Efficiency (AFUE)

slide-24
SLIDE 24

24

1 1 5 3 2 1 5 2 1 1 6 1 2 3 4 5 6 7 0.28 0.29 0.3 0.31 0.32 0.33 0.34 0.35 0.36 0.37 0.38 0.39 0.4 0.41 0.42 0.43 0.44 0.45 0.46 0.47 0.48

Frequency U-Factor

Preliminary - Window U-Factor

Orange Line = 2009 IECC (.35 U-factor maximum)

slide-25
SLIDE 25

Enjoy The Break!

25

slide-26
SLIDE 26

Sampling Plan Methodology

  • Based on 2015 Census Permit Data
  • Only Single Family Homes
  • Permits are Weighted by County
  • Then Randomly Selected
  • Representative Cross-Section of Construction

26

slide-27
SLIDE 27

27

slide-28
SLIDE 28

County Substitution Process

  • So far the only substitution required is St. Louis City

– Lack of construction

  • Look for demographic similarity and reasonably

proximity

– Typically things like population, median income, owner

  • ccupancy rate, education, poverty level, density

– In this case a major consideration is a similar urban environment

  • Check for similar construction types and techniques

28

slide-29
SLIDE 29

Group Discussion

  • Feedback on sampling plan methodology and

preliminary results

  • Suggestions of partners/contacts to make

remaining data collection as efficient as possible

  • General discussion, feedback, and questions

29

slide-30
SLIDE 30

Next Steps

  • Field data collection continues

– Southwest Missouri, St. Louis city, other

  • MEEA will submit report to DED/DE in mid / late

summer 2016

  • PNNL will analyze final data

30

slide-31
SLIDE 31

Contact Information

  • Chris Burgess, MEEA – cburgess@mwalliance.org
  • Kelsey Horton, MEEA – khorton@mwalliance.org
  • Matt Belcher – belcherma@missouri.edu
  • Brenda Wilbers – brenda.wilbers@ded.mo.gov

31