Mirasol Village Redevelopment Project Update Report to SHRC A u g u s t 5 , 2 0 2 0 Mirasol Village 1200 Richards Rendering of Block A. Recent Accomplishments and Looking Forward Achievements The Year Ahead September 2020 Virtual


slide-1
SLIDE 1

Mirasol Village Redevelopment Project Update Report to SHRC

A u g u s t 5 , 2 0 2 0

slide-2
SLIDE 2
slide-3
SLIDE 3

Mirasol Village – 1200 Richards

Rendering of Block A.

slide-4
SLIDE 4

Recent Accomplishments and Looking Forward

Achievements

  • February 2020 –

Infrastructure contract start

  • April 2020 – Tax credit and

bond award for Block A

  • April 2020 – Convert to

Zoom meeting format

  • May 2020 - Execute Green

Infrastructure Grant for Mirasol Village Park; execute TCC Grant Agreement

  • June 2020 – Close financing;

start Blocks B/E construction

  • July 2020 – MHP award for

Block C The Year Ahead

  • September 2020 – Virtual

Groundbreaking

  • October 2020 – Start Block A
  • November 2020 – Complete

infrastructure construction

  • February 2021 – Start park and

garden construction

  • January 2021 – Apply for bonds

and tax credits for Block C

  • Late 2021
  • First set of residents move-in

Blocks B and E

  • Park & garden completion
  • Start Block C construction
slide-5
SLIDE 5

Neighborhood Updates

TCC funded projects

  • RT station design 65%

complete and Construction start (track realignment) 2021

  • NeighborWoods tree location

plan underway; added 566 more leverage trees

  • Community Garden site plan

approved by City; construction drawings 50%

  • Block A housing development

and Solar Installation start

  • Workforce Development MOU

finalized with SacRT

City projects

  • Salvation Army site

improvements completed

  • 12th Street ‘Complete Streets’

in pre-development, new fence at overpass, sidewalk and bike lane construction 2021

  • 12th Street Mural and Art

project planning underway

  • D Street basketball and

multi-sports court in 2021

  • Bus shelter, Route 11 service

expansion in 2022

slide-6
SLIDE 6
  • Major area of

focus for resident stability: economic mobility.

  • Reached the

60% mark at the beginning

  • f 2020 and

the pandemic came in March.

  • Why is the 60%

mark important?

People Strategy – Economic Mobility

36% 48% 54% 59% 60% 60% 57% 57% 58% 57% 55% 30% 35% 40% 45% 50% 55% 60% 65% 2016 2017 2018 2019 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20

Employment Rate

slide-7
SLIDE 7

People Strategy – COVID 19 Survey Results

Basic Needs

  • Households with enough food to last 7 days:
  • 80% March 2020 – 97% June 2020
  • Households with antibacterial soap or other disinfectants:
  • 66% March 2020 – 87% June 2020
  • Households with a 2-week supply of prescriptions:
  • 90% March 2020 – 100% June 2020

Households with School–Age Youth

  • Households with access to broadband internet at home:
  • 87% March 2020 – 100% June 2020
  • Households with access to a computer or tablet with internet

connectivity:

  • 73% March 2020 – 100% June 2020
  • Head of households &/or school-aged children required to do remote

learning:

  • 26% March 2020 – 96% June 2020