Miranova Condominiums Columbus, Ohio Chris Crilly Structural - - PowerPoint PPT Presentation

miranova condominiums
SMART_READER_LITE
LIVE PREVIEW

Miranova Condominiums Columbus, Ohio Chris Crilly Structural - - PowerPoint PPT Presentation

Miranova Condominiums Columbus, Ohio Chris Crilly Structural Option Spring 04 Presentation Outline Project Background Existing Conditions Problem Statement Goals Proposed Solution Floor System Lateral System Other Considerations


slide-1
SLIDE 1

Miranova Condominiums

Columbus, Ohio Structural Option Spring ‘04 Chris Crilly

slide-2
SLIDE 2

Presentation Outline

Goals Floor System Lateral System Acoustics Construction Management Acknowledgments Questions Existing Conditions Project Background Proposed Solution Other Considerations Summary/Conclusions Problem Statement

slide-3
SLIDE 3

Project Background

Columbus, Ohio Adjacent to I-70 Along Scioto River Faces North into the city Location

N

I-70

slide-4
SLIDE 4

Project Background

Size Gross Building Area Garage - 123,254 SF 5 Stories Tower - 332,862 SF 22 Stories Total - 456,116 SF 27 Stories Cost $52 Million Total Cost Groundbreaking was in July of 1998 Substantial Completion was in October of 2000 Tenant fit out continued into 2002 Construction Dates

slide-5
SLIDE 5

Project Background

Basement Visitor Parking Ground Floor Reception/Lobby Storage Social Spaces Offices Fitness Areas Levels 2-4 Resident Parking Small Storage Spaces Levels 5-28 Condominiums Building Occupancy Approximately 146 High-end Luxury Condominiums Approximately 226 Total parking Spaces

slide-6
SLIDE 6

Project Background

Design Architect – Arquitectonica Architect of Record – HKS Inc. Structural Engineer – The Thornton–Tomasetti Group MEP Engineer – Flack & Kurtz Consulting Engineers Lighting Designer – Lighting Design Alliance Civil Engineer – E M H & T, Inc. Construction Manager – Turner Construction Company Wind Tunnel Consultant – Cermak Peterka Peterson, Inc. Project Team

slide-7
SLIDE 7

Existing Conditions

North Façade – Blue Tinted Glass Curtain Wall Other Façades – 6” Precast Conc. Panels Level 1 – 5 120’ x 250’ Tower 60’ x 280’ 655’ Radius Architecture

slide-8
SLIDE 8

Existing Conditions

Concrete Mat Foundation f’c = 4000 psi – Normal Weight Concrete Placed on a 2” Mud Slab 5’-3” to 5’-9” thick under the tower 2’-9” to 3’-3” thick under 5 story portion Structure – Foundation

slide-9
SLIDE 9

Existing Conditions

8” Post-Tensioned Flat Plate f’c = 5000 psi – Normal Weight Conc. Post Tensioning ½” ∅, 270 ksi Low-Relaxation Strands Banded in 6’ Width over Col. Lines in E/W Direction Uniformly Spaced in N/S Direction Structure – Floor System

slide-10
SLIDE 10

Existing Conditions

Concrete Shear Walls f’c = 5000 psi – Normal Weight Conc. Thickness Decreases up the Building 22” to 12” Thick Structure – Lateral System

slide-11
SLIDE 11

Goals/Criteria

Possibility exists for owner to purchase to adjacent units and connect the two to make a larger living space

Problem Statement

Vertically – due to post-tensioned slabs Very difficult and expensive to execute future expansions: Horizontally – due to R/C shear walls

slide-12
SLIDE 12

Goals/Criteria

Allow greater and cheaper flexibility for possible future renovations

Goals

Vertically Horizontally Minimize impact on architecture Minimize impact on overall cost

slide-13
SLIDE 13

Proposed Solution

Steel Systems More flexible to future changes than concrete Easier to add openings for stairways and ducts Lighter

Floor System

Steel floor systems are typically deeper I will concentrate on Low Floor-to-Floor systems to minimize impact on architecture and cost

slide-14
SLIDE 14

Proposed Solution

Steel Braced Frames More flexible to future changes than concrete shear walls Easier to add openings for doorways Lighter

Lateral System

Braced frames allow for only discrete door locations I will concentrate on maximizing the area for door

  • penings for greater future flexibility
slide-15
SLIDE 15

Floor System

Composite Slab and Beam System Slight modification to Beam-Girder connections

  • ver typical connections

Reduces floor depth Reduces fabrication time and costs Connection L4x4x12x3” Erection Angle 3 – 1/2” ∅ Erection Bolts

slide-16
SLIDE 16

Floor System

Infill Beams (N-S Span Direction) W10 x 22 – Center Bay W10 x 17 or W10 x 19 – Outer Bays Girders (E-W Span Direction) W12 x 26 to W12 x 40 ∆EL b/w TopBeam and TopGirder 1.625” – 1.875” Allows for 1/8” Mill Tolerance 2” Max Required - 2” – 18 gage VLI Deck

slide-17
SLIDE 17

Floor System

Connection Check Yield Line Analysis Initially Studied by W. S. Easterling of Va. Tech. Followed up with Master’s Thesis by Wey-Jen Lee at Va. Tech

⎥ ⎥ ⎥ ⎥ ⎦ ⎤ ⎢ ⎢ ⎢ ⎢ ⎣ ⎡ − + =

g g b f y

b d b b t F R 2 1 4 2 2

2

R = Nominal Strength of Girder Flange Fy = Yield Strength of Girder tf = Thickness of Girder Flange bb = Width of Beam Flange bg = Length of Girder Flange (bf/2 – k1) D = Length of Beam Bearing φ = 0.9 - Assumed

slide-18
SLIDE 18

Floor System

These Capacities are CONSERVATIVE. Why?

Connection Check Connection Check

Beam Web Limit states were also checked and found to be OK Proven by experimental tests Bearing point is assumed to be at Center of Bearing Area Connection similar to un-stiffened seated connection Bearing point determined by beam web limits states simultaneously with bending limit state

slide-19
SLIDE 19

Floor System

Sound & Impact Transmission through floor system Investigated under Acoustic Breadth

Other Design Considerations

Floor Vibrations Typical beams checked Interior Bays Fell in upper half of barely perceptible range of the modified R-M scale

  • Max. acceleration – 0.339% < 0.5% OK

Exterior Bays Fell in lower half of slightly perceptible range of the modified R-M scale Max acceleration – 0.495% < 0.5% OK

slide-20
SLIDE 20

Floor System

A typical composite floor system was also designed Typical connections No depth restrictions Partially composite beams Same beam and girder layout was used

Typical Composite System

Infill Beams – W12x19 Girders – W16x26 to W16x30 Beam to Girder Connections – Shear Tab (3) – ¾” ∅ A325 Bolts PL – 3/8” x 4 ½” x 9” A36 5/16” fillet weld φRn = 27.8 k

slide-21
SLIDE 21

Floor System

Cost & Time Advantages Cost & Time Advantages

Shallow System Heavier Members Slightly more shear studs Less Connection Material Less Beam Fabrication (Copes) This was done to compare: Material costs Fabrication costs & Fabrication time

slide-22
SLIDE 22

Lateral System

Combination of R/C shear walls and steel braced frames Steel Braced Frames

Replace large shear walls in N-S Direction 3 options studied to:

  • Determine most efficient system
  • Determine most economical system
  • Maximize available space for future doors

Shear Walls

Keep existing walls around 2 building cores Walls added around building core

  • Better protection in emergencies
  • Stiffens building
slide-23
SLIDE 23

Lateral System

Option #1: All Braces Option #2: Outer Braces Center Brace – Same as

  • ption #1
slide-24
SLIDE 24

Lateral System

Option #3: Eccentrically Braced Frames Pros

4X area for doors in center frame 2X area for doors in outer frames Smaller Columns Acceptable building and story drifts

Design Summary

4 ft link in larger bay

  • Ext. Columns – W14x426 to W14x48
  • Int. Columns – 2 to 3 sizes smaller

Beams – W16x45 to W18x60 Braces – W12x40 to W12x45

Cons

Slightly larger beams

  • Approx. 2X # bracing connections
  • Approx. 2X # braces
slide-25
SLIDE 25

Lateral System Final Design

Outer Braces Center Brace

slide-26
SLIDE 26

Lateral System

Comparison b/w Existing and Proposed System

slide-27
SLIDE 27

Lateral System

slide-28
SLIDE 28

Level 5 Diaphragm

Existing Building used Wind Loads from wind tunnel test I used Code stipulated loads which were larger Change in lateral system at level 5 caused large shears in diaphragm Check proved existing diaphragm to be adequate

slide-29
SLIDE 29

Impacts on Arch.

15 ft Building height increase over 20 stories Locations of existing doors in shear walls had to be slightly moved to accommodate the braces, did not greatly impact space layouts 3 additional columns – easily hidden 8” increase in party wall thickness – 4” loss of living space on each side

slide-30
SLIDE 30

Acoustics

Building Code Design Criteria: STC 50 IIC 50 Fire Rating – 2 HR

Floor System

Recommended Design Criteria for Luxury Residences: STC 60 IIC 60

slide-31
SLIDE 31

Acoustics

Properties STC ≅ 62 IIC ≅ 74 – with carpet IIC ≅ 60 – with hard flooring on foam rubber underlay Fire Rating – UL No. D916 – 2 HR rating with 3 ½” slab

  • Actual slab is 4 ¼”
slide-32
SLIDE 32

Acoustics

Building Code Design Criteria: STC 50 Fire Rating – 1 HR

Brace Infill Wall

Properties: STC 60 Fire Rating – UL No. U411

  • 2 HR

Recommended Design Criteria for Luxury Residences: STC 60

slide-33
SLIDE 33
  • Constr. Management

Cost Estimate

Material Labor Equipment Total Floor Slab 1406825 1195081 194338 2796244 Columns 164808 147230 8420 320458 Shear Walls 209181 290109 10497 509787 Totals $1,780,814 $1,632,420 $213,255 $3,626,489

Existing Structure Cost

Material Fabricaction Erection/Labor Total Beams Gravity 328309 131203 114878 574390 Lateral 19723 1291 5253 26267 Braces 23495 2336 6458 32288 Columns Gravity 122870 1538 31102 155510 Lateral 62540 985 15881 79406 Connections 33276 108003 35320 176599 Shear Walls 201814 459507 661321 Floor Slab 926751 252953 1179703 Fire Protection 42251 28743 70994 Totals $1,761,028 $245,357 $950,095 $2,956,480 Square Ft. Cost = 8.88 $/SF

Steel Structure Cost

slide-34
SLIDE 34
  • Constr. Management

Cost Estimate

Item Unit Quantity Material Cost Labor Cost Gypsum Board (Cols.) SF 1815 0.42 762 0.34 617 Gypsum Board (Wall) SF 2480 0.42 1042 0.34 843 Glass Fiber Insulation (Ceiling) SF 14661 0.14 2053 0.37 5425 Glass Fiber Insulation (Wall) SF 2480 0.14 347 0.37 918 Precast Curtain Wall SF 348 25.50 8874 5.25 1827 Glass Curtain Wall SF 344 20.00 6880 6.00 2064 Totals/Story $19,958 $11,693 Totals/Building $399,153 $233,869

Additional Costs

slide-35
SLIDE 35
  • Constr. Management

Cost Estimate

Totals Structure Savings Total Savings Existing Structure $3,626,489 Steel Redesign $2,956,480 Additional Costs $633,022 $36,988 $670,010

Cost Savings

slide-36
SLIDE 36
  • Constr. Management

Site Logistics

Building Offices/Trailers Site Traffic Cranes Steel Shakeout Site Boundary

slide-37
SLIDE 37

Summary/Conclusion

Steel System Concrete System Better Option Total Weight 20% Lighter, Smaller Mat Foundation Possible

  • Steel

Ability to Accomadate Renovations Relatively Easy & Inexpensive Difficult & Expensive Steel Cost $37,000 Cheaper

  • Steel

Architectural Impacts 15 ft Height Increase, Larger Cladding Cost

  • Concrete

Acoustics Better Properties, but More Expensive Meets Criteria Steel Floor Vibrations Meets Criteria Not Typically a Problem in Concrete Concrete Construction Common System w/ Minor Modification Post-Tensioning Requires Skilled Labor Steel Schedule Requires Spray on Fire Proofing Requires Post-Tensioning Equal

System Comparison

slide-38
SLIDE 38

Summary/Conclusion Conclusion Bottom Flange Bearing Beam-to-Girder System With Eccentric Chevron Bracing in larger Bays

slide-39
SLIDE 39

Acknowledgments

AE Faculty

  • Dr. Geschwindner – for all of the help and guidance throughout the year
  • Dr. Hanagan – for guidance in understanding new connections

Courtney Burroughs – for guidance on acoustical design All other AE faculty – for getting me to the point where I could complete this

Project Team – for allowing me to use the building and providing required materials

  • Pizutti Companies
  • Robert Sedlak, Flack & Kurtz
  • Kirby Chadwell, HKS Inc.
  • Leighton Cochran, CPP
  • Aine Brazil, The Thornton-Tomasetti Group

Jeremy Smith, Altoona Pipe & Steel Co. – for all the help in estimating steel costs Melissa Toth, P.E. – for all the help, guidance and insight into the AE Thesis Experience My Parents – for guidance, support, and giving my the opportunity to attend PSU and make my dreams come true. Friends & Family – for all the support over the past five years Sarah Steeves – for putting up with me over the past few months while I was constantly busy with thesis

slide-40
SLIDE 40

Questions Miranova Condominiums

Columbus, Ohio Structural Option Spring ‘04 Chris Crilly

slide-41
SLIDE 41

Foundation

3 additional columns added Reduction of 250k to 750k in tower column loads Average of 250k net uplift in braced frame cols. Smaller loads would allow for significantly reduced thickness in mat at most locations Existing mat would require extra tension reinforcement to distribute uplift forces over area in which mat can resist them Wide flange or channel shapes

slide-42
SLIDE 42
  • Constr. Management

Other Issues

Steel Lead Time

Excavation and construction of foundation & first five stories will provide sufficient time for steel to be on sight Required lead time will not delay schedule

Schedule Impact

Only rough calculations performed Steel structure can be erected faster than existing concrete structure Additional gypsum board, glass fiber insulation, and curtain wall will add time to schedule Overall schedule construction duration not effected