Milton Road Local Liaison Forum 18 February 2019 Consultation Response Over 15,000 household received a consultation brochure 870 completed questionnaires were received and various events were held with good attendance All questions


slide-1
SLIDE 1

Milton Road

Local Liaison Forum

18 February 2019

slide-2
SLIDE 2

Consultation Response

  • Over 15,000 household received a consultation brochure
  • 870 completed questionnaires were received and various events were held with

good attendance

  • All questions gained more support that opposition with most questions gaining

significant support.

  • The project team have also talked in depth with Road Safety Officers, Signals

Team and Cycling Officers.

  • This engagement process has led to a number of design considerations which

were outlined and discussed at an LLF workshop in January 2019

slide-3
SLIDE 3

January Workshop Discussion

  • The first part of the LLF workshop dealt with proposed design

changes following comments received during the public consultation and also discussion with Safety, Signals, and Cycling

  • fficers at Cambridgeshire County Council
  • The second part covered landscaping proposals. The outcome of

the discussions has helped to inform the outline landscape proposals that are being recommended by officers.

slide-4
SLIDE 4

Modifications Summary

  • Detail of the modifications to the scheme following consultation feedback is

contained within the publish report that will be presented to the Joint Assembly, in summary, changes include:

  • Addition of signalised crossing near Westbrook Place and subsequent changes to the

design of Gilbert Road junction.

  • Additional space for pedestrians and cyclists at Elizabeth Way roundabout and removal
  • f shared use areas in favour of full segregation.
  • Slight modifications to the Arbury Road Junction, consistency with Gilbert Road
  • Addition of signalised crossing near Downhams Lane
  • Re-worked design for the area around Woodhead Drive to enhance the outbound bus

lane, shorten the inbound bus lane, and provide an uncontrolled crossing.

  • New design for pedestrians and cyclists at Kings Hedges junction.
  • Reduction of proposed shared use pavement to include only the section between

Ascham Road and Highworth Avenue

  • Minor modifications to the position of several bus stops
slide-5
SLIDE 5

Milton Road Design

slide-6
SLIDE 6

Programme and Timescales

Construction Executive Board

  • Detailed Design
  • Final Business Case
  • TRO’s
  • Contractor Procurement

Mar March Ap April il to

  • De

December 2019 March 2020 Early ly 2019 2019

Executive Board

slide-7
SLIDE 7