Milton Madison Bridge: Construction Update Aaron L. Stover, PE, SE - - PowerPoint PPT Presentation

milton madison bridge construction update
SMART_READER_LITE
LIVE PREVIEW

Milton Madison Bridge: Construction Update Aaron L. Stover, PE, SE - - PowerPoint PPT Presentation

2012 KYTC Partnering Conference September 11, 2012 Milton Madison Bridge: Construction Update Aaron L. Stover, PE, SE Michael Baker Jr., Inc. Agenda Project Overview Bridge Construction Process Project Challenges Project


slide-1
SLIDE 1

Aaron L. Stover, PE, SE

Michael Baker Jr., Inc.

Milton Madison Bridge: Construction Update

2012 KYTC Partnering Conference

September 11, 2012

slide-2
SLIDE 2

Agenda

  • Project Overview
  • Bridge Construction Process
  • Project Challenges
  • Project Successes
  • Upcoming Project Activities

2

slide-3
SLIDE 3

Markland Dam Project Site I-275 I-65 Cincinnati Louisville

Study Area

One of two Ohio River bridges between Cincinnati and Louisville

I-65 Bridge - 46 miles Markland Dam - 26 miles I-275 Bridge – 65 miles

3

Project Overview

slide-4
SLIDE 4

Project Timeline

  • June 2008 – Kickoff Environmental Process
  • Fall 2009 – Proposed Superstructure Replacement
  • February 2010 – TIGER Grant Funding Announced
  • September 2010 – Contractor Announced (Walsh)
  • January 2011 – Construction Began
  • April 25-29th 2012 – First Bridge Closure
  • June 25-29th – First Bridge Lift
  • Sept 10th– Second Bridge Lift
  • 2013 – New bridge Open to Traffic

4

slide-5
SLIDE 5

Project Purpose and Need

  • KYTC Structurally Deficient List
  • Weight Restriction

5

Structurally Deficient Functionally Obsolete

slide-6
SLIDE 6
  • Milton Approach re-construction
  • STR 1 replace KY Approaches
  • STR 2 Truss replacement

– Pier Strengthening and Scour Mitigation – Superstructure Replacement

6

Milton, KY Madison, IN

  • STR 3 – Replace IN Approaches
  • STR 4 – Pedestrian Access to Park

No Right-of-Way required 1 2 3 4

Selected Alternative: Superstructure Replacement

slide-7
SLIDE 7

12’-0”

LANE

8’-0”

SHOULDER

5’-0” 12’-0”

LANE

8’-0”

SHOULDER 7

Typical Section

  • Existing 20 ft curb to curb – Becomes 40 ft
  • 5 ft pedestrian walkway
  • 8 ft shoulders will accommodate bicyclists
slide-8
SLIDE 8

Selected Alternative

8

Existing Bridge Proposed Bridge

slide-9
SLIDE 9

Bridge Construction Process

9

slide-10
SLIDE 10

Design – Build Letting Summary

  • September 22, 2010
  • Five Contractors submitted bids
  • Formula for Effective Bid Price
  • lowest effective bid wins
  • [A + B – Adjustment]
  • A = construction cost ($102-$127 million)
  • B = closure days x $25,000/day. (365 days max)
  • Adjustment = $3.75 million for early opening

(Sept 2012 or May 2013)

10

slide-11
SLIDE 11

Project Partners

slide-12
SLIDE 12

Construction Overview

  • Strengthen existing piers
  • Innovative construction process:
  • Build a new truss on downstream piers while

the existing bridge remains open to traffic

  • Remove old truss and slide the new truss
  • nto the strengthened existing piers
  • Shorten closure periods (approx 10 days)

12

slide-13
SLIDE 13

13

Step 1

  • Pier strengthening and widening begins
  • Detour approach ramps are built on Vaughn Dr and KY 36
  • Existing bridge remains open to traffic

Construction Sequence

slide-14
SLIDE 14

14

Pier Strengthening

slide-15
SLIDE 15

15

slide-16
SLIDE 16

Madison Temporary Access Ramp

16

Courtesy Debbie Crawford

slide-17
SLIDE 17

Milton Temporary Access Ramp

17

Courtesy Debbie Crawford

slide-18
SLIDE 18

18

Step 2

  • Bridge closed to traffic for 5 days
  • Approach ramps are connected to existing bridge
  • Existing bridge reopens to traffic using approach ramps
  • Pier strengthening work continues

Construction Sequence

slide-19
SLIDE 19

Madison Demolition

19

slide-20
SLIDE 20

Madison Demolition

20

slide-21
SLIDE 21

21

Closure – Started off with a bang…

slide-22
SLIDE 22

Madison Demolition

22

slide-23
SLIDE 23

23

Truss Erection on Barges

slide-24
SLIDE 24

Truss Assembly Yard

24

slide-25
SLIDE 25

Span 2 Nearing Completion

25

slide-26
SLIDE 26

26

Step 3

  • Downstream bridge piers are constructed
  • Truss Erected on Downstream Piers

Construction Sequence

slide-27
SLIDE 27

27

slide-28
SLIDE 28

Temporary Towers - P3 & P4

28

slide-29
SLIDE 29

Sliding Girders

29

slide-30
SLIDE 30

30

slide-31
SLIDE 31

31

Step 3

  • Downstream bridge piers are constructed
  • Truss Erected on Downstream Piers

Construction Sequence

slide-32
SLIDE 32

Span 2 Truss Float Out

32

slide-33
SLIDE 33

Span 2 Lift (Animation)

33

slide-34
SLIDE 34

Span 2

34

slide-35
SLIDE 35

Truss Float

35

slide-36
SLIDE 36

Truss Float

36

slide-37
SLIDE 37

Span 3 Lift – 9/10/12

37

slide-38
SLIDE 38

Jacking Platform

38

slide-39
SLIDE 39

Sidewalk Superintendents

39

slide-40
SLIDE 40

Span 3 Float (Animation)

40

slide-41
SLIDE 41

Span 3 Lift (Animation)

41

slide-42
SLIDE 42

42

slide-43
SLIDE 43

43

slide-44
SLIDE 44

44

Step 4

  • Downstream bridge is connected to US 421
  • Traffic is rerouted onto downstream bridge

Construction Sequence

slide-45
SLIDE 45

45

Step 5 Existing bridge is demolished

  • Detour approach ramps are removed
  • Pier strengthening and widening is completed

Construction Sequence

slide-46
SLIDE 46

46

Step 6

  • bridge closed for 5 days
  • new truss superstructure is moved from

downstream piers to its permanent place

  • New Milton-Madison Bridge opens to traffic
  • Downstream piers are removed

Construction Sequence Bridge Slide

slide-47
SLIDE 47

47

slide-48
SLIDE 48

48 Pulling Strands Bearing Pulling Bracket

slide-49
SLIDE 49

Project Challenges

49

slide-50
SLIDE 50

50

8 flood events 131 Flood Days 20 days/yr allowed for in contract Record Rainfall

slide-51
SLIDE 51

Spring 2011 Flooding

51

slide-52
SLIDE 52

Project Successes

52

slide-53
SLIDE 53

Temporary Ramps Completed

53

slide-54
SLIDE 54

Lifts of Span 2 and Span 3

54

slide-55
SLIDE 55

Peregrine Falcons Hatched

55

slide-56
SLIDE 56

56

Next Steps?

Stick Build out the end spans Complete the Approach Spans Cast the Deck Switch Traffic to new Bridge

slide-57
SLIDE 57

57

For More Information

Visit the project website www.miltonmadisonbridge.com Follow us on Twitter @MMBridgeProject