milton madison bridge construction update
play

Milton Madison Bridge: Construction Update Aaron L. Stover, PE, SE - PowerPoint PPT Presentation

2012 KYTC Partnering Conference September 11, 2012 Milton Madison Bridge: Construction Update Aaron L. Stover, PE, SE Michael Baker Jr., Inc. Agenda Project Overview Bridge Construction Process Project Challenges Project


  1. 2012 KYTC Partnering Conference September 11, 2012 Milton Madison Bridge: Construction Update Aaron L. Stover, PE, SE Michael Baker Jr., Inc.

  2. Agenda  Project Overview  Bridge Construction Process  Project Challenges  Project Successes  Upcoming Project Activities 2

  3. Project Overview I-275 Cincinnati Project Site Markland Dam I-65 Study Area One of two Ohio River bridges between Cincinnati and Louisville Louisville I-65 Bridge - 46 miles Markland Dam - 26 miles I-275 Bridge – 65 miles 3

  4. Project Timeline  June 2008 – Kickoff Environmental Process  Fall 2009 – Proposed Superstructure Replacement  February 2010 – TIGER Grant Funding Announced  September 2010 – Contractor Announced (Walsh)  January 2011 – Construction Began  April 25-29th 2012 – First Bridge Closure  June 25-29th – First Bridge Lift  Sept 10th– Second Bridge Lift  2013 – New bridge Open to Traffic 4

  5. Project Purpose and Need  KYTC Structurally Deficient List  Weight Restriction Structurally Deficient Functionally Obsolete 5

  6. Selected Alternative: Superstructure Replacement 4 Milton, KY 2 Madison, IN 3 1 • STR 3 – Replace IN Approaches • Milton Approach re-construction • STR 1 replace KY Approaches • STR 4 – Pedestrian Access to Park • STR 2 Truss replacement – Pier Strengthening and Scour No Right-of-Way Mitigation required – Superstructure Replacement 6

  7. Typical Section  Existing 20 ft curb to curb – Becomes 40 ft  5 ft pedestrian walkway  8 ft shoulders will accommodate bicyclists 5’-0” 8’-0” 12’-0” 12’-0” 8’-0” SHOULDER LANE LANE SHOULDER 7

  8. Selected Alternative Existing Bridge Proposed Bridge 8

  9. Bridge Construction Process 9

  10. Design – Build Letting Summary  September 22, 2010  Five Contractors submitted bids  Formula for Effective Bid Price  lowest effective bid wins  [A + B – Adjustment]  A = construction cost ($102-$127 million)  B = closure days x $25,000/day. (365 days max)  Adjustment = $3.75 million for early opening (Sept 2012 or May 2013) 10

  11. Project Partners

  12. Construction Overview  Strengthen existing piers  Innovative construction process:  Build a new truss on downstream piers while the existing bridge remains open to traffic  Remove old truss and slide the new truss onto the strengthened existing piers  Shorten closure periods (approx 10 days) 12

  13. Construction Sequence Step 1 - Pier strengthening and widening begins - Detour approach ramps are built on Vaughn Dr and KY 36 - Existing bridge remains open to traffic 13

  14. Pier Strengthening 14

  15. 15

  16. Madison Temporary Access Ramp 16 Courtesy Debbie Crawford

  17. Milton Temporary Access Ramp 17 Courtesy Debbie Crawford

  18. Construction Sequence Step 2 - Bridge closed to traffic for 5 days - Approach ramps are connected to existing bridge - Existing bridge reopens to traffic using approach ramps - Pier strengthening work continues 18

  19. Madison Demolition 19

  20. Madison Demolition 20

  21. Closure – Started off with a bang… 21

  22. Madison Demolition 22

  23. Truss Erection on Barges 23

  24. Truss Assembly Yard 24

  25. Span 2 Nearing Completion 25

  26. Construction Sequence Step 3 - Downstream bridge piers are constructed -Truss Erected on Downstream Piers 26

  27. 27

  28. Temporary Towers - P3 & P4 28

  29. Sliding Girders 29

  30. 30

  31. Construction Sequence Step 3 -Downstream bridge piers are constructed - Truss Erected on Downstream Piers 31

  32. Span 2 Truss Float Out 32

  33. Span 2 Lift (Animation) 33

  34. Span 2 34

  35. Truss Float 35

  36. Truss Float 36

  37. Span 3 Lift – 9/10/12 37

  38. Jacking Platform 38

  39. Sidewalk Superintendents 39

  40. Span 3 Float (Animation) 40

  41. Span 3 Lift (Animation) 41

  42. 42

  43. 43

  44. Construction Sequence Step 4 - Downstream bridge is connected to US 421 -Traffic is rerouted onto downstream bridge 44

  45. Construction Sequence Step 5 Existing bridge is demolished - Detour approach ramps are removed - Pier strengthening and widening is completed 45

  46. Construction Sequence Bridge Slide Step 6 - bridge closed for 5 days new truss superstructure is moved from - downstream piers to its permanent place - New Milton-Madison Bridge opens to traffic - Downstream piers are removed 46

  47. 47

  48. Pulling Strands Bearing Pulling Bracket 48

  49. Project Challenges 49

  50. Record Rainfall 8 flood events 131 Flood Days 20 days/yr allowed for in contract 50

  51. Spring 2011 Flooding 51

  52. Project Successes 52

  53. Temporary Ramps Completed 53

  54. Lifts of Span 2 and Span 3 54

  55. Peregrine Falcons Hatched 55

  56. Next Steps? Stick Build out the end spans Complete the Approach Spans Cast the Deck Switch Traffic to new Bridge 56

  57. For More Information Visit the project website www.miltonmadisonbridge.com Follow us on Twitter @MMBridgeProject 57

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend