MIDAS Civil Curved Bridge Analysis Comparison of Methods & Construction Staging
Tom Less, PE, SE, ENV SP Team Leader, Bridge/Structural Engineer
MIDAS Civil Curved Bridge Analysis Comparison of Methods & - - PowerPoint PPT Presentation
MIDAS Civil Curved Bridge Analysis Comparison of Methods & Construction Staging Tom Less, PE, SE, ENV SP Team Leader, Bridge/Structural Engineer Introduction Curved Bridge Modeling Types of Models to be Discussed Traditional
Tom Less, PE, SE, ENV SP Team Leader, Bridge/Structural Engineer
Types of Models to be Discussed
Project Background – CVG CONRAC Unit 2
Construction Sequencing and Constructability
Project – ODOT GUE-513-08.65, Temporary Supports and Staged Construction Conclusions
Girder Line Modeling
a target utilization ratio (1.00 – anticipated V-Load increase)
composite bridges with radial crossframes or bracing
intermittent influence surface
V-Load Theory
apply external forces to induce resultant internal forces corresponding to the curved structure under vertical loads
Figure from Horizontally Curved I-Girder Bridge Analysis: V-Load Method By Grubb, M.A.
to MIDAS Civil or other FEM for larger radii, say R > 1000-ft
limitations which do not qualify for required analysis methods for curved structures and may underestimate deflections, reactions, twist
Grillage Analysis
nodes as beam elements, but with different offset (eccentric beam)
secondary virtual beams are used for load distribution
curvature are not captured
2D+ Grillage Analysis/Limited 3D Analysis
deck plates and nodes for crossframe members in 3D
virtual transverse beams
2D+ Grillage Analysis/Limited 3D Analysis Tip:
Renumber nodes & elements by beam/girder to 10001-10xxx (Girder 1) 20001-20xxx (Girder 2) Makes manipulation and
Full 3D Analysis
in addition to plates for the deck
highly curved members
Full 3D Analysis
Full 3D Analysis
Where to find in MIDAS:
CVG Airport (Cincinatti)
Original Condition Final Proposed Condition
MSE Buildup Three Elevated Structures
Unit 2: Curved Steel Plate Girder Bridge
Site and Geometric Constraints
Shop splice versus field splice considerations
cost effective
require 0.5”-0.625” thickness differential in field section from positive moment to negative moment.
than the V-load
Preliminary (V-Load) Final (Grillage/All-Plate)
aligned to MIDAS output
concatenation occurring during the wizard generation
into MIDAS menu, βi = 90 + tan-1(Δyi/Δxi); where Δyi and Δxi are distances from the MIDAS center point/origin to the nodal location (xi , yi).
be indicated on the plans for the fabricator.
I recommend the presentation by AISC, “Top 10 Changes in the 8th Edition AASHTO LRFD Steel Specifications” if you have not watched it. The handouts are available here: https://www.aisc.org/webinarhandouts121317/
camber from settling of the curved structure per AASHTO 6.7.7.3
Feature MIDAS LEAP Steel Tabular Input X Model Readily Accessible X Tabular Output X X Output Sorting Functions X Detailed Calculations Output X X Data Restricting Functions X Visual Output X Visual Display of Live Loads for Max Effect X
3% worst case
sizes, though utility (demand versus capacity) varied. This is due to program interpretations of several parameters, such as lateral bracing
stress
sacrificial haunch is 2-inches thick to make up for variations, and there is a 1/16-in tolerance on steel fabrication and 1/8-in tolerance on concrete, this is not as much of a concern in this case
critical for camber predictions
0.6Fy = 30 ksi, but overall combined stress was less than capacity
axis bending. For cases in which the elastically computed flange lateral bending stress is larger than approximately 0.6Fyf, the reduction in the major- axis bending tends to be greater than that determined based on these provisions. The service and strength limit state provisions of these Specifications are sufficient to ensure acceptable performance of I girders with elastically computed fl values somewhat larger than this limit.”
bending stresses were limited to around 10-20% over 0.6Fy, provided utility ratio remains below 1.0.
attempt to minimize effect of next pour in sequence
construction process, particularly for curved structures.
Figures from The Ohio Department of Transportation Bridge Design Manual
formwork on a web. Usually only a concern for deeper beams/girders.
Figure from The Ohio Department of Transportation Bridge Design Manual
formwork loads, and screed loads.
program developed by the Kansas DOT. This software is free, and can be downloaded at http://www.ksdot.org/kart
calculation is possible for items 1 and 3, with some limitations
Figure from The Ohio Department of Transportation Bridge Design Manual
into TAEG for just screed load and oil-canning as a very localized effect (between crossframes)
Stage 1 – Initial Steel Set Stage 2-1: Wet Concrete, Pour 1 Stage 2-2: Hardened Pour 1
Stage 2-3: Wet Concrete, Pour 2 Stage 2-4: Hardened Pour 2
Stage 2-5: Wet Concrete, Pour 3 Stage 2-6: Hardened Pour 3
Stage 2-7: Wet Concrete, Pour 4 Stage 2-8: Hardened Pour 4
moment, but would require 2x the inputs
line moment, then converted line moment into a line-force-couple to apply as edge loading
(10.4 x 10-3), however this is not a code provision, but engineer’s judgment
less
produced much higher rotations
final condition design, a full plate model is strongly recommended for evaluation of lateral deformation during construction sequencing
limit on rotations, but provide temporary timber blocking at
being poured
Lateral Rotation (Rad x 10-3) Stage Grillage+ All Plate Note Stage 1 0.502 2.969Steel Stage 2-1 3.318 18.617Pour 1 Stage 2-2 0.046 11.290 Stage 2-3 2.280 13.990Pour 2 Stage 2-4 0.230 9.350 Stage 2-5 2.155 13.476Pour 3 Stage 2-6 0.889 8.828 Stage 2-7 1.137 7.896Pour 4 Stage 2-8 0.187 8.616 Stage 3 0.238 6.434Final
analysis: single lane signalized. Needed ramp queue and red time clear analyses
to include cracked moment of inertia/stiffness, particularly for elastic analysis
composite beams, and steel temporary support all from the same model file.
stiffness of foundation was not included
foundation as well. This is possible in MIDAS through spring assignments at foundations.
positive contact with pier cap, grout under base plates for leveling
rods)
well as design multiple material types within a single model is very advantageous
small radii. Need to provide contingency for additional girder warping and internal force effects, but is still a useful tool in preliminary engineering
was faster to set up and run model but is more difficult to extract output and model is less readily available
and forces during construction, but underestimates girder rotation
during deck pour sequence
with common checker and final reviewer. Cross review by designers.