Metro Orange Line Extension Briefing and Construction Update September 14, 2010 Metro Orange Line Extension Project Highlights Four miles Busway and Bikeway Landscaping similar to Orange Line Four new Stations and three Bridges
Metro Orange Line Extension
Project Highlights
- Four miles Busway and Bikeway
- Four new Stations and three Bridges
- Park and Ride:
- Canoga – 257 spaces (608 existing)
- Sherman Way – 207 spaces
- Chatsworth – 610 spaces (130 new)
- Landscaping similar to Orange Line
- 45,500 average daily boardings in 2030
- 52 businesses relocated, 3 leases
amended and 26 billboards removed
- Budget $215.6 million
- Estimated completion Summer 2012
Metro Orange Line Extension
Accomplishments to date
Metro Orange Line Extension
Design Build Work is Underway
MOL - Typical Station Rendering
Metro Orange Line Extension
Orange Line Features
Metro Orange Line Extension
Station Platform at Chatsworth Station
Current View View at Completion
TH THREE EE SPA PAN BRID IDGE BRID IDGE APPR PROACH UN UNDERGROUN UND RELO ELOCATI TION OF CONFLIC LICTI TING OVERHEA EAD LIN LINES ES UP UPGRADE EXIS EXISTI TING AT-GRADE RAIL IL CROSSING ING (SCRRA) NEW EW TRAFF FFIC IC SIGN IGNAL CHATS TSWO WORTH TH BUS US STA TATI TION EXIS EXISTI TING CHATS TSWORTH TH METR TROLIN LINK STA TATI TION REA EALIG LIGN TR TRACK (SCRRA)
Metro Orange Line Extension
Lassen Street/Railroad Overcrossing Location
PR PRIV IVACY FE FENCE
Metro Orange Line Extension
Lassen Street Bridge
Metro Orange Line Extension
LA River Bridge and Santa Susana Creek Bridge
LOS ANGELES RIVER BRIDGE LOOKING EAST
Metro Orange Line Extension
Busway
Typical Busway Corridor Bikeway Looking from Canoga Ave
Existing Condition Busway landscaping Existing Condition Bikeway landscaping
Typical Cross Section
Metro Orange Line Extension
Canoga Station
Ticket Vending Machine CANOGA STATION By-pass Lane at Station Platform
Metro Orange Line Extension
Sherman Way, Roscoe and Nordoff Stations
SHERMAN WAY STATION NORDOFF STATION ROSCOE STATION
Busway Signage Busway Signage
Metro Orange Line Extension
Chatsworth Station
Bike Lockers Metro Pylon Sign
Porcelain enamel steel art panel Glass/stone mosaic ellipse- shaped paving
Locations of Artwork at Station Platform
Metro Orange Line Extension
Community Relations
Role of Construction Community Relations
- Active participant on construction management team.
- Facilitates construction activities and coordinates access requests.
- Liaison between project management and the community.
- Responds to the community in a timely manner.
- Keeps the public abreast of the most up-to-date construction information.
- Project briefings with offices of elected officials and community
stakeholders. Goals & Objectives
- Community Outreach prior to major construction on public right-of-way.
- Keeping neighbors informed as construction progresses.
- Minimizing construction impacts.
- Facilitating complaints.
Notifications
- Construction Notices
- Fact Sheets
- Detour & road closure information
- Safety Education Program