Metro Orange Line Extension Briefing and Construction Update September 14, 2010 Metro Orange Line Extension Project Highlights Four miles Busway and Bikeway Landscaping similar to Orange Line Four new Stations and three Bridges


slide-1
SLIDE 1

Metro Orange Line Extension

Briefing and Construction Update September 14, 2010

slide-2
SLIDE 2

Metro Orange Line Extension

Project Highlights

  • Four miles Busway and Bikeway
  • Four new Stations and three Bridges
  • Park and Ride:
  • Canoga – 257 spaces (608 existing)
  • Sherman Way – 207 spaces
  • Chatsworth – 610 spaces (130 new)
  • Landscaping similar to Orange Line
  • 45,500 average daily boardings in 2030
  • 52 businesses relocated, 3 leases

amended and 26 billboards removed

  • Budget $215.6 million
  • Estimated completion Summer 2012
slide-3
SLIDE 3

Metro Orange Line Extension

Accomplishments to date

slide-4
SLIDE 4

Metro Orange Line Extension

Design Build Work is Underway

slide-5
SLIDE 5

MOL - Typical Station Rendering

Metro Orange Line Extension

Orange Line Features

slide-6
SLIDE 6

Metro Orange Line Extension

Station Platform at Chatsworth Station

Current View View at Completion

slide-7
SLIDE 7

TH THREE EE SPA PAN BRID IDGE BRID IDGE APPR PROACH UN UNDERGROUN UND RELO ELOCATI TION OF CONFLIC LICTI TING OVERHEA EAD LIN LINES ES UP UPGRADE EXIS EXISTI TING AT-GRADE RAIL IL CROSSING ING (SCRRA) NEW EW TRAFF FFIC IC SIGN IGNAL CHATS TSWO WORTH TH BUS US STA TATI TION EXIS EXISTI TING CHATS TSWORTH TH METR TROLIN LINK STA TATI TION REA EALIG LIGN TR TRACK (SCRRA)

Metro Orange Line Extension

Lassen Street/Railroad Overcrossing Location

PR PRIV IVACY FE FENCE

slide-8
SLIDE 8

Metro Orange Line Extension

Lassen Street Bridge

slide-9
SLIDE 9

Metro Orange Line Extension

LA River Bridge and Santa Susana Creek Bridge

LOS ANGELES RIVER BRIDGE LOOKING EAST

slide-10
SLIDE 10

Metro Orange Line Extension

Busway

Typical Busway Corridor Bikeway Looking from Canoga Ave

Existing Condition Busway landscaping Existing Condition Bikeway landscaping

Typical Cross Section

slide-11
SLIDE 11

Metro Orange Line Extension

Canoga Station

Ticket Vending Machine CANOGA STATION By-pass Lane at Station Platform

slide-12
SLIDE 12

Metro Orange Line Extension

Sherman Way, Roscoe and Nordoff Stations

SHERMAN WAY STATION NORDOFF STATION ROSCOE STATION

Busway Signage Busway Signage

slide-13
SLIDE 13

Metro Orange Line Extension

Chatsworth Station

Bike Lockers Metro Pylon Sign

Porcelain enamel steel art panel Glass/stone mosaic ellipse- shaped paving

Locations of Artwork at Station Platform

slide-14
SLIDE 14

Metro Orange Line Extension

Community Relations

Role of Construction Community Relations

  • Active participant on construction management team.
  • Facilitates construction activities and coordinates access requests.
  • Liaison between project management and the community.
  • Responds to the community in a timely manner.
  • Keeps the public abreast of the most up-to-date construction information.
  • Project briefings with offices of elected officials and community

stakeholders. Goals & Objectives

  • Community Outreach prior to major construction on public right-of-way.
  • Keeping neighbors informed as construction progresses.
  • Minimizing construction impacts.
  • Facilitating complaints.

Notifications

  • Construction Notices
  • Fact Sheets
  • Detour & road closure information
  • Safety Education Program
slide-15
SLIDE 15

MOL Extension Hotline: 213.922.3668

On-call 24/7 for emergencies

Project E-mail: molextension@metro.net Project Webpage: www.metro.net/orangeext

Metro Orange Line Extension

How to reach us