MEP Means Coordination Jason Richards Peter Martin MEP Means - - PowerPoint PPT Presentation
MEP Means Coordination Jason Richards Peter Martin MEP Means - - PowerPoint PPT Presentation
MEP Means Coordination Jason Richards Peter Martin MEP Means Coordination Western Link, Hunterston & Flintshire Bridge 1 billion project bringing renewable energy from Scotland to England and Wales. Project will play a key role
SLIDE 1
SLIDE 2
MEP Means Coordination
SLIDE 3
Western Link, Hunterston & Flintshire Bridge
- £1 billion project bringing renewable energy from Scotland to England and Wales.
- Project will play a key role in helping the UK meet its renewable energy targets.
- Project includes DC subsea and underground cables, incorporating a converter station at each end.
SLIDE 4
Marine Cable
- Marine cable is 385km long.
- Longest 2,200MW capacity high voltage direct current cable in the world.
- First subsea link to use a DC voltage level of 600,000 volts.
- Sufficient electricity to meet the needs of around 2,000,000 people.
SLIDE 5
Converter Stations
- Stations convert DC electricity to AC to allow use in existing National grid system.
- Equipment had to be located internally to protect from the coastal salt damaging environment.
- Design for the converter stations was undertaken using Revit.
SLIDE 6
Federated Model
- Multi-discipline design involving Architects, Structural, MEP and client appointed specialist engineers.
- Multiple buildings were spread across two sites so shared coordinates had to be agreed and published to maintain alignment.
SLIDE 7
- Electrical equipment has very high heat gains.
- Natural ventilation was preferred but unachievable due to extreme external design conditions.
Thermal Modelling – Internal Environment
SLIDE 8
Project
- Large Residential regeneration
project – First development site; 6 blocks consisting high-rise, maisonettes and extra care facility. Engineering Challenges
- Site wide electrical demand could not
exceed existing.
- Emphasis placed on passive design
features to reduce the need for cooling; hence lower electrical demand. Lessons Learnt/Benefits
- CIBSE TM52 criteria used to assess
- verheating risk.
- External solar shading devices
modelled in IES to mitigate use of cooling.
Thermal Modelling – Occupant Comfort
SLIDE 9
- Subsequent to thermal modelling natural ventilation was ruled
- ut.
- All air mechanical ventilation system
- Large ducts to coordinate in small plant space.
- Revit enables detailed solution that would be impossible in 2D.
Plantrooms
SLIDE 10
Air Handling Units
- Very large Air handling units had to be accommodated.
- 4no. units 9.3m (L) x 6.5m (W) x 3m (H), 33 tonnes each supplying 42m3/s.
- Early collaboration with Structures in order to accommodate air handling units in model.
SLIDE 11
- Coordination of services with sensitive electrical equipment clearance zones.
- Any outages are business critical and would have serious implications.
- Clearance requirements based on record 2D sectional drawings.
2D Problem
SLIDE 12
- Created 3D Spheres in order to provide a visual aid and a means of clash detection.
- Real time model fly through presented to other disciplines to demonstrate coordination.
3D Solution
SLIDE 13
- Valve Hall – Ductwork drops coordinated around clearance zones, ductwork sizes,
- AHU plantroom duct external – had to get all fresh air intakes to one side and exhaust on other side
to prevent cross contamination of air.
- AHU plant room internal – provide internal 3D view of plantroom, any visible space left is retained
for maintenance and access requirements of the air handling units.