Membrane Bioreactor vs. Extended Aeration Treatment Pilot Study - - PowerPoint PPT Presentation

membrane bioreactor vs extended aeration treatment pilot
SMART_READER_LITE
LIVE PREVIEW

Membrane Bioreactor vs. Extended Aeration Treatment Pilot Study - - PowerPoint PPT Presentation

Membrane Bioreactor vs. Extended Aeration Treatment Pilot Study Effluent and Groundwater Quality Presenter Leslie Dumas September 15, 2009 Innovative Solutions for Water and the Environment Acknowledgements Thanks to: Colin Moy, REA.,


slide-1
SLIDE 1

Innovative Solutions for Water and the Environment

Membrane Bioreactor vs. Extended Aeration Treatment Pilot Study – Effluent and Groundwater Quality

Presenter

Leslie Dumas September 15, 2009

slide-2
SLIDE 2

Acknowledgements

Thanks to: Colin Moy, REA., East Bay Municipal Utility District [EBMUD] – Project Manager Eileen Fanelli, P.G., East Bay Municipal Utility District/Presidio Trust – Project Manager David W. Smith, Ph.D., Merritt Smith Consulting – Principal Investigator

slide-3
SLIDE 3

Background

  • WateReuse Foundation Project WRF-04-016
  • Project Title: Development of Regulatory

Protocol for Incidental Environmental Reuse of Title 22 Recycled Water

  • Issued August 2005 to EBMUD with RMC Water &

Environment

  • EBMUD’s ‘upcountry’ wastewater systems needs:
  • Upgrading systems to meet evolving regulatory requirements
  • Beneficial reuse of treated effluent
  • Use of small MBR treatment systems
slide-4
SLIDE 4

The Pardee Site

slide-5
SLIDE 5

Key Challenges to Recycling in California

  • Regulatory Compliance - Resolution #68-16

Antidegradation Policy

  • Cost-Benefit for Small Systems
  • Higher capital cost to implement MBR treatment
  • Little to no reduction in longer-term operating costs
  • Permitting costs increase overall capital costs
slide-6
SLIDE 6

Study Goals

  • Recognize baseline assumptions on meeting

CCR Title 22 standards for unrestricted use

  • Provide a standardized process (Framework) for

evaluating recycled water projects

  • Utilize established and industry-accepted tools

and practices for assessment

slide-7
SLIDE 7

A Two-Part Study Approach was Used

  • Develop a Framework (standardized process)
  • Conduct a Pilot Test
slide-8
SLIDE 8

Pilot Study Design

  • Conducted over 12 month period
  • Sampled and analyze influent, effluent and

groundwater quality from both existing and pilot systems

  • Apply data to Framework analysis
  • Identify key operating differences between the

extended aeration and MBR treatment plants

slide-9
SLIDE 9

Treatment Trains

Pilot MBR Plant Schematic PACT Extended Aeration Plant Schematic

slide-10
SLIDE 10

Conventional Plant

slide-11
SLIDE 11

Pilot Plant

slide-12
SLIDE 12

Pilot Plant

slide-13
SLIDE 13

Pilot Plant

slide-14
SLIDE 14

Pilot Plant

slide-15
SLIDE 15

Pilot Plant

slide-16
SLIDE 16

Pilot Program Analytical Plan

Parameter Influent Effluent Groundwater Settleable Solids (SS)  Total Suspended Solids (TSS)  pH    Dissolved Oxygen  Total Dissolved Solids (TDS)   Turbidity  Biological Oxygen Demand (BOD5)   Chemical Oxygen Demand (COD)   Total Organic Carbon (TOC)    Total Kjeldahl Nitrogen (TKN)    Ammonia (NH3 - N)    Nitrate (NO3 – N)   Total Coliform Bacteria (after disinfection)   Viruses (after disinfection)  General Minerals    Metals   Trihalomethanes (THMs)   Halogenic Acetic Acids (HAAs)   n-Nitrosodimethylamine (NDMA)  

slide-17
SLIDE 17

Influent W ater Quality Analysis

  • Influent quality was consistent throughout the

pilot study

  • Influent from PACT is found to be consistent with

a low-strength municipal wastewater

  • Constituent concentrations appear to be on the

same order of magnitude for both pre- and pilot- period influent data based on a trend analysis.

slide-18
SLIDE 18

Effluent W ater Quality Analysis

  • 1. Confirm the assumption that the MBR effluent

met disinfected tertiary-treatment criteria

  • 2. Identify the main differences in effluent quality

produced by the extended aeration and the MBR pilot systems

  • 3. Compare to groundwater quality over the pilot

study period

slide-19
SLIDE 19

Comparison of Expected and Actual MBR Effluent Quality

Parameter Units Published Expected Effluent Value Pilot MBR Effluent Quality Average Range BOD5 mg/L < 5 1.2 ND (< 2) - 2.2 TSS mg/L < 1 Not Sampled Not Sampled Ammonia mg/L as N < 1 0.63 ND (<0.3) - 6.72 Nitrate mg/L as N NA 30.03 0.19 – 53 Total Kjeldahl Nitrogen (TKN) mg/L as N NA 1.58 ND (< 1) – 11 Nitrite mg/L as N NA 0.16 ND (<0.0035) – 0.44 Total Nitrogen mg/L as N < 3 32.40* 0.19 – 71.16* Total Phosphorous (measured as Orthophosphate as P) mg/L < 0.2 6.8 1.7 - 9.9 Turbidity NTU < 0.2 0.34 0.13 – 1 Bacteria (measures as Total Coliform) Log removal Up to 6 log (99.9999%) 23.3 ND (< 2) – 230 Viruses Log removal Up to 3 log (99.9%) ND ND

slide-20
SLIDE 20

MBR Effluent W ater Quality Analysis

  • Results
  • Improved for clarity, aluminum removal

and BOD degradation

  • No difference for nitrogen, phosphates,

total dissolved solids and most metals

  • Reduction in lead, manganese, and
  • rthophosphate
  • Poor denitrification (no change in TKN,

ammonia and nitrate concentrations)

slide-21
SLIDE 21

Groundwater W ater Quality Analysis

  • Water quality analyzed to:
  • characterize groundwater quality for both the pre- and

MBR pilot periods

  • Identify statistical differences that could be

attributable to the MBR pilot system

  • The aquifer underlying the effluent pond is

composed fractured bedrock

  • Used major ionic species to ‘fingerprint’ the

water quality

slide-22
SLIDE 22

Piper Diagram shows no difference between pilot and pre-pilot groundwater quality

slide-23
SLIDE 23

Similar shaped Stiff Diagrams support the same conclusion

Pre-Pilot Data Pilot Data

slide-24
SLIDE 24

Groundwater Quality Results did not Reflect Change in Effluent Quality

  • Few anomalies observed, but longer

monitoring required to determine cause

  • Pre- and pilot effluent qualities are

significantly different from groundwater

  • No changes in groundwater quality may

be result of:

  • slight change in effluent chemistry
  • low volumes of effluent discharged to

pond

  • short monitoring period
slide-25
SLIDE 25

Study Conclusions

  • MBR system produced generally better effluent
  • MBR system was efficient in biodegradable and
  • rganic compounds removal
  • MBR was not efficient in phosphorus removal or

denitrification

  • Groundwater does not appear to be impacted by

either pre-pilot or pilot data over the monitoring period Based on testing, not reasonable to upgrade plant to achieve improved environmental results

slide-26
SLIDE 26

The Framework was Tested with Pilot Data

  • Highlighted need for

thorough data collection

  • Demonstrated

flexibility needed in developing the reuse scenario

slide-27
SLIDE 27

The Full Report

  • A Protocol for Estimating Potential Water Quality

Impacts of Recycled Water Projects: Final Report and Pilot Test Results; WateReuse Foundation: Alexandria, VA. 2009.

  • A Protocol for Estimating Potential Water Quality

Impacts of Recycled Water Projects: Framework and User Guidance; WateReuse Foundation: Alexandria ,VA. 2009.

slide-28
SLIDE 28

QUESTIONS?

slide-29
SLIDE 29

Framework Design

  • Internally consistent process
  • Early disclosure of potential impact
  • Allow project refinement to address possible

impacts

  • Rely on established analytical tools and

accepted industry practices

  • Apply on a constituent basis
  • Broadly applicable
  • Scalable relative to both project size and

number of constituents of potential concern

slide-30
SLIDE 30

Framework Analysis Process

Consists of two main elements

  • Preliminary Screening
  • Detailed Site Evaluation

Figure 1 – Framework Analysis Process Figure 1 – Framework Analysis Process

slide-31
SLIDE 31

Preliminary Screening

 Process

 Step 1 –Water Quantity Analysis  Step 2 –General Water Quality Analysis  Step 3 – Screen Applicable Guidelines and Regulations

 Assumptions

 Meets criteria for disinfected tertiary recycled water  Beneficial reuse for irrigation at agronomic rates  Storage not in a water of the United States

 Outcomes

 Identification of constituents of potential concern  Identification of applicable water quality goals and objectives  Identification of site-specific parameters for detailed analysis

slide-32
SLIDE 32

Detailed Site Analysis

 Process

 Step 4 –Prepare site assessment focused on vegetation,

soil geochemistry and soil hydraulics

 Step 5 –Complete the constituent analysis

 Assumptions

 Rely on site-specific data or literature values ,as

appropriate

 Outcomes

 Refine list of potential constituents of concern  Estimate short and long term magnitude of potential impact  Identify options for mitigating potential impacts

slide-33
SLIDE 33

Framework Tools

 Nutrients (nitrogen and phosphate)

 Nutrient budget

 Salts (measured by water and soil salinity & sodicity)

 Determination of leaching fraction relative to assimilative

capacity

 Metals (aluminum, copper, lead, nickel & zinc)

 Metals inventory and attenuation

 Organic carbon (as precursor for disinfection by-

products and HAA formation)

 Effluent organic matter (EfOM)