Meeting Presentation - Company Report & Overview of - - PowerPoint PPT Presentation

meeting
SMART_READER_LITE
LIVE PREVIEW

Meeting Presentation - Company Report & Overview of - - PowerPoint PPT Presentation

Stratford Coal CCC Meeting Presentation - Company Report & Overview of Activities April 2014 Jo Wiffen Environmental Officer Table of Contents Title 1. Agenda Item 7a (Progress at Mine) 2. Agenda Item 7b (Environmental


slide-1
SLIDE 1

Stratford Coal CCC Meeting

Jo Wiffen

Environmental Officer

April 2014

Presentation - Company Report & Overview of Activities

slide-2
SLIDE 2

Table of Contents Title

1. Agenda Item 7a (Progress at Mine) 2. Agenda Item 7b (Environmental Projects/Activities) 3. Agenda Item 7c (Environmental monitoring performance) 4. Agenda Item 7d (Community complaints) 5. Agenda Item 7e – (Other matters)

2

slide-3
SLIDE 3

28 April 2014

3

  • 1. Progress at the Mine

Mining 1st Quarter 201

  • Waste BCM 113,000 BCM
  • Coal tonnes 228,000 tonnes
  • Total BCM

275,000 BCM

  • BRN coal remaining to be mined approx 110k t and

scheduled for completion about June 14.

3

slide-4
SLIDE 4

28 April 2014

4

  • 2. Environmental Projects/Activities

4

Management Area Project Status Air Quality

  • Pollution Reduction Programs
  • Real-Time Dust Management
  • PRP U2 Haul road wheel generated dust monitoring – Three

rounds of monitoring completed with control efficiencies of 92%, 92% and 93%. Final report to demonstrate 80% control efficiency to be sent to EPA in August 14.

  • PRP U3 Handling overburden in adverse weather conditions –

Performance indicators for adverse weather conditions have been developed and weather station alarming established. Following an alarm being received an investigation would be undertaken to determine the need for any management measures.

  • No verified alarms have been received.

Flora

  • 2014 Noxious Weed Program
  • Commenced April – focusing on Giant Parramatta Grass &

Blackberry Fauna

  • 2014 Wild Dog Control Program
  • Commenced April 2014 (trapping)
  • Scheduled to be repeated later in 2014

Blast

  • Roseville West Pit
  • BRN Pit
  • Last blast completed 29 August 2013 – 24 blast for 2013, no

licence criteria exceedances

  • Blasting ongoing – 3 blasts for 2014, no licence criteria

exceedances Noise Mitigation works:-

  • CAT988 loader to 110dB
  • 5m ROM barrier; stockpiles maintained at 5m

height

  • Secondary crusher to 106 dB
  • Maintain southern coal stockpile at 137RL
  • Increase noise bund southern side of CHPP by

3m

  • Complete
  • Complete
  • Full replacement completed
  • Complete
  • Complete
slide-5
SLIDE 5

28 April 2014

5

  • 2. Environmental Projects/Activities – cont.

5

Management Area Project Status Noise

  • CAT D10 dozer to 110dB
  • New conveyors to be consistent with current low

noise technology

  • Duralie train unloading facility
  • Rail loop acoustic barriers
  • Low noise idlers on CV18 and CV17
  • Enclosure on coal loader
  • Real-Time Noise
  • Complete
  • Ongoing
  • Alsynite replaced with standard sheeting (complete).
  • Complete August 2013.
  • Noise assessment conducted with reductions of 9-16 dB

recorded.

  • Complete; 6dB gain achieved per conveyor
  • Completed February 2014.
  • System operational. No alarms received in last quarter.

Real-time noise monitoring profiles continue to be monitored and indicate no exceedence of the performance criteria due to mining operations. Lighting

  • Lighting optimisation (reductions)
  • Implementation of change to prevent daytime use of

exterior CHPP lighting.

  • Further optimisation work planned for night-time
  • perations
  • Stockpile lighting now controllable, lights turned off during

the day Rehabilitation

  • Roseville West Pit
  • BRN Pit
  • Old Main Pit
  • 5 Ha cover crop of millet established, planting of additional

pasture grasses completed

  • Planting of 13 Ha of native plant species completed
  • Reshaping of southern edge of main pit in progress,

planting of cover crop upon completion of shaping – May.

slide-6
SLIDE 6

28 April 2014

6

  • 3. Environmental Monitoring Performance

1.

Rainfall

2.

Surface Water a. Total Suspended Solids b. pH c. Electrical Conductivity

3.

Main Pit a. pH b. Electrical Conductivity c. Sulphate

4.

Reject Monitoring

5.

Air Quality a. Dust Deposition b. Dust Deposition – Petrographic Analysis c. High Volume Air Sampler d. High Volume Air Sampler-Rolling Average e. Real Time Dust Monitoring (TEOM) – PM2.5/PM 10

6.

Blasting a. Bowens Road North b. Roseville West

6

slide-7
SLIDE 7

28 April 2014

7

Rainfall

7

Average 2005 2008 2011 2014 200 400 600 800 1000 1200 1400

Year Rainfall (mm) Month

Rainfall 2003 - 2014

Average 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014

slide-8
SLIDE 8

28 April 2014

8

Surface Water – Total Suspended Solids

8

  • All sites returned generally low TSS
  • Gaps indicate no flow

5 10 15 20 25 30 35 40 Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

TSS (mg/L)

Sampling Month

Total Suspended Solids (TSS) - Avon River/Avondale Creek March 2013 - March 2014

W1 W2 W4 W5 W6

slide-9
SLIDE 9

28 April 2014

9

Surface Water - pH

9

  • All sites within ANZECC Guideline range.
  • No obvious trending toward ANZECC Guideline limits
  • Gaps indicate no flow

1 2 3 4 5 6 7 8 9 Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

pH

Sampling Month

pH - Avon River/Avondale Creek March 2013 - March 2014

W1 W2 W4 W5 W6

slide-10
SLIDE 10

28 April 2014

10

Surface Water – Electrical Conductivity

10

  • Gaps indicate no flow

200 400 600 800 1000 1200 1400 1600 Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

Electrical Conductivity (µS/cm)

Sampling Month

Electrical Conductivity - Avon River/Avondale Creek March 2013 - March 2014

W1 W2 W4 W5 W6

slide-11
SLIDE 11

28 April 2014

11

Main Pit - pH

11

  • Results show neutral pH; no decrease trend in pH

4.00 5.00 6.00 7.00 8.00 9.00 10.00 Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

pH

Sampling Month

Stratford Main Pit pH April 2013 - March 2014

slide-12
SLIDE 12

28 April 2014

12

Main Pit – Electrical Conductivity

12

  • All results within expected range.

500 1000 1500 2000 2500 3000 3500 4000 4500 Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

Electrical Conductivity (µS/cm)

Sampling Month

Stratford Main Pit Electrical Conductivity April 2013 - March 2014

slide-13
SLIDE 13

28 April 2014

13

Main Pit - Sulphate

13

  • All results within expected range.

200 400 600 800 1000 1200 1400 1600 Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

Sulphate (mg/L)

Sampling Month

Stratford Main Pit Sulphate April 2013 - March 2014

slide-14
SLIDE 14

28 April 2014

14

Reject Sampling

14

  • pH within expected range
  • No access January, April & June to October
  • Faulty pH probe in March – Reject Beach limed 12 March

1 2 3 4 5 6 7 8 9 10 Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar pH Sampling Month

Stratford Main Pit Reject Monitoring March 2013 - March 2014

Site 1 Site 2 Site 3 Site 4 Site 5

slide-15
SLIDE 15

28 April 2014

15

Air Quality – Dust Deposition

15

  • All sites below EPA limit
  • Samples with significant contamination excluded

0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Dust Deposition (g/m²/month) Sampling Month

Monthly Dust Deposition April 2013 - March 2014

D5 Straford Village D6 Mine D7 Isaac D8 Bramley D9 Craven D10 Williams D11 Ellis EPA Limit

slide-16
SLIDE 16

28 April 2014

16

Air Quality – Petrographic Analysis

16 Samples are examined under a stereo-microscope (50x) to determine the nature

  • f the dust deposits.

The relative amount of dust deposits on the filter paper is described as: Trace

  • traces only on filter paper

Light

  • thin cover over most of the filter paper

Moderate

  • thin cover over filter paper

Heavy

  • thicker cover over filter paper

The dust is grouped into:

  • coal
  • inorganic (clays, etc.)
  • insect and plant remains

The proportions are described as: Major - >30% Minor - 5% - 30% Trace - <5% Slight trace- <1% Note: Estimated percentages are considered as: 5% +/- 2% 10% +/- 5% 30% to 80% +/- 10% 90% +/- 5% 95% +/- 2%

Sample Deposit Coal Minerals; quartz, clay, etc. Insect & Plant Remains

D5 PETRO (19/12/13 - 17/01/2014) Very light Light grey/brown Angular to sub- rounded. 0.2 - <0.01 mm; generally <0.1mm. Minor, 10% - 15% Sub-angular to rounded. 0.25 - <0.01 mm; generally <0.1mm. Minor, 20% - 25% Mainly plant fragments, minor insect fragments. Major, 60% - 70% D5 PETRO (17/01/2014

  • 17/02/2014)

Very light Light grey/brown Angular to sub- rounded. 0.3 - <0.01 mm; generally 0.1 - 0.2 mm. Minor, 5% - 7% Sub-angular to rounded. 0.2 - <0.01 mm; generally <0.1mm. Minor, 15% - 20% Mainly plant fragments, minor insects & insect fragments. Major, 70% - 80% D5 PETRO (17/02/14 - 17/03/14) Very light Light grey Angular to sub- rounded. 0.2 - <0.01 mm; generally <0.1mm. Trace, 2% - 3% Sub-angular to rounded. 0.2 - <0.01 mm; generally <0.1mm. Minor, 15% - 20% Mainly insects and fragments, insect fragments minor. Major, 75% - 80%

slide-17
SLIDE 17

28 April 2014

17

Air Quality – High Volume Air Sampler

17

  • All sites generally well below NEPM 24hr average level.
  • Spike in October due to smoke from Hunter Valley fires being blown up into Gloucester Valley.

0.0 10.0 20.0 30.0 40.0 50.0 60.0

Particulate Matter PM10 (µg/m³)

Sampling Date

High Volume Dust Monitoring - Particulate Matter (PM10) March 2013 - March 2014

Stratford Craven Ellis Clarke NEPM 24 hr Avg

slide-18
SLIDE 18

28 April 2014

18

Air Quality – HVAS Rolling Average

18

  • All site averages well below EPA Limit

0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00

4-Mar-13 18-Mar-13 1-Apr-13 15-Apr-13 29-Apr-13 13-May-13 27-May-13 10-Jun-13 24-Jun-13 8-Jul-13 22-Jul-13 5-Aug-13 19-Aug-13 2-Sep-13 16-Sep-13 30-Sep-13 14-Oct-13 28-Oct-13 11-Nov-13 25-Nov-13 9-Dec-13 23-Dec-13 6-Jan-14 20-Jan-14 3-Feb-14 17-Feb-14 3-Mar-14 17-Mar-14

Particulate Matter PM10 (µg/m³)

Sampling Date

High Volume Dust Monitoring Particulate Matter (PM10) Rolling Average March 2013 - March 2014

Stratford Craven Ellis Clarke EPA Limit

slide-19
SLIDE 19

28 April 2014

19

Air Quality – TEOM (Real Time) Monitoring

19

  • Zero/negative values are due to moisture vapour/dew drying on filter creating small

negative mass readings.

10 20 30 40 50 60 70 80 90 100 µg/m³ Sampling Date

TEOM (Real Time) Dust Monitoring - Hourly averaged PM2.5/PM10 April 2013 - March 2014

PM2.5 PM10

slide-20
SLIDE 20

28 April 2014

20

Blasting – Bowens Road North Pit

20

Note: Blast Compliance: No more than 5% of total blasts for annual monitoring period to exceed an overpressure of 115 dBL or ground vibration of 5 mm/s. No blast is to exceed an overpressure of 120 dBL or ground vibration of 10 mm/s

Date Ellis Clarke Falla Ex-Judge Isaac Exceedances % >115dbL Exceedances % >120dbL mm/s dBL mm/s dBL mm/s dBL mm/s dBL mm/s dBL BRN 20-Nov-13 0.262 100.6 0.115 100.2 0.59 93.4 0.213 90.6 0.164 104.4 27-Nov-13 0.228 104.7 0.099 100.2 <0.21 <110.0 0.099 95.8 0.079 97.7 13-Dec-13 0.483 91.5 0.199 102.4 <0.21 <110.0 0.137 98.5 0.159 107.7 15-Jan-14 0.39 99.7 0.13 104.5 0.38 96.2 0.28 91.9 0.21 95.4 15-Jan-14 0.17 105.0 0.09 102.9 0.23 92.3 0.12 99.6 0.07 98.3 4-Feb-14 0.211 108.2 0.104 105.6 <0.21 <110.0 0.104 107.5 0.053 111.1 11-Mar-14 0.313 100.2 0.125 103.3 0.31 97.7 0.13 98.5 0.088 102.6

slide-21
SLIDE 21

28 April 2014

21

Blasting – Roseville West Pit

21

Note: Blast Compliance: No more than 5% of total blasts for annual monitoring period to exceed an overpressure of 115 dBL or ground vibration of 5 mm/s. No blast is to exceed an overpressure of 120 dBL or ground vibration of 10 mm/s

Date Ellis Clarke Falla Ex-Judge Isaac Exceedances % >115dbL Exceedances % >120dbL mm/s dBL mm/s dBL mm/s dBL mm/s dBL mm/s dBL Roseville 04-Jul-13 0.12 89.7 0.094 93.8 0.42 101.3 0.324 98 0.329 81.6 11-Jul-13 0.101 97.3 0.094 100.3 0.62 102.3 0.318 99.3 0.356 87.7 18-Jul-13 0.096 95.8 0.11 98.7 0.44 105.2 0.321 103 0.326 97.2 25-Jul-13 0.101 93.8 0.089 96.6 0.39 103.8 0.37 99.3 0.408 93.7 08-Aug-13 <0.23 <109.8 <0.22 <110.0 0.50 111.5 0.402 105 0.531 105.2. 29-Aug-13 0.41 96.6 <0.22 <110.0 0.39 103.1 0.314 99.8 0.295 97.9

slide-22
SLIDE 22

28 April 2014

22

22

  • 4. Community Complaints

Stratford Complaint Summary

Period: 1/01/14 - 15/04/14 Total No. of Complaints: 1 (noise) Total No. of Complainants: 1 Time/Date of Complaint Complainant Location Method of Complaint Nature of Complaint Outcome

2222hrs 22/03/2014 Approx 2.7km SW of Stratford CHPP SMS to Mark Jacobs "Hi Mark. Your Coal train is making an enormous amount of noise tonight :(" Investigation indicates operations likely to be within required limits Noise source likely to be Pacific National export train whilst still on the main northern line (train arrived at load point 2225hrs with loading commencing at 2236hrs) Internal review continuing and to be finalised prior to formal response to complainant