MEASURE L BOND UPDATE August 13, 2019 Measure L Overview Project Updates Program Schedule Review Measure L Project Updates Cherrywood Elementary School - FIS Completion August 30, 2019 In progress: Elevator


slide-1
SLIDE 1

MEASURE L BOND UPDATE

August 13, 2019

slide-2
SLIDE 2

Measure L – Overview

  • Project Updates
  • Program Schedule Review
slide-3
SLIDE 3

Measure L – Project Updates

Cherrywood Elementary School - FIS

  • Completion August 30, 2019
  • In progress:
  • Elevator
  • Ceilings
  • Painting
  • Flooring
  • Finish Plumbing
  • HVAC
  • Lighting
  • Fire Alarm
slide-4
SLIDE 4

Measure L – Project Updates

Cherrywood FIS – FIS Space Looking Up at FIS

slide-5
SLIDE 5

Measure L – Project Updates

Cherrywood FIS – FIS Space Looking East- August

slide-6
SLIDE 6

Measure L – Project Updates

Cherrywood FIS – Kitchen Area - August

slide-7
SLIDE 7

Measure L – Project Updates

Toyon Elementary School - FIS

  • Grass installation – Complete
  • Twinkle Lights – Completion August 16, 2019

Brooktree Elementary School - FIS

  • Printed ceiling tiles replacement - Complete

Morrill

  • Library desk - Complete

Piedmont Parking Lot

  • In use as of Monday, August 5, 2019
  • Progress:
  • Landscaping
  • New Driveway Approach
slide-8
SLIDE 8

Measure L – Project Updates

Morrill Library Desk

slide-9
SLIDE 9

Measure L – Project Updates

Toyon FIS

slide-10
SLIDE 10

Measure L – Project Updates

Piedmont Parking Lot

slide-11
SLIDE 11

Measure L – Project Updates

Additional Projects

  • Completed Projects
  • Plumbing Projects
  • Cherrywood – Hot water line replacement
  • Backflow preventer's – Complete @ Piedmont and Sierramont
  • Paving – Laneview - upper pavement replacement at delivery area
  • Fertigation System
  • In Progress:
  • Traffic Gates – BT, CW, NW, SD, VP, and MM
  • Cafeteria Tables
  • Portable Restroom Replacement @ Brooktree
  • Wireless thermostat's at portables
slide-12
SLIDE 12

Project Updates

Northwood Elementary School – Portable Relocation

  • Complete:
  • Driveway and fencing at southwest corner of site along Lakewood

Drive

slide-13
SLIDE 13

Measure L – Program Schedule

Design Preconstruction Furniture Design DSA Review Construction Quote Pricing Bid Start of School PO Generated Award Punch List

Construction Projects

1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 5 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4 5 Pie dm ont Parking I m provem ents Che r ry wood FI S/ Modernization Additiona l Proj e cts Tr a ffic Ga te s BT, CW, NW SD, BP, MM NB, PM, SM Ca fe te ria Ta ble Re pla ce m e nt Libra ry She lv ing HVAC Proj e cts Toyon Morrill Plum bing Pr oj e cts Cherrywood - Water line replacem ent Backflow Preventer - Piedm ont Backflow Preventer - Morrill Por ta ble Re str oom Re pla ce m e nt @ Brook tr e e Pe r im e te r Fe ncing Cherrywood Laneview Noble Ruskin Sierram ont Pa v ing - La ne v ie w Upper delivery Area S Staff Parking Lot Wir e le ss The r m osta t @ Porta ble s Ma in Ala r m Se cur ity Pa ne l Re pla ce m e nt Fe r tiga tion Sy ste m - Mor rill Lunch Sha de Str ucture s Noble Ruskin Morrill

Furniture Projects

FI S Furniture - Cherrywood Week Week Week November November December Week Week Week Week Week Week Week Week Week Week Week Week Week Week June July August September October January February March April May August September October December

2 0 2 0 2 0 1 9

Construction Legend Furniture Legend

slide-14
SLIDE 14