Master Plan & V Visioning Study
- F. H . T U T T L E M I D D L E S C H O O L
A N D
S O U T H B U RL I N G T O N H I G H S C H O O L
Public In Information Session
11 April 2019
Master Plan & V Visioning Study F. H . T U T T L E M I D D L E - - PowerPoint PPT Presentation
Master Plan & V Visioning Study F. H . T U T T L E M I D D L E S C H O O L A N D S O U T H B U RL I N G T O N H I G H S C H O O L Public In Information Session 11 April 2019 Overview Topics Welcome Study Process Master Plan
Master Plan & V Visioning Study
A N D
S O U T H B U RL I N G T O N H I G H S C H O O L
Public In Information Session
11 April 2019
Overview Topics
Overview Topics
PHASE 1 - Physical Site & Building Assessment:
capital improvements? PHASE 2 - Educational Program Assessment:
(i.e. achievement of the District’s Ends)?
educational practices and facilities?
Overview Topics
Development
Input
Study Process- Master Plan
PHASE II
Education & Options
PHASE I
Physical Building
Nov / Dec / Jan / Feb / Mar / Apr / May / Jun / Jul / Aug / Sep / Oct / Nov / Dec / Jan / Feb / Mar / Apr / May / Jun 2017 2018 2019
SBHS and Tuttle MS
Phase 1 Physical Building Condition
to last 25 to 35 years before needing replacement.
design life
Existing Conditions Overview
151,500 sf building 1960 Original Building 1977-78 Reno/Add Grades 9-12 942 Students
South Burlington High School
1960: 91,400 sf 1977-78: 59,500 sf 1995 +/-(?): 600 sf Total: 151,500 sf
1960 Original Building and 1977-78 Addition
First Floor Second Floor
Key
Bus Route Bus Drop Parent Route Parent Drop Student Route Student ParkingLA LANDSCAPE/CIVIL South Bu Burlington Hig High Sc School
walls
infiltration
STRUCTURAL So South Bu Burli lington Hig High Sc School
throughout the building (some units
Gym, Cafeteria, Kitchen, Library, and Science Wing
leaky air intakes
classrooms to central mechanical system
MECHANIC ICAL So South Bu Burli lington Hig High Sc School
sprinkler system; Original 1960 building does not.
building to be fully sprinklered
valves
with new- independent of boiler
kitchen- independent of boiler
conserving types
PL PLUMBIN ING / FIR FIRE PR PROTECT CTION S South Bu Burlington Hig High Sc Schoo
vintage: should be replaced (designed at 3,000A; now using 400A.
and additional devices added
recommended with IP cameras
cloud recording is recommended ELE ELECTRICAL Sou South Bu Burlin ington Hig High Sch School
in near future
entrance changes recommended for security and longevity
ARCHITECT CTURAL - Ext Exterior So South Bu Burli lington Hig High Sc School
exceeding lifespan
in need up complete upgrade
made: more to be done (i.e. auditorium, band rooms, access to several areas in center of building, toilet rooms, clearance at doors, etc.)
equipment ARCHITECT CTURAL - In Interior
So South Bu Burli lington Hig High Sc School
120,552 sf building 1967 Original Building 6-8 555 Students
F.H. Tuttle Middle School
Key
Bus Route Bus Drop Parent Route Parent DropLA LANDSCAPE/CIVIL FH Tuttle le Mid iddle le Sc School
condition
pedestrian path crossing bus and car path through parking lot
walking paths recommended from parking to building
Key
Bus Route Bus Drop Parent Route Parent DropLA LANDSCAPE/CIVIL FH Tuttle le Mid iddle le Sc School
condition
pedestrian path crossing bus and car path through parking lot
walking paths recommended from parking to building
STRUCTURAL FH FH Tuttle le Mid iddle Sc School
Generally exterior and interior walls are in good condition; structure is solid.
walls
STRUCTURAL FH FH Tuttle le Mid iddle Sc School
pneumatic system
burners as planned; excellent energy savings
equipment, exhaust fans, dampers, actuators and associated equipment
MECHANIC ICAL F FH Tuttle Mid iddle Sch School
air louvers; tend to freeze
serving the boiler and storage rooms
require the building to be fully sprinklered
valves at both boiler room and plumbing system
new- independent of boiler
system and address
PL PLUMBIN ING / FIR FIRE PR PROTECT CTION F FH Tuttle le Mid iddle le Sc School
distribution system components
due to tripping circuit breakers
upgraded and additional devices added; this is ongoing
recommended with IP cameras
cloud recording is recommended ELE ELECTRICAL FH FH Tuttle Mid iddle Sc School
exceeding service life
life-, ponding, shrinking/double roof
system deteriorating
entrance changes recommended for security, comfort and longevity
ARCHITECT CTURAL - Ext Exterior FH Tuttle Mid iddle Sch School
surface; throughout building
and in need up complete upgrade
safety concern
(door clearance, access to platform, toilet rooms, steps in corridors, casework, etc.) ARCHITECT CTURAL - In Interior
FH FH Tuttle Mid iddle Sc School
Site and Building Assessment Ph Ph 1 Summary
Overview Summary of Assessment
What has changed since original construction?
SBHS and Tuttle MS
Phase 2 Educational Space Assessment and Options
Phase 2 Info Gathering
enrollment projections FHTMS
5th Grade Enrollment Projections
2018-2019Enrollment projections – SBHS
2018-2019Building Capacity Analysis Tuttle MS
FH Tuttle Middle School
*School Capacity 575 Students
Students
Existing 120,552 sf
*Based on VT DOE guidelines of 160 sf/student
Tuttle MS
10 Year Enrollment Projections 632 750 Current Enrollment
Existing 158,542 sf
Students
880 Students
*Based on VT DOE guidelines of 180 sf/studentSBHS
921 1045 10 year Enrollment Projections Current Enrollment *School Capacity
Building Capacity Analysis SBHS
South Burlington School District
District Ends Po Policy: 1.1 Disposition for Life-long Learning 1.2 Academic Proficiency 1.3 Personal Development 1.4 Citizenship
SBHS and Tuttle MS
Educational Vision
1st Floor – SBHS – 1960 and today
e n g a g e d c i t i z e n s
effective communicators
South Burlington School District
District Ends Po Policy: 1.1 Disposition for Life-long Learning 1.2 Academic Proficiency 1.3 Personal Development 1.4 Citizenship
1st Floor – SBHS – 1960 and today
1960’s “Stand and Deliver” Teaching ; Not designed to include: Special Education, Remedial Assistance, Project Based Learning, Computers
Does this layout encourage collaboration?
1st Floor – SBHS – 1960 and today
1960’s “Stand and Deliver” Teaching ; Not designed to include: Special Education, Remedial Assistance, Project Based Learning, Computers
Does this layout encourage collaboration?
If we teach today’s students as we taught yesterday’s, we rob them of tomorrow.
—John Dewey
It requires the integration of: SCIENCE TECHNOLOGY ENGINEERING ART
RT
MATH
Middle School: Collaboration Space - FHTMS
New Vision: STEM LAB
Existing Science Space
New Vision: STEM LAB
Next Generation Collaboration Space
Community, Collaboration and Peer Review
Flexibility and Transformation Extended Learning Areas
Transparency & Trust; Supports Project Based Learning
Middle School: SBHS/FHT Physical Education Space
Next Generation Physical Education Space
Middle School: SBHS Cafeteria Space
Next Generation Multi-functional Cafeteria/Learning Space
50% of FHTMS: No Natural Light
Importance of physical adjacencies
Science Art Engineering and Technology
1960’s Departmental Organization
1st Floor – SBHS – 1960 and today
1960’s “Stand and Deliver” Teaching ; Not designed to include: Special Education, Remedial Assistance, Project Based Learning, Computers
Does this layout encourage collaboration?
ELA= Extended Learning Areas Science Math Math Math Math Science ELA ELA ELA Business / Career Tech/Eng Fab Lab Art Art Art Flex Science Science
Collaboration Teamwork Communication Problem Solving Autonomy Pa
Passive Supervision
ELA= Extended Learning Areas Science Math Math Math Math Science ELA ELA ELA Business / Career Tech/Eng Fab Lab Art Art Art Flex Science Science
Local Example Shelburne Community School
KEY
Visual Connection Visual Connection and Noise Transfer Creates team atmosphere by creating Small Learning Community Suite of spaces Maintains transparency and visual connection while eliminating sound transfer Shared Project Space maximizes efficient useOutcomes Classroom Wing
Project DescriptionExisting Conditions
Accordion partitions on three walls provided virtually no barrier to intrusion, sound or visual distractions. Layout does not promote “team” approachSBHS and Tuttle MS
SPACE PLANNING AND OPTION DEVELOPMENT
FHTMS Ph Ph 2: Educational Space Analysis Summary
educational vision for the future
SBHS Ph Ph 2 Educational Space Analysis Summary
Conceptual Bubble Diagram - MS MS
Conceptual Bubble Diagram - HS HS
SBHS and Tuttle MS
OPTION REVIEW
Evaluation Criteria Matrix
Seven Categories:
SBHS and Tuttle MS
OPTION 1
Existing Site
Option 1: Baseline Capital Improvement Plan Only
No educational or space revisions
$17.8 M
Tuttle MS Fi First Floor
Scope Includes the Following General Outline:
Repairs
Systems Upgrades
lot and some re-configuring Scope Does Not Include any renovations to address educational space needs
Existing Conditions First Floor Plan
Classrooms Administration Cafeteria Kitchen Gym Boys Lockers Nurse Tech/Fab Tech/Fab Media Center Alt Ed ELL
$17.8 M $13.8 M
Tuttle MS Second Floor
Option 1: Baseline Capital Improvement Plan Only
No educational or space revisions
Existing Conditions Second Floor Plan
Art ArtGirls Lockers Band Chorus Science Science Science Science Science Science Art Art Classrooms Classrooms Classrooms Classrooms Classrooms Sp Ed
Possible Phasing Scenario
Ph 1 : Construct Portable Classrooms and Move Students Ph 2 : Renovate Wing and Move Students
building over break. Ph 3: Move students out of central core.
Ph 4: Repeat. This section may be done
Ph 5: Move Students back in. Remove Portable Classrooms
Option 1: MS Phasing Considerations
Portable ClassroomsPH 2 PH 3 PH 4
Portable ClassroomsPH 1,5
Construction Staging Area$17.8 M
SBHS Fi First Floor
Option 1: Baseline Capital Improvement Plan Only
No educational or space revisions
Scope Includes the Following General Outline:
Upgrades
some re-configuring Scope Does Not Include any renovations to address educational space needs
Existing Conditions First Floor Plan
Media Ctr Auditorium Tech Lab Tech Lab Cafeteria Kitch Big Pic Admin
$17.8 M
SBHS Second Floor
Option 1: Baseline Capital Improvement Plan Only
No educational or space revisions
Existing Conditions Second Floor Plan
Science Wing Auditorium Below
Band ChorusGym
Band BandLckrs Platform
Possible Phasing Scenario
Ph 1 Summer-1: Construct Portable Classrooms and Move Students Ph 2 Fall-1: Renovate Wing and Move Students
Ph 3 Spring-1: Move students out of central core.
Ph 4 Summer-2: Repeat. This section may be done
Ph 5 Fall-2: Repeat Ph 6 Spring -2: Repeat Ph 7 Summer-3: Complete last section. Move Students back in. Remove Portable Classrooms
Option 1: HS Phasing Considerations
Ph 1, 7 Portable ClassroomsPH 2 PH 3 PH 3
Ph 1, 7 Portable ClassroomsPH 1,5
Construction Staging AreaPH 5 PH 4 PH 6 PH 7
SBHS and Tuttle MS
OPTION 2
Tuttle MS
Option 2: Reno/Add MS – 1st Floor
Priorities: 1. Team Geography 2. Cafeteria Zones 3. Gym Space
Team -1 House
Classrooms Extended Learning Extended Learning Media Center Classrooms Science Science
Team -2 House
Administration Cafeteria Kitchen Existing Gym Gym Addition Boys Lockers Girls Lockers Art Art Extended Learning Tech/Fab Shop
Tuttle MS
Option 2: Reno/Add MS – 2nd Floor
Priorities: 1. Team Geography 2. Cafeteria Zones 3. Gym Space
Team -3 House
Classrooms Extended Learning Classrooms
Team - 4 House
Science Science Extended Learning Extended Learning Extended Learning Classrooms Classrooms
Team - 6 House Team - 5 House
Science Science Health Opport’y Fam Cons Sc Guid Band and Chorus Movement
Possible Phasing Scenario
Ph 1 : Construct Portable Classrooms and Move Students Ph 2 : Renovate Wing and Move Students
building over break. Ph 3: Move students out of central core.
Ph 4: Repeat. This section may be done
Ph 5: Move Students back in. Remove Portable Classrooms
Option 2: MS Phasing Considerations
Portable ClassroomsPH 2 PH 3 PH 4
Portable ClassroomsPH 1,5
Construction Staging Area New AdditionSBHS
Option 2: Reno/Add HS 1st Floor
Priorities: 1. Cafeteria/Kitchen 2. Science 3. Gym Space
Extended Learning Media Center Cafeteria Kitchen Blk Box Theater Tech and Scene Shop Admin. Guid. Gym Ext Lrng Admin. Bus Ctr. Big Picture. Nurse Weight Rm Health Ext Lrng Auditorium Addition New Construction
SBHS
Option 2: Reno/Add HS 2nd Floor
Priorities: 1. Cafeteria/Kitchen 2. Science 3. Gym Space
Art Art Dept Ctr Ext Lrng Fash/Flex Studio Ext Lrng Dept Ctr Ext Lrng Band/Chorus Sci Sci Sci Sci Sci STEM Lab Sci Ext Lrng Gym Cafet Below Open to Below Sci Sci Sci Sci Sci Admin
Movement HealthNew Construction
Possible Phasing Scenario
Ph 1 Summer/Fall/Spring-1: Construct New Addition Ph 2: Summer-2 Construct Portable Classrooms and Move Science students and Library into new addition and PC Ph 3 Fall-2: Renovate Science and Library. Mobilize and set up next section of building over break. Ph 4 Spring-2: Move students out. Renovate. Move Students Back Ph 5 Summer-3: Repeat. This section may be done
Ph 6 Fall-3: Repeat Ph 7 Spring -4: Repeat Ph 8 Summer-4: Complete last section. Move Students back in. Remove Portable Classrooms
Option 2: HS Phasing Considerations
Ph 2 -Portable ClassroomsPH 3 PH 3 PH 4 PH 1,5
Ph 1 Construction Staging AreaPH 5 PH 6 PH 8 PH 6-7-8
Site Plan
Option 2 – SITE PLAN
SBHS and Tuttle MS
OPTION 3
Tuttle MS
Option 3: Reno/Add MS – 1st Floor
Team -1 House
Classrooms Extended Learning Extended Learning Classrooms Science Science
Team -2 House
Administration Cafeteria Kitchen Gym Addition Boys Lockers Girls Lockers Band Art Chorus Nurse Media Center Art Tech/Fab Tech/Fab New Entry Hellerup Stair Platform New Construction
Tuttle MS
Option 3: Reno/Add MS – 2nd Floor
Team -3 House
Classrooms Extended Learning Extended Learning Classrooms Science Science
Team -4 House
Cafeteria Below Media Center Below Extended Learning Classrooms Classrooms
Team - 6 House Team - 5 House
Science Science Extended Learning New Construction
SBHS
Option 3: Reno/Add HS 1st Floor
Media Center STEM Lab Bus Ctr/ Big Picture Blk Box Auditorium Band Chorus Stage Theater Tech Scene Shop Flex Studio Administration Admin Kitchen Cafeteria Weight Movement GymNew Construction
SBHS
Option 3: Reno/Add HS 2nd Floor
Sci Sci Sci Sci Sci STEM Lab Below Sci Extended Learning Sci Sci Health Health Blk Box Below Health Health Café Below Ext Lrng Health Art Art Art Ext Lrng New Construction
Option 3 – SITE PLAN
Option 3: HS Phasing Considerations
SBHS and Tuttle MS
OPTION 4
Tuttle MS
Option 4: Same as Option 3 except: Reno/Add MS with 5th Grade – 1st Floor
5th Grade Classroom Wing Ext Lrng Classrooms Extended Learning Extended Learning Classrooms Science Science Cafeteria Media Center Kitchen Admin Gym Band New Construction
Team -1 House Team -2 House
Chorus Lckrs Lckrs Art Art Tech Tech Nurse Classrooms
Tuttle MS
Option 4: Same as Option 3 except: Reno/Add MS with 5th Grade – 2nd Floor
Ext Lrng Classrooms Extended Learning Extended Learning Classrooms Science Science Cafeteria Below Media Center Below Extended Learning Classrooms Classrooms Science Science Extended Learning Science Classrooms New Construction
Team -3 House Team -4 House Team - 6 House Team - 5 House
5th Grade Classroom Wing
SBHS and Tuttle MS
OPTION 5
Fi First Floor
Option 5: Add/Reno MS (6-8)/HS Addition 1st Floor
MS I HS
MS – HS Separation New ConstructionLeadership, Civic Life, Service & World Lang
Second Floor
Option 5: Add/Reno MS (6-8)/HS Addition 2nd Floor
MS – HS Separation New ConstructionMS I HS
SITE PLAN
Option 5: Add/Reno MS (6-8)/HS Addition
Option 5: Phasing Considerations
PH 1 PH 3 PH 2 Move PH 2 PH 5 PHASE 1: Construct New HS Addition PHASE 2: Move HS students into new school Move MS students into existing high school PHASE 3: Renovate/Add to existing MS PHASE 4: Move MS students into renovated Middle School PHASE 5: Demolish existing High School and complete remaining field and parking improvements PH 4 Move
SBHS and Tuttle MS
OPTION 6
Tuttle MS
Team -1 House
Classrooms Extended Learning Extended Learning Classrooms Science Science
Team -2 House
Administration Cafeteria Kitchen Gym Addition Boys Lockers Girls Lockers Band Art Chorus Nurse Media Center Art Tech/Fab Tech/Fab New Entry Hellerup Stair Platform
Option 6: Reno/Add MS / New High School MS 1st Floor MS: Same as Option 3
Tuttle MS
Option 6: Reno/Add MS (6-8)/New HS MS 2nd Floor
Team -3 House
Classrooms Extended Learning Extended Learning Classrooms Science Science
Team -4 House
Cafeteria Below Media Center Below Extended Learning Classrooms Classrooms
Team - 6 House Team - 5 House
Science Science Extended Learning
MS: Same as Option 3
Fi First Floor
New HS: Similar to Option 5 but stand- alone building Option 6: Reno/Add MS (6-8)/New HS HS - First Floor
Leadership, Civic Life, Service & World Lang
Fi First Floor
Option 6: Reno/Add MS (6-8)/New HS HS - 2nd Floor New HS: Similar to Option 5 but stand-alone building
Digital Literacy & Humanities
SITE PLAN
Option 6: Add/Reno MS (6-8)/New HS
Option 6: Phasing Considerations
Similar Phasing as Option 5
SBHS and Tuttle MS
OPTION 7
MS MS - Fi First Floor Option 7: New MS (6-8)/New HS New MS 1st Floor
MS MS - Second Floor Option 7: New MS (6-8)/New HS New MS – 2nd Floor
HS HS 1st
st and 2nd nd Flr
New HS: Similar to Option 6 Option 7: New MS (6-8)/New HS New HS 1st Floor
Leadership, Civic Life, Service & World Lang
HS HS 1st
st and 2nd nd Flr
New HS: Similar to Option 6 Option 7: New MS (6-8)/New HS New HS 2nd Floor
Digital Literacy & Humanities
SITE PLAN
Option 7: New MS (6-8)/New HS
Option 7: Phasing Considerations
PH 3 PH 1 PH 4 PH 2 PH 5 PHASE 1: Construct New MS PHASE 2: Move MS students into new school PHASE 3: Construct New HS and demo existing Middle School PHASE 4: Move HS students into new school PHASE 5: Demolish existing High School and complete remaining field and parking improvements PH 3
SBHS and Tuttle MS
OPTION 8
Fi First Floor
Option 8: New MS-HS(6-8/9-12)
Overall 1st Floor
Second Floor
Option 8: New MS-HS(6-8/9-12)
Overall 2nd Floor
Fi First Floor
Option 8: New MS-HS
HS 1st Floor
Leadership, Civic Life, Service & World Lang
Second Floor
Option 8: New MS-HS
HS 2nd Floor
Digital Literacy & Humanities
Fi First Floor
Option 8: New MS-HS
MS 1st Floor
Second Floor
Option 8: New MS-HS
MS 2nd Floor
SITE PLAN
Option 8: New MS-HS (6-8 / 9-12)
Option 8: Phasing Considerations
PHASE 1: Construct New MS and HS wings PHASE 2: Move MS students into new middle school. Move HS students into existing middle school and new high school wings PHASE 3: Demo existing high school PHASE 4: Complete construction of remaining high school PHASE 5: Move HS students into new high school PHASE 6: Demo existing middle school and complete remaining field and parking improvements PH 3 Demo HS PH 1 Build MS PH 4 Build remaining HS PH 1 Build HS PH 6 Demo MS
Conceptual Project Cost Estimates
Comparison Purposes
$- $50,000,000 $100,000,000 $150,000,000 $200,000,000 $250,000,000Option 1 Option 2 Option 3 Option 4 Option 5 Option 6 Option 7 Option 8
Reno/Add MS and Reno/Add HS Reno/Add MS and Reno/Add HS – Limited Educational Same as Option 3, but add 5th Grade wing Baseline CIP- No Ed Reno/Add MS / New HS Addition Reno/Add MS / New HS – Stand Alone New MS / New HS New MS-HS
New Construction
$173-$178M
Reno/Add
$182-$192M
Reno/Add MS New HS
$174-$177M
Limited Reno/Add
$136M
Infrastructure only
$55M
School Board Research Infrastructure – Considerable $$ to extend life of buildings Enrollments – Increasing over 10 year window (and beyond) Capacity – Over capacity at HS currently, some wiggle room at MS Educational delivery – Methods have changed; buildings interfere with methods Cost – Best value of investment? Decision Point for School Board Fix infrastructure only; no educational changes? Renovate and provide additional space where necessary? Improve building design to support current and future educational delivery methods? Do Nothing? Extend the life of buildings – infrastructure only/no educational improvements? Additions/Renovations? New Construction? MS and HS connected or not? Community Input - How should the Board move forward?
Master Planning Community Information and Feedback Meeting Exit Card
Feedback for School Board Regarding Next Steps Please tell us which of the following options most closely matches your preference for what the District should do and why. ___ Do nothing. Continue to fix infrastructure issues as they arise. ___ Fix infrastructure only. Extend the life of the buildings. Do not address educational needs at this time. ___ Address as many future and current educational needs as possible through Additions/Renovations or New Construction. Do you prefer the MS and HS to be connected? Why?
Circle one YES NO
What was the most interesting thing you learned tonight? What questions do you still have? Do you have other thoughts or general comments you would like to share? Please tell us something about yourself (optional). I identify as (circle as many as you wish)… Elementary School Parent Middle/High School Parent Pre-K Parent Alumni Parent Homeowner Renter Alumnus/a of SB Current Student of SB District Faculty/Staff Retiree
Next Steps
FOR FURTHER INFORMATION
Questions, Comments, Reactions