Mass Timber: Sustainable from All Perspectives
With Nordic With SA+R and KL&A
Mass Timber: Sustainable from All Perspectives Understand a mass - - PowerPoint PPT Presentation
With Nordic With SA+R and KL&A Mass Timber: Sustainable from All Perspectives Understand a mass timber project through the eyes of a building owner, an architect, and a general contractor to understand why the material is so compelling
Mass Timber: Sustainable from All Perspectives
With Nordic With SA+R and KL&A
Understand a mass timber project through the eyes of a building owner, an architect, and a general contractor to understand why the material is so compelling across the industry.
4 Learning Objectives
1) Benefits and challenges of building with mass timber compared to other structural systems. 2) Sustainability benefits of mass timber. 3) How to communicate about mass timber and respond to concerns about using mass timber. 4) Understand how mass timber contributes to LEED.
Ryan Yaden
Associate Lake | Flato Architects
STICK FRAME Max 5 stories Must be covered Quality control
TIMBER FRAME + DECKING
certain size prescribed by code
DIFFERENCE BETWEEN TIMBER AND MASS TIMBER Timber made up of smaller components like 2x4’s [or smaller] glued or pressed together. LOTS OF ACRONYMS: GLT CLT NLT DLT MPP T&G LVL PSL
Mass Timber Suite
ALBINA YARD
Mass Timber Suite
MASS TIMBER: CROSS LAMINATED TIMBER - CLT Efficient, two-way structure Newer technologies, precision Dimensionally stable
MURRY GROVE LONDON, UK Waugh Thistleton Architecture 9 story housing Completed 2009 CLT only Construction photo Simple kit of parts
Carbon Focus – Embodied Carbon
Green Build | Whole Building LCA
END OF LIFE?
Operational VS Embodied Carbon
TIME VALUE OF CARBON
Option 4: Whole Building Life Cycle Assessment *measures reductions in environmental impacts as compared to a baseline building.
Impact Categories:
*at least three of the six categories, including Global Warming Potential, must achieve this 10% reduction
Carbon Leadership Forum Document: LCA Practice Guide
life cycle assessment calculation method for determining cradle to grave (extraction to disposal) embodied energy and environmental impacts
LCA
Design Baseline 1 Floor slab 3-ply CLT panel
mesh 3" concrete decking
2 Column 11" Glulam HSS 8x8 steel column 3 Beams Glulam sized per drawings W16x26 steel beam 4 Shear walls 5-ply CLT panels 8" cast in place concrete with rebar reinforcement 5 Cladding Slate panels metal panels, 24 gauge steel, coated with flouropolymer paint
Option 2: Compare baseline design to the current design
0% 20% 40% 60% 80% 100% 120% 140% Acidification Potential Total Eutrophication Potential Total Global Warming Potential Ozone Depletion Potential Smog Formation Potential Primary Energy Demand Non-renewable Energy Demand Renewable Energy Demand Mass Total
Denver Achievement Center LCA Comparison
Baseline TIMBER
FORESTRY PRACTICES AND EMBODIED CARBON BEST CASE = FSC
MASS TIMBER
Biophilia – quality of natural environment Fewer added materials and toxins, more efficiency Reduced greenhouse gas emissions
CRAFT PLACEMAKING PERFORMANCE COMMUNITY
HIGH PERFORMANCE + WELLNESS
Houston MFA Conservation Center
UNIVERSITY OF DENVER BURWELL CARRIER ACHIEVEMENT CENTER
denver, colorado
SOTO OFFICE BUILDING
san antonio, texas
UNIVERSITY OF PENNSYLVANIA SEAS DATA SCIENCE BUILDING
philadelphia, pennsylvania
TRINITY UNIVERSITY HUMANITIES BUILDING
san antonio, texas
CHALLENGES
INTEGRATED DESIGN WORKSHOP
Integrated Design Workshop at DU
Integrated Design Workshop 80+ participants
Students, faculty, facilities, leadership Key goals included: Xeriscape and usable outdoor spaces Explore mass timber structure Maximize variety Universal design Explore Net zero energy User control Explore composting toilets
COLLECT
TIMBER BAY SIZING – 24’ GRID
MINIMIZE FIBER VOLUME
COORDINATE, COORDINATE, COORDINATE….
SHOP DRAWINGS
UNIVERSITY OF DENVER
BURWELL CAREER ACHIEVEMENT CENTER
denver, colorado SIZE: 23,000 SF BUDGET: $13.5 M Tracking LEED Platinum in construction: 2020 fall completion
Ankit Sanghvi
Preconstruction Manager PCL Construction
TIME LAPSE VIDEO
PROCUREMENT: Manufacturer Selection
Domestic vs. International Sourcing Varying Panel Fabrication Size Limits Engineering Support Panel Width Shipping Constraints – Land vs. Sea Proximity to Jobsite / Shipping Costs Sustainability – FSC vs. SFI Certification Aesthetic Considerations Wood Species
PROCUREMENT: Best Practices
Early Go/No-Go Decision on Mass Timber CM/GC design-assist Early supplier selection vs. competitive bid Optimize structural grid with supplier input Maximize time for design coordination
Transfer of Revit model to contractor
MEP COORDINATION: Case Study – Wood Innovation Design Center
MEP COORDINATION: Case Study – CSU Pavilion at Laurel Village
1st CLT project in Colorado (2014) LEED Platinum certification No topping slabs at floor assembly Rigid insulation at roof assembly Long span, exposed ceilings Extensive use of mockups
MEP COORDINATION: Burwell Center for Career Achievement
Challenge: No exposed conduit! Well defined space programming Originally explored access flooring 3” topping slabs at floor & roof assembly 3D model ALL conduit Penetration overlay with CLT shop drawings Strategic placement of soffits & ceilings Topping slab reinforcing
MEP COORDINATION: Best Practices
Identify aesthetic MEP routing goals early Determine extent of flexibility required Early transfer of REVIT model Prioritize MEP penetration coordination Consolidate MEP in soffits/ceilings Maximize shop penetrations made with CNC machine in factory Minimize field penetrations
CONSTRUCTION TYPE ANALYSIS: III-A vs. III-B
Location of Event Space Rooftop 1st Floor Construction Type III-A III-B Assembly Group A-3 A-3 Fire Resistive Rating 1-Hr Not required Connections Concealed Exposed CLT Panel Thickness 5-Ply 3-Ply Superstructure Cost/SF $65/SF $53/SF
CONSTRUCTION EFFICIENCIES: Reduced Waste
Prefabricated components Precision-fit No scrap material or field cuts Reduced deliveries / construction traffic Smaller onsite workforce Less impact on water quality / SWPPP
CONSTRUCTION EFFICIENCIES: Site Planning
Targeted Goals: Pick CLT panels directly off the trailer Eliminate double-handling Eliminate onsite storage of material Eliminate back-up of deliveries Best Practices: Align erection and fabrication sequence Optimize lay down area & crane placement Review onsite vs. offsite marshalling yard
CONSTRUCTION EFFICIENCIES: Faster Schedule
40% Faster than Concrete! Concurrent CLT core wall erection Eliminate re-shores Accelerated start of MEP rough-in Reduced manpower & crew size Prefabrication / precision-fit Minimal weather protection No temp heat required Erected in 6 weeks with 8 person crew
James Rosner
Associate Vice-Chancellor University of Denver
UNIVERSITY OF DENVER: Campus Overview
University Hall: 1892 Engineering/Computer Science: 2016
year standard
–
Several LEED Gold and Silver Certified
the Public Good”
Polling Question: What is the best way to gain support for the use of Mass Timber?
– Campus Carbon Neutrality Goal? – Campus Sustainability Goal? – Individual Building Performance Goal?
–
24% reduction by 2020*
–
45% reduction by 2025*
–
Internally funded projects
–
5-year payback ROI
–
Savings returned to fund
production by 2025
UNIVERSITY OF DENVER: Campus Energy and GHG Goals
784 kW Ritchie Center installation from Solar PPA *For scope I, II, and III emissions
The Denver Advantage program is to build three new buildings focused on improving the student experience:
285,900 GSF of new buildings?
UNIVERSITY OF DENVER: The Denver Advantage Program
N
DIMOND F AMIL Y RE SI DE NT I AL VIL L AGE 500 Be d s 130,699 GSF , $61.9 millio n COMMUNI T Y COMMONS Ce ntra l Dining , Stud e nt Se rvic e s 132,301 GSF , $79.8 millio n BURWE L L CE NT E R F OR CARE E R ACHIE VE ME NT Alumni Re la tio ns, Ca re e r Se rvic e s 22,904 GSF , $17 millio n
–
Class “B” building, not to DU’s traditional 100-year standard
–
LEED v4 Silver, no renewables
–
Net Zero Building
–
LEED v4 Platinum and Well Building Certified
–
Mass Timber
–
Solar on site
–
LEED v4 Platinum UNIVERSITY OF DENVER: Burwell Center Sustainability Goals
–
Emerged as a means to reach LEED goal and project schedule
–
Net Zero not achievable due to limited project site and inability to cross property lines via regulation.
–
Funded with the campus-wide Solar PPA with no cost to the project
–
Incorporated as part of architectural roof design/mechanical screen
–
Green Fund brought $434,000 needed to meet goal
–
Used opportunity for Platinum to “sell” MT and Solar to Trustees UNIVERSITY OF DENVER: Burwell Center Sustainability Goals
UNIVERSITY OF DENVER: Burwell Center Sustainability Goals
BURWELL CENTER FOR CAREER ACHIVEMENT SCORECARD Y ? N
Location and Transportation 16 12 0 4 Sustainable Sites 10 4 4 2 Water Efficiency 11 1 9 1 Energy and Atmosphere 33 24 6 5 Materials and Resources 13 5 4 4 Indoor Environmental Quality 16 11 5 Innovation 6 6 Regional Priority - 80208 4 2 1 1
Totals 65 30 17 likely maybes to become "yes" 24 Platinum 80-110 89
Watch our progress: https://app.oxblue.com/open/DU/Dashboard
You must allow time for audience Q&A
Ankit Sanghvi ASanghvi@pcl.com Ryan Yaden Ryaden@LakeFlato.com