Luas Cross City Why? Background to Luas Cross City (LCC) What? - - PowerPoint PPT Presentation

luas cross city
SMART_READER_LITE
LIVE PREVIEW

Luas Cross City Why? Background to Luas Cross City (LCC) What? - - PowerPoint PPT Presentation

TII National Roads Conference 2016 28 th September 2016 Luas Cross City Why? Background to Luas Cross City (LCC) What? The works involved in delivering LCC How? Key Issues for the delivery phase Where? ..have we got to so


slide-1
SLIDE 1

TII National Roads

Conference 2016

28th September 2016

Luas Cross City

slide-2
SLIDE 2

Background to Luas Cross City (LCC) The works involved in delivering LCC Key Issues for the delivery phase …..have we got to so far

  • Why?
  • What?
  • How?
  • Where?
slide-3
SLIDE 3

NTA Transport Strategy 2016 - 2035

2035 Metropolitan Light Rail Network

(Source: NTA Draft Transport Strategy 2016 – 2035)

Luas Red Line Luas Cross City Luas Green Line

Luas Finglas Luas Poolbeg Luas Lucan Luas Bray

slide-4
SLIDE 4

Benefits of LCC

slide-5
SLIDE 5

What does LCC involve?

slide-6
SLIDE 6

What does LCC involve? Luas Cross City Aerial Map

  • Total route length 5.6km - equating to approximately 13.3km of single track

equivalent

  • 6 km off-street between Broadstone and Broombridge
  • 2.1 km at Broombridge depot for tram stabling
  • 5.2 km of embedded on street track in city centre
slide-7
SLIDE 7

LCC Programme

slide-8
SLIDE 8

Heritage Works – KN Networks Services

slide-9
SLIDE 9

Cellar Works – KN Networks Services

slide-10
SLIDE 10

Utility Works – GMC Utilities

  • c.70km of new ducting and

pipe-work

  • 2 km of Sewer re-lining
  • Construction of 50 no. new

drainage manholes

  • Building Service connections
slide-11
SLIDE 11

Utility Works

slide-12
SLIDE 12

Main Infrastructure Works – Sisk-Steconfer Joint Venture

  • HV and LV ducting and chambers
  • Track installation
  • Ballasted
  • Embedded Rails
  • Structural Works
  • Depot Construction
  • Stop Construction
  • Traffic Signalling
  • OCS Installation
slide-13
SLIDE 13

Access Crossings maintained

Install Traffic Management and fencing Plane out carriageway Excavations & Pipelaying Hardcore Fill Concrete foundation Track Assembly & rebar Overhead wires erected at night at end of program Installation of facade fixings Isolated works for pole installation New Road Surfacing Concrete trackslab Secondary ducting works and new granite paving

Typical Methodology

Works Completion Remove Traffic Management Replace road surface with new

slide-14
SLIDE 14

Key Issues for Delivery

Site Access / Traffic Management

LCC Traffic Forum (~Monthly) NTA/DCC/TII/Dublin Bus/ Bus Eireann / An Garda Síochána LCC Traffic Group (Weekly) NTA/DCC/TII/Dublin Bus/ Bus Eireann / An Garda Síochána Contractors’ Traffic Management Application to DCC Roadworks Control Unit

slide-15
SLIDE 15

Key Issues for Delivery Communications

KEY PILLARS

  • Public Office
  • Web-site - Traffic

updates, works progress, maps

  • CRM

database – members of public and other interested parties

  • Local liaison officers –

direct contact with retailers/shops/reside nts

  • Sponsorships – Local

communities, Dublin Town events

slide-16
SLIDE 16

Works Progress – end of August 2016

NORTH SIDE OF LIFFEY SOUTH SIDE OF LIFFEY

slide-17
SLIDE 17

Works Progress – end of June 2016

slide-18
SLIDE 18

Works Progress – end of June 2016

slide-19
SLIDE 19

Works Progress – end of June 2016

slide-20
SLIDE 20

Works Progress – end of June 2016

slide-21
SLIDE 21

Works Progress – end of June 2016

slide-22
SLIDE 22

Works Progress – end of June 2016

slide-23
SLIDE 23

Works Progress – end of June 2016

slide-24
SLIDE 24

Works Progress – end of June 2016

slide-25
SLIDE 25

Works Progress – end of June 2016

slide-26
SLIDE 26

Thank you