LOS ANGELES STREET LOS ANGELES STREET CIVIC BUILDING CIVIC BUILDING JANUARY 29, 2019 MAYORS CABINET PRESENTATION MAYORS CABINET PRESENTATION https://civiccenterprojects.lacity.org July 9, 2018 July 9, 2018 180928_v2.1 01 OUR FUTURE


slide-1
SLIDE 1

MAYOR’S CABINET PRESENTATION MAYOR’S CABINET PRESENTATION July 9, 2018 July 9, 2018

LOS ANGELES STREET LOS ANGELES STREET CIVIC BUILDING CIVIC BUILDING

01

180928_v2.1

JANUARY 29, 2019 https://civiccenterprojects.lacity.org

slide-2
SLIDE 2

OUR FUTURE WORKPLACE OUR FUTURE WORKPLACE CIVIC CENTER MASTER PLAN CIVIC CENTER MASTER PLAN

Vision District Design Guidelines Los Angeles Street Civic Building

PROCESS AND NEXT STEPS PROCESS AND NEXT STEPS

P3 - DBFOM Delivery Method LASCB Space Programming Questionnaire

  • 1. INTRODUCTIONS
  • 2. CIVIC CENTER MASTER PLAN
  • 3. PARKER CENTER DEMOLITION
  • 4. REVIEW OF THE LOS ANGELES

STREET CIVIC CENTER PROJECT

02

slide-3
SLIDE 3

CIVIC CENTER CIVIC CENTER MASTER PLAN MASTER PLAN

03

CIVIC CENTER DISTRICT BOUNDARIES

CIVIC CENTER DISTRICT DESIGN GUIDELINES

Union Station

Temple St. 1st St. 2 n d S t . Spring St. Main St. L

  • s

A n g e l e s S t . J u d g e J

  • h

n A i s

  • S

t . Grande Ave. Alameda St. 1st St.

180927_v2.0

LAPD CalTrans CITY HALL

slide-4
SLIDE 4

Demolition Design Information Technology Decabling Hazardous W aste R emoval Building Deconstruction Site Grading 19’ Below Street Level

PARKER CENTER PARKER CENTER DEMOLITION DEMOLITION CIVIC CENTER MASTER PLAN

DRAFT CONCEPTUAL DESIGN

PH.A PH.D PH.B PH.F PH.E PH.C

LOS ANGELES STREET CIVIC BUILDING 04

180927_v2.0

https://civiccenterprojects.lacity.org/projects/civic-center-master-plan-environmental-impact-report-eir

slide-5
SLIDE 5

Demolition Design Information Technology Decabling Hazardous W aste R emoval Building Deconstruction Site Grading 19’ Below Street Level

PARKER CENTER PARKER CENTER DEMOLITION DEMOLITION

PHASE B PHASE B PHASE C PHASE C PHASE D PHASE D PHASE E PHASE E PHASE F PHASE F PHASE A PHASE A

LOS ANGELES STREET CIVIC BUILDING

05

CIVIC OFFICE RETAIL TOTAL: 750,000 SF CIVIC OFFICE RETAIL TOTAL: 360,000 SF RESIDENTIAL RETAIL TOTAL: 659,000 SF CIVIC OFFICE RETAIL FLEX TOTAL: 750,000 SF RESIDENTIAL RETAIL TOTAL: 610,000 SF CULTURAL CIVIC PLAZA TOTAL: 77,000 SF

slide-6
SLIDE 6

Demolition Design Information Technology Decabling Hazardous W aste R emoval Building Deconstruction Site Grading 19’ Below Street Level

PARKER CENTER PARKER CENTER DEMOLITION DEMOLITION PARKER CENTER DEMOLITION

DEMOLITION DRAWINGS RELOCATION OF INFORMATION TECHNOLOGY CABLING IN COLLABORATION WITH ITA ARTWORK PRESERVATION AND RELOCATION IN COLLABORATION WITH DCA REMOVAL OF HAZARDOUS MATERIALS BUILDING DECONSTRUCTION SITE GRADING TO 19 FT. BELOW STREET LEVEL DEMOLITION COMPLETION DECEMBER 2019 06

slide-7
SLIDE 7

Demolition Design Information Technology Decabling Hazardous W aste R emoval Building Deconstruction Site Grading 19’ Below Street Level

PARKER CENTER PARKER CENTER DEMOLITION DEMOLITION

BUREAU OF ENGINEERING BOARD OF PUBLIC WORKS MUNICIPAL FACILITIES COMMITTEE

COUNCIL

PERKINS + WILL

PREPARE PRE-DESIGN DOCUMENTS

P3 DEVELOPER TEAM

MAYOR CITY ATTORNEY

07

PROJECT ORGANIZATIONAL STRUCTURE CITY ADMINISTRATIVE OFFICE CITY LEGISLATIVE ANALYST MAYOR'S OFFICE

ASHURST

OUTSIDE COUNSEL

ARUP

RFQ/ RFP WRITER CITY P3 ADVISOR

slide-8
SLIDE 8

Demolition Design Information Technology Decabling Hazardous W aste R emoval Building Deconstruction Site Grading 19’ Below Street Level

PARKER CENTER PARKER CENTER DEMOLITION DEMOLITION

  • gy

R emoval tion

  • w

NTER NTER N

LOS ANGELES STREET CIVIC BUILDING

DRAFT CONCEPTUAL DESIGN

08

slide-9
SLIDE 9

Demolition Design Information Technology Decabling Hazardous W aste R emoval Building Deconstruction Site Grading 19’ Below Street Level

PARKER CENTER PARKER CENTER DEMOLITION DEMOLITION

27 - 29 STORY, 753,740 S.F., APPROX. 1,173 SUBTERRANEAN PARKING COMMERCIAL SPACE AREA 65,000 S.F. RANGE OF OCCUPANTS 2,600 -3,200 INNOVATIVE CONSIDERATIONS:

CONFERENCE CENTER COLLABORATIVE WORK SPACES WITH STAFF HOTELING LEED PLATINUM SECURITY MEASURES AUTOMATED PARKING

NEW CIVIC BUILDING

09 27 - 29 STORY (753,740 SF., APPROX.) 1,173 SUBTERRANEAN PARKING SPACES 65,000 SF. OF COMMERCIAL SPACE 2,600 - 3,200 RANGE OF OCCUPANTS INNOVATIVE CONSIDERATIONS CONFERENCE CENTER COLLABORATIVE WORK SPACES LEED PLATINUM / NET-ZERO SOPHISTICATED SECURITY AUTOMATED PARKING

slide-10
SLIDE 10

Demolition Design Information Technology Decabling Hazardous W aste R emoval Building Deconstruction Site Grading 19’ Below Street Level

PARKER CENTER PARKER CENTER DEMOLITION DEMOLITION CIVIC CENTER MASTER PLAN DISTRICT DESIGN GUIDELINES

IN COLLABORATION WITH THE CHIEF DESIGN OFFICER, THE PLANNING DEPARTMENT AND THE DEPARTMENT OF TRANSPORTATION

  • 1. DEVELOP PEDESTRIAN REALM DESIGN

STANDARDS

  • 2. PUBLIC RIGHT-OF-WAY STANDARDS (i.e.

SIDEWALKS)

  • 3. MOBILITY CIRCULATION PLAN
  • 4. PUBLIC OPEN SPACE
  • 5. BUILDING FRONTAGE STREET LEVEL DESIGN
  • 6. PARKING ANALYSIS
  • 7. BUILDING MATERIALS AND COLOR

10 http://clkrep.lacity.org/onlinedocs/2015/15-0554_rpt_CAO_01-09-2017.pdf

slide-11
SLIDE 11

AND NEXT STEPS AND NEXT STEPS

11

slide-12
SLIDE 12

P3 P3 PROJECT DELIVERY PROJECT DELIVERY METHOD METHOD DESIGN DESIGN - BUILD BUILD - FINANCE FINANCE - OPERATE OPERATE - MAINTAIN MAINTAIN

Design Competition - RFP Process Construction Completed by 2023 Estimated Capital Costs approximately $700M+

12

http://clkrep.lacity.org/onlinedocs/2014/14-1604_rpt_CAO_05-25-2018.pdf

slide-13
SLIDE 13

Performance Specifications Performance Specifications

(Present - December 2018)

Space Planning Space Planning

(Present - December 2018)

Parker Center Demolition Parker Center Demolition

(Scheduled completion December 2019)

Procurement Procurement

July 2018 - April 2019

Construction Construction

(Target August 2023)

PROJECT PROJECT MILESTONES MILESTONES

  • 1. PRE-DESIGN

TASK A: PROGRAMMING TASK B: PERFORMANCE SPECIFICATION TASK C: DESIGN GUIDELINES FOR CIVIC CENTER TASK D: OPERATIONS & MAINTENANCE

  • 2. PROCUREMENT

CONSULTANT TO WRITE RFQ/RFP AND PROVIDE ADVICE ON FINANCIAL & ASSET DISPOSITION.

  • 3. P3 LEGAL COUNSEL

TO ASSIST AS NECESSARY DURING RFQ/RFP & IN WRITING PROJECT AGREEMENT

13

slide-14
SLIDE 14

Demolition Design Information Technology Decabling Hazardous W aste R emoval Building Deconstruction Site Grading 19’ Below Street Level

PARKER CENTER PARKER CENTER DEMOLITION DEMOLITION

14

TASK A: FACILITY PROGRAMMING

· STREETS AND OPEN SPACES · BUILDINGS AND ARCHITECTURE · IDENTITY AND WAYFINDING · MOBILITY AND TECHNOLOGY · ETC... · FACILITY MANAGEMENT

· UTILITY MANAGEMENT · HELPDESK · HOUSEKEEPING · LANDSCAPE · SECURITY

· PARKING · REPAIRS

· LIFE CYCLE MAINTENANCE · ETC...

· SPACE PROGRAMMING · SPACE DATA · BLOCKING/STACKING DIAGRAMS · PARKING STRATEGIES · ETC...

TASK B: ARCHITECTURAL AND ENGINEERING PERFORMANCE SPECIFICATIONS

UNIFORMAT II SPECIFICATIONS (TO LEVEL 4) FOR: · A - SUBSTRUCTURE · B - SHELL · C - INTERIORS · D - SERVICES · E - EQUIPMENT & FURNISHINGS · F - SPECIAL CONSTRUCTION & DEMOLITION · G - BUILDING SITEWORK · ETC...

TASK C: CIVIC CENTER MASTER

PLAN DISTRICT DESIGN GUIDELINES

TASK D: OPERATING AND

MAINTENANCE SPECIFICATIONS

slide-15
SLIDE 15

Demolition Design Information Technology Decabling Hazardous W aste R emoval Building Deconstruction Site Grading 19’ Below Street Level

PARKER CENTER PARKER CENTER DEMOLITION DEMOLITION

CITY'S GOAL IS TO HAVE:

START OF

DESIGN & CONSTRUCTION APPROXIMATELY LATE 2020

FACILITY

GRAND OPENING APPROXIMATELY EARLY 2024

SCHEDULE

15