LEVERAGED TO GOLD
Q2 F2010 RESULTS
Johannesburg Johannesburg 4 February 2010
LEVERAGED TO GOLD Q2 F2010 RESULTS Johannesburg Johannesburg 4 - - PowerPoint PPT Presentation
LEVERAGED TO GOLD Q2 F2010 RESULTS Johannesburg Johannesburg 4 February 2010 2 Emergency Procedures INTRODUCTION INTRODUCTION In the event of an emergency an alarm will sound. Exit premises through doors on the north side of room.
Q2 F2010 RESULTS
Johannesburg Johannesburg 4 February 2010
2
3
5
6
7
1 200
900 1,000 1,100 1,200
Free Cash Flow Margin
600 700 800 900
Investing in the future
200 300 400 500
Good cost control
200
009 009 009 009 010 010 Q1 F20 Q2 F20 Q3 F20 Q4 F20 Q1 F20 Q2 F20
Gold price Cash costs NCE
8
9
10
11
13
13
000oz
US$/oz
US$/ZAR
R/kg
R
Rm
Rm
R/ton
SA R/t
SA ug R/t
Rm
%
R/k
R/kg
US$/oz
R/kg
R/kg
1 NCE = Operating cost + Capex
US$/oz
14
14
Rm
Rm
Rm
Rm
R
Rm
Rm
Rm
Rm
Rm
Rm
SA cps
Rm
SA cps
15
15
Rm
Rm
Rm
Rm
Rm
Rm
Rm
Rm
Rm
Rm
16
16
Q1 $/R 7 37
Q1 $/R 7.37 Q2 $/R 7.65
17
17
4 002 3 924 5,000 2,700 741 940 3,534 4,002 741 3,319 3,924 3,082 2,000 3,000 4,000 Utilised R8,497m Facilities R15,068m
*C t d t US$1 7 65
741 940 582 741
Q3 F2010 Q4 F2010 F2011 F2012 F2013 Facilities R15,068m Headroom R6,571*
*Converted at US$1 : 7.65
18
20
21
22
23
Increasing magnitude
s Events
Events E
24
10.22 10.00 12.00
8.00
man hours 6.27 3 82
6.00
er million m 3.82
2.00 4.00
Rate pe
0.00
Rate F2008 Rate F2009 F2010 Q1 & Q2
25
Hanging wall Sidewall Face
119 99 64 11 7 44 34 33 13 5 7 1 4 1 4 2005 2006 2007 2008 2009
26
27
28
Gold produced
Kg koz
16,257 523 16,386 527
Total cash cost
R/kg US$/oz
165,707 688 162,553 647
US$/oz
688 647 NCE
R/kg US$/oz
242,050 1 005 233,034 927
NCE
US$/oz
1,005 927
Capex
Rm US$m
1,137 152 1,050 134
29
Gold Produced
kg
5,825 5,893 Gold Produced
Koz
187 190 Total cash cost
R/kg
154,678 154,387
US$/oz
642 614
R/kg
208,103 207,416
NCE
g
208,103 207,416
US$/oz
864 825 Capex
Rm
274 272
US$m
37 35
30
Gold Produced
kg
4,887 5,024 Gold Produced
koz
157 162 Total cash cost
R/kg
169,306 162,818
US$/oz
703 648
/
233 804 217 456
NCE
R/kg
233,804 217,456
US$/oz
971 865 Capex
Rm
280 244
US$m
37 31
US$m
37 31
31
Gold Produced
Kg
3,318 3,437 Gold Produced
Koz
107 111 Total cash costs
R/kg
167,722 165,900
US$/oz
696 660
R/kg
220,766 215,595
NCE
g
220,766 215,595
US$/oz
917 858 Capex
Rm
156 150
US$m
21 19
32
Gold Produced
Kg
2,227 2,032 Gold Produced
Koz
72 65 Total cash costs
R/kg
183,655 179,921
US$/oz
763 716
R/kg
380,647 375,344
NCE
g
380,647 375,344
US$/oz
1,581 1,493 Capex
Rm
427 384
US$m
57 49
33
Colour Coding: Red Up Cast. GreenDown Cast Gold Rock Handling Capacity
South Shaft Twins Ventilation Shaft Twins Main Shaft M t ll i l Pl t
1 4km
SV 1 SV 3 Metallurgical Plant SV 2
1.4km
50 Lvl Rock Capacity 120ktpm Rock Capacity 175ktpm Rock Capacity 195ktpm 51 Lvl
70 Lvl 71 Lvl 78 Lvl
Initial mining to focus on 78 Level – east Shaft Complex
78 Lvl 90 Lvl 84 Lvl 90 Lvl 95 L l
95 Lvl
100 Lvl
105 Lvl 110 Lvl
Deepened Section
110a Pump 95 Lvl
110a Pump
34
2,500 3,000 60 70 80 1 500 2,000
ment (m)
40 50 60
uction (koz)
1,000 1,500
Developm
20 30 40
Gold Produ
500
Q1 Q2 Q3 Q4 Q1 Q2
10
Q1 Q2 Q3 Q4 Q1 Q2 Q1 F2009 Q2 F2009 Q3 F2009 Q4 F2009 Q1 F2010 Q2 F2010 Q1 F2009 Q2 F2009 Q3 F2009 Q4 F2009 Q1 F2010 Q2 F2010
35
Item Year Q2 F2010 F2010 F2011 F2012 F2013 F2014 Status 94 Level Refrigeration Plant No 2 Twin Vent Shaft (C l ti f k (Completion for rock hoisting) Tailings Storage Facility Plant Expansion to 330ktpm or above New Mine Development p Phase 1 Total Capital (All projects) R1,770m R1,875m R2,079m R1,484m R1,198m
Note: Capital estimates in July 2009 money
36
38
Gold produced
koz
143 146
Total cash cost
A$/oz
703 754
US$/oz
637 626
US$/oz
637 626
A$/oz
1,053 1,002
NCE
US$/oz
956 831
Capex
US$m
41 30
39
Q2 F2010 Q1 F2010
Gold produced
koz
96 100 SALIENT FEATURES
Total cash cost
A$/oz
798 841
US$/oz
724 698
A$/oz
1,149 1 089
d i d d d
NCE
A$/oz
1,149 1,089
US$/oz
1,043 901
Capex
A$m
31 23 drop in underground grades:
Belleisle stope failure;
Lower grades mined at Argo;
it d 10% t t f A ll
p
US$m
28 19
Q3 OUTLOOK
Underground Improved grades at Argo, new Naiad ore body at Belleisle.
40
14 16
8 10 12
2 4 6
2 22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov 29-Nov 30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb Actual MTD Grade Daily Grade
41
180
Development progress
ATHENA
100 120 140 160
res
20 40 60 80
Metr
Cumulative Advance (m)
42
Poseidon North
Blue Lode A1
Apollo Zeus Dido Athena Pollux Hamlet Yorick Clifton
Yorick Macbeth Diana Argo A’
Diana LEGEND
RC
Scallop CN6
Drilling
F2010 Drill Targets
RC Diamond
43
Q2 F2010 Q1 F2010
Gold produced
koz
47 46 SALIENT FEATURES
Total cash costs
A$/oz
509 566
US$/oz
461 470
A$/oz
856 819
NCE
$
856 819
US$/oz
777 679
Capex
A$m
15 13
S$
13 10
US$m
13 10 Q3 OUTLOOK
44
North South
Existing Reserve/Resource Kim Lode 4m @ > 5g/t
Current Development Level
Zone with
Kim S Extension Project Drillhole Completed Zone with Bulk Mining Potential
1400m
Drillhole Planned Projected Kim Lode Extension Projected Intersection of Kim Lode with Barrick Tenement
45
47
Gold produced *
koz
218 227
Total cash cost
US$/oz
524 513
NCE
US$/oz
741 678
C
US$
43 36 Capex
US$m
43 36
48
Gold produced
koz
173 175 p
Total cash cost
US$/oz
492 480 NCE
US$/oz
728 690
p
Capex
US$m
37 33
Successful completion of de-bottlenecking and process control improvements.
Plant performing at 1mtpm.
49
Gold produced
koz
45 51 Gold produced 45 51
Total cash cost
US$/oz
643 622 NCE
US$/oz
791 637
Capex
US$m
6 3
50
51
GREATER DAMANG
HUNI GAP
DPCB
JUNO
(DRILLING IN PROGRESS) )
2.8KM
TAMANG
(DRILLING IN PROGRESS)
TOMENTO NORTH TOMENTO EAST GREATER AMOANDA
52
Juno Juno DPCB DPCB Huni Huni
2008 - $420/oz
N
S N
53
HUNI GAP - PHASE 1 – SUMMARY OF RESULTS
DRC1701D DRC1707D
4m at 2 85g/t
DRC1704D
29 t 1 5 /t
81m at 1.14g/t incl. 12m at 5.95g/t 4m at 2,85g/t 17m at 1.21g/t 24m at 3.67g/t
DDD033 3.6m @ 4.96g/t
HUNI GAP 29m at 1.5g/t 1m at 15.33g/t
DRC1709D
9m at 1.29g/t 22m at 1.36g/t
DRC1708D
3m at 2.01g/t 8m at 1.41g/t 11m at 2.25g/t g 11m at 2.25g/t
Huni and DPCB Looking South West Huni and DPCB Looking South West
54
Tomento East PitAmoanda – Tomento E. Corridor Amoanda North Extension Amoanda Pit
FAULT FAULT
4m @ 11.7g/t 4m @ 11.7g/t
FAULT FAULT
Visible Gold observed at 80m Visible Gold observed at 80m
900m N S
Inferred Blocks Indicated Blocks Interpreted Mineralisation
55
YANFOLILA
56
Bagama Bagama
Bokoro Bokoro
Kobada Kobada g
Bokoro Bokoro
57
Komana East
58
Komana Komana
59
Interim resource
Interim resource
Additional discoveries
Conceptual study
61
Gold
koz
35 33 Copper
tons
10,600 9,100 Production
Eq oz
98 89
Total cash cost
US$/oz
378 349 NCE
US$/oz
617 599 higher Cu grade and recoveries
Capex
US$m
24 23
– Equivalent ounces: 100k eq oz (Au @ US$ 1,085/oz and Cu @ US$ 6,700 per ton).
q q
62
cash generation (~US$ 27M/quarter) 800 1,200
400 800
‐
Q2 F2009 Q3 F2009 Q4 F2009 Q1 F2010 Q2 F2010
revenues, tons shipped and earnings Gold Spot Price Cash Cost NCE
63
800 1,200
cash generation (~US$ 27M/quarter)
400 800
‐
Q2 F2009 Q3 F2009 Q4 F2009 Q1 F2010 Q2 F2010
‐800 ‐400
revenues, tons shipped and earnings
800 Gold Spot Price Gold Price Received Cash Cost NCE NCE Margin
64
100 120
Eq oz Produced
40 60 80 100
Q
‐ 20 40 Q1 F2009 Q2 F2009 Q3 F2009 Q4 F2009 Q1 F2010 Q2 F2010
80 90
Recoveries
50 60 70
A R
30 40 Q1 F2009 Q2 F2009 Q3 F2009 Q4 F2009 Q1 F2010 Q2 F2010
Au Recovery Cu Recovery
65
Las Las Gordas Las Águilas
66
Canahuire
Cerro Chucapaca
Katrina
GF
Katrina South
BVN
67
CCP09-59 92m @ 2.08g/t Au CP09-58 198.9m @ 1.22g/t Au CCP09-63 40m @ 7.84g/t Au CCP09-60 CCP09 60 127.4m @ 8.55g/t Au uncut CCP09-52 72.2m @ 6.94g/t Au CCP09-61 12.86m @ 6.95g/t Au
68
Peru Bolivia
Argentina Chile
! ! !!
Marte Lobo Au deposit La Coipa Au Mine
Pircas and other projects
Refugio Au Mine Cerro Casale Au Deposit Marte Lobo Au deposit
69
71
72
4,000 4,500
2,500 3,000 3,500
1,000 1,500 2,000
500
F2008 F2009 ecast ecast ecast ecast F F F2010 Fore F2011 Fore F2012 Fore F2013 Fore
73
Q2 F2010 RESULTS
Johannesburg Johannesburg 4 February 2010