LBNE Jim Strait, Project Director Fermilab Science & Technology - - PowerPoint PPT Presentation

lbne
SMART_READER_LITE
LIVE PREVIEW

LBNE Jim Strait, Project Director Fermilab Science & Technology - - PowerPoint PPT Presentation

LBNE Jim Strait, Project Director Fermilab Science & Technology Review November 5-7 2013 Outline LBNE Overview and Science Goals Collaboration and Project Organization, and Fermilab roles Progress since the last S&T review


slide-1
SLIDE 1

LBNE

Jim Strait, Project Director Fermilab Science & Technology Review November 5-7 2013

slide-2
SLIDE 2

Outline

  • LBNE Overview and Science Goals
  • Collaboration and Project Organization, and

Fermilab roles

  • Progress since the last S&T review
  • CD-1
  • Developing International Partnerships
  • Technical Progress toward a “full” LBNE
  • Cost and Schedule
  • Key Near-Term Plans
  • Conclusions

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 2

slide-3
SLIDE 3

3

LBNE CD-1 Director's Review - 26-30 March 2012

Sample with bullet points

  • First Bullet
  • Second Bullet
  • More
  • Yet more
  • Still more
  • Less important
  • Trivial

New Neutrino Beam at Fermilab… And all the Conventional Facilities required to support the beam and detectors …aimed at the Sanford Underground Research Facility (SURF) in Lead, South Dakota 35 kton Liquid Argon TPC Far Detector at a depth of 4850 feet

LBNE-doc-7074

Precision Near Detector

  • n the Fermilab site
slide-4
SLIDE 4

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 4

Physics Motivations and Goals

  • CP Violation in neutrino sector?
  • Violation of a fundamental symmetry; viability of

leptogenesis models

  • Neutrino Mass Hierarchy
  • GUTs, Dirac vs. Majorana nature and feasibility of

measuring 0 decay

  • Testing the Three-Flavor Paradigm
  • Precision measurements of known fundamental mixing

parameters

  • New physics -> non-standard interactions, sterile

neutrinos… (with beam + atmospheric  sources)

  • Precision neutrino interactions studies with the

near detector

slide-5
SLIDE 5
  • Other fundamental physics enabled by

massive detectors

  • Baryon number violation search
  • Grand Unification Theory
  • Astrophysics
  • Supernova  burst flux measurement

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 5

Physics Motivations and Goals

slide-6
SLIDE 6

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 6

LBNE Collaboration

slide-7
SLIDE 7

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 7

LBNE Collaboration Organization

  • Highlight non-Fermilab parts, support for non-

Fermilab postdocs/students

  • More
  • Yet more
  • Still more
  • Less important
  • Trivial

* * * * * * *Significant Fermilab roles

slide-8
SLIDE 8

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 8

Key Fermilab roles in collaboration leadership

  • Executive Committee Members: G.Zeller, J.Strait
  • Long-baseline physics coordinator:

G.Zeller (co with M.Bishai, BNL)

  • Physics Tools Coordinator: T.Junk

Electron/Photon Simulations – B.Rebel (co with M.Szydakis, UCD)

  • Technical Coordinators:

Beam – A.Marchionni 35 t prototype – M.Stancari (co with M.Convery, SLAC)

  • Software and Computing Coordinator: T.Junk (co with

M.Potehkin, BNL)

slide-9
SLIDE 9

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 9

LBNE Project Organization

  • Fermilab plays dominant role in Project Management and Beamline
  • Fermilab’s role is strong in the far detector
  • Project Mechanical and Project Electrical Engineers
  • Responsible for cryogenics and cryostat, and installation & comm.
  • Fermilab people are present in all aspects of the LAr project
  • Fermilab leads CF and is fully responsible for all work at Fermilab
  • Collaboration is integrated into all aspects of the Project

Fermilab has ultimate responsibility for the Project.

slide-10
SLIDE 10

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 10

LBNE Organization will evolve

  • As international partners become part of LBNE,

both the collaboration and project organizations will need to evolve.

  • An international governance structure will be
  • necessary. First discussions with DOE have
  • ccurred concerning formal relations with

external partners.

  • We are looking at structures from other

international experiments to learn what we can from them.

slide-11
SLIDE 11

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 11

LBNE Progress since last S&T Review

  • CD-1 approval 10 Dec 2012 provides flexibility to

refine the scope before CD-2 with partners

  • CD-1 has enabled us to attract international

partners

slide-12
SLIDE 12
  • We are in serious discussion with both physics groups

and funding agencies, in:

  • Brazil
  • India
  • Italy
  • UK

New groups from these countries have joined LBNE.

  • We are also in discussions with:
  • CERN
  • LAGUNA/LBNO collab.
  • Dubna
  • NESSiE collab.
  • We have had initial conversations with:
  • Japan
  • China
  • Additional countries in the Americas, Asia and Europe
  • Also exploring how to engage domestic funding sources

beyond the DOE.

  • Collaboration, Project and Fermilab management are

actively working together to develop new partnerships

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 12

Engaging the International Community

slide-13
SLIDE 13

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 13

LBNE Visit to Brazilian National Lab CNPEM, April 2013

slide-14
SLIDE 14

J.Strait NuFact 2013 14

slide-15
SLIDE 15

J.Strait NuFact 2013 15

slide-16
SLIDE 16

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 16

INFN Visit to Fermilab 17 Sep 2013

slide-17
SLIDE 17
  • Working with international partners (and within the

CD-1 budget) we are developing a plan to deliver an initial project consisting of:

  • A neutrino beamline
  • A highly-capable near detector system
  • A ≥10 kt fiducial mass far detector at the 4850

foot level at SURF

  • A cavern for a full 34 kt detector system.

DOE/HEP encourages this approach.

  • The project allows for future upgrades:
  • The beamline is designed to handle ≥2.3 MW

proton beam power

  • Future detector module(s) can be installed in the

underground cavern.

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 17

Post CD-1 Project Goals

slide-18
SLIDE 18

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 18

LBNE Beamline

  • 60 ≤ Ebeam ≤ 120 GeV
  • 700 kW initially, upgradeable 2.3 MW
  • Options under study to provide more flux
  • 204 m (reference design) vs. 250 m decay pipe
  • Air-filled (reference design) vs helium-filled decay pipe
  • Improved target/horn system design
slide-19
SLIDE 19

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 19

LBNE Near Detector System

  • Muon detectors
  • Near neutrino detector,

Fine Grain Tracker, as developed by partners

slide-20
SLIDE 20

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 20

LBNE Far Detector

  • Modular detectors in a

common cavern

  • Located at 4850L at

SURF

  • Membrane cryostat
  • TPC design:
  • 3.7 m drift length
  • 5 mm wire spacing
  • 3 stereo views
  • Detector modules developed by partners will enhance

the reach of the experiment.

  • These may be of a different design than ours.
slide-21
SLIDE 21

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 21

Progress - 35t Prototype Detector

  • At Fermilab’s PC-4, built

by Fermilab staff + vendor (IHI)

  • Initial run for purity testing

to start later this month

  • Phase II run with TPC is

planned to start next fiscal year.

4,000 mm 2,700 mm Concrete

Membrane

Insulation 5,404 mm 4,104 mm 3,804 mm 2,700 mm 4,804 mm 3,504 mm 3,504 mm 1,000 mm Plate A Plate B

slide-22
SLIDE 22

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 22

Progress – Muon Detector Prototypes

  • Prototypes developed by LANL and universities and

installed in NuMI beamline muon alcove

  • Defined to be Fermilab test-beam experiment T-1046.
  • May prove to help understand the NuMI beamline, too.

Threshold Cherenkov Detector Prototype Drexel Stopped Muon Counter R&D Devices

slide-23
SLIDE 23

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 23

Progress – Beamline

  • Stress and thermal analysis of

absorber

  • Evaluation of types of shielding

steel to reduce cost

  • Target R&D initiated in conjunction

with CERN and RAL

  • Decay Pipe shielding and cooling reviews
  • Developed design for helium-filled decay pipe
  • Prototype beam position monitors

tested in NuMI beamline

slide-24
SLIDE 24

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 24

Progress – Conventional Facilities

  • Geotechnical site investigation

performed for beamline at Fermilab

  • Mapping and laser scanning of

existing drifts at SURF - 4850L.

  • Proposals received for geotechnical site

investigation of the underground far detector location at SURF

  • CF work is the critical path – preliminary design

at both sites should start as soon as funding allows.

slide-25
SLIDE 25

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 25

Progress – Software Development

  • FD Geometries implemented in LArSoft/GEANT4
  • Several detector geometries => optimization for physics
  • Preliminary ICARUS geometry
  • MC samples with several event generators
  • G4 photon and electron parameterization => e/ separation
  • Working with LArSoft on reconstruction algorithms,

including LBNE-specific challenges (wrapped APAs)

  • Many physics and detector topics being addressed, e.g.
  • Energy resolution for EM showers and full event calorimetry
  • Short-stub efficiency and resolution
  • Photon detectors
  • Working closely with Fermilab Scientific Computing Division
  • n computing resources, framework, etc.
  • See talk by Oliver Gutsche’s talk in the Experiment Support

Facilities Breakout this afternoon

slide-26
SLIDE 26

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 26

LBNE Cost Range

  • CD-1 cost range is $805M to $1,100M
  • We are working to a TPC of $867M, based on the

CD-1 scope

  • In moving detector to 4850L and including near

neutrino detector through international partnerships, we will still be managing to DOE cost parameters.

  • Precise scope that the DOE budget will deliver

depends on the developing international partnerships.

slide-27
SLIDE 27

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 27

LBNE Timeline & Critical Decision Status

Current Critical Decision Milestones

  • CD-0 (mission need)

Jan 2010 Actual

  • CD-1 (prelim baseline range)

Dec 2012 Actual

  • CD-3a (long-lead proc. => beam hill)

FY16/Q3 Forecast

  • CD-2 (baseline)

FY17/Q2 Forecast

  • CD-3b (start construction)

FY18/Q1 Forecast

  • CD-4 (project complete, includes float) FY26

Forecast

We are working to keep this schedule or better with the updated project scope with new partners.

slide-28
SLIDE 28

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 28

LBNE Key Near Term Plans

  • Continue to develop partnerships and involve

collaborators in their areas of interest; work towards real commitments and corresponding collaboration and project governance mechanisms

  • Complete geotechnical site investigation at

4850L to understand range of cavern span possibilities and start excavation design

  • Complete 35t prototype cryostat purity run and

install 35t phase II TPC

  • Complete studies on decay pipe and absorber

geometry and helium fill / cooling

slide-29
SLIDE 29

Jim Strait , Fermilab S&T Review, Nov 5-7 2013 29

Conclusions

  • LBNE will provide dramatic improvement in CP violation,

mass hierarchy, non-standard interactions relative to current generation experiments

  • Longer baseline and very large instrumented targets for

a comprehensive program

  • Large detectors probe physics not accessible in other ways
  • Proton decay (Grand Unified Theories)
  • Supernova burst neutrinos from intra-galactic distances
  • LBNE has received approval to begin this program
  • It will be a major US HEP facility for the 2020’s
  • With a budget of $867M we are proceeding with the

most important aspects in the first phase and actively working with partners to expand the scope

  • LBNE will develop into a world center for neutrino physics

to complement hadron/lepton colliders elsewhere