Lake EMS Operations Study 1 LAKE EMS BOARD OF DIRECTORS PHASE - - PowerPoint PPT Presentation

lake ems operations study
SMART_READER_LITE
LIVE PREVIEW

Lake EMS Operations Study 1 LAKE EMS BOARD OF DIRECTORS PHASE - - PowerPoint PPT Presentation

Lake EMS Operations Study 1 LAKE EMS BOARD OF DIRECTORS PHASE THREE CONSULTANT PRESENTATION DECEMBER 5, 2017 FITCH & ASSOCIATES, LLC EMS System Design 2 Responses by Agency 3 Cost Comparisons 4 Phase 1 - Deployment Costs for


slide-1
SLIDE 1

LAKE EMS BOARD OF DIRECTORS PHASE THREE

CONSULTANT PRESENTATION DECEMBER 5, 2017 FITCH & ASSOCIATES, LLC

Lake EMS Operations Study

1

slide-2
SLIDE 2

EMS System Design

2

slide-3
SLIDE 3

Responses by Agency

3

slide-4
SLIDE 4

Cost Comparisons

4

slide-5
SLIDE 5

Phase 1 - Deployment Costs for Implementation

  • Adjust one 0900-2200 to 0800-2100
  • Adjust one 0900-2200 to 0700-2000
  • Add 0700-1900 on Friday
  • Add 1900-0700 on Friday
  • Remove 0900-2200 on Sunday
  • Additional 11-hours per week at a UHC of $113.37 is $64,848 annually.

5

slide-6
SLIDE 6

6

slide-7
SLIDE 7

7

slide-8
SLIDE 8

EMS Response Time Improvement

8

slide-9
SLIDE 9

Implementation Considerations - Lake EMS

9

slide-10
SLIDE 10

Projected Growth

10

slide-11
SLIDE 11

Workload Considerations

11

slide-12
SLIDE 12

Workload Management Strategies

  • The 24/48 hour shift is the most fiscally efficient manner to staff

for 24 hours

  • Lake EMS has maximized this most efficient deployment for

many years

  • Workload is too high for five of the 24-hour units
  • Given the total time on task of 43,705 out of the 161,330

deployed hours the fleet could remain below 0.30, at 0.27 if the workload was managed and evenly distributed

  • Once the workload is greater than the ability to manage, it is

suggested that units are incrementally changed to 12-hour shifts.

  • Each 24-hour unit converted to two 12-hour shifts would cost an

additional $149,575.

12

slide-13
SLIDE 13

Analysis of System Fragmentation

13

slide-14
SLIDE 14

Analysis of System Fragmentation

14

slide-15
SLIDE 15

Implementation Considerations - Lake EMS

  • Utilize the report’s urban/rural analyses to define urban/rural areas that correlate to the

dispatch response parameters

  • Design response areas for the Lake County Fire Rescue rural transport units
  • Ensure LCFR units have MDT’s and AVL capability in the identified rural transport areas
  • Utilize AVL to determine closest responding units for both the urban/suburban and rural

areas separately

  • Allow the MPDS process to complete the call triaging prior to dispatch
  • Identify the closest existing stations to the optimized posts and their suitability for

accommodating Lake EMS crews

  • Develop the ISBA areas in the new CAD with different response parameters for emergent

versus non-emergent calls

  • Obtain a blanket or master automatic-aid agreement and remove emergent response

activity from the ISBAs.

  • Ensure that all units and fire departments have MDTs and AVL capabilities
  • 18 Month to 24 Month Implementation

15

slide-16
SLIDE 16

Medical Priority Dispatching

16

slide-17
SLIDE 17

Summary of Recommendations

  • Lake EMS to change deployment plan that maintains

current urban performance and improves rural performance

  • Cost of approximately $65,000
  • LCFR to provide cross-staffed ambulance services in 6 to

8 rural stations

  • No additional recurring costs
  • Evaluate workload and adjust accordingly at

approximately $150,000 per 24 to 12 hour conversion

  • Remove “emergent” incidents from the ISBA boundaries

and utilize a master automatic-aid agreement countywide

17

slide-18
SLIDE 18

Summary of Recommendations

  • Under current deployment, optimized staffing for

Lake EMS would be 136 personnel assigned to ambulance services

  • Lake EMS currently has 131
  • This 5 person gap will significantly influence OT
  • Fleet should maintain 140% of peak ambulance

deployment

  • This would be approximately 10 units in reserve
  • May need additional units to account for remount

lag time

18

slide-19
SLIDE 19

Questions?

19