Packwood Lake Hydroelectric Project (P-2244) Lake Creek Restoration Public Meeting 11/7/19 Packwood, Washington Project Layout and Infrastructure 26+ MW 92,000 MWh/year average 511.65 federal acres occupied Packwood Lake 452


slide-1
SLIDE 1

Packwood Lake Hydroelectric Project (P-2244)

Lake Creek Restoration Public Meeting

11/7/19 Packwood, Washington

slide-2
SLIDE 2

Project Layout and Infrastructure

◘ 26+ MW ◘ 92,000 MWh/year average ◘ 511.65 federal acres occupied ◘ Packwood Lake – 452 acres ◘ Lake Intake to Surge Tank – approx. 4.1 miles ◘ 1.3 mile long asphalt/concrete lined tailrace emptying into the “tailrace slough” ◘ Lake Creek (bypass reach) – approx. 5.3 miles ◘ Lower 1 mile is the anadromous reach

slide-3
SLIDE 3

Project Layout and Infrastructure

◘ The 4.1 mile of Pipeline tunnels 1&2 ◘ Operating pressure is ~780psi. ◘ Unit is roughly 36,700 HP at 26MW ◘ Generator is rated at 26MW, 1150 amps @ 13.8KV and stepped up to 69KV

slide-4
SLIDE 4

Project Layout and Infrastructure

slide-5
SLIDE 5

Project Layout and Infrastructure

slide-6
SLIDE 6

Project Layout and Infrastructure

slide-7
SLIDE 7

Project Layout and Infrastructure

slide-8
SLIDE 8

Project Layout and Infrastructure

slide-9
SLIDE 9

Project Layout and Infrastructure

slide-10
SLIDE 10

Project Layout and Infrastructure

slide-11
SLIDE 11

Project Layout and Infrastructure

slide-12
SLIDE 12

Project Layout and Infrastructure

slide-13
SLIDE 13

Regulatory Timeline

2004-2008 – Energy Northwest conducts relicensing effort in collaboration with agencies (USFS, NMFS, WDFW, WDOE, ACOE, Yakama Nation and Cowlitz Indian Tribe, FERC)

◘ Integrated Licensing Process ◘ Natural Resource Studies ◘ Terms and Conditions agreements

2/25/08 – EN files Final License Application with FERC 7/1/09 – FERC issues Final Environmental Assessment 3/21/18 – NMFS issues Biological Opinion 10/11/18 – FERC issues new operating license October-Current – Compliance prep, site visits, re-initiate agency collaboration, 2019-specific planning

slide-14
SLIDE 14

Public Meeting Intent

Inform local public of required measures for lower Lake Creek Address all questions/concerns Describe general timeline for the effort Discuss potential for access via private lands

slide-15
SLIDE 15

Lower Lake Creek Restoration

Develop and implement a plan for restoring anadromous salmonid habitat in the lower 1.0 mile (anadromous reach) of Lake Creek. Both implementation and success criteria must be initially incorporated into the plan and updated on a regularly scheduled basis.

slide-16
SLIDE 16

Develop and Implement Lake Creek Stream Restoration Plan

Timeline – Plan must be collaboratively developed within 2 years of license issuance and restoration activities must be completed by year 5. Currently in discussions with agencies to extend implementation window to 7 years. Implementation

◘ Formation of Restoration Sub-group ◘ Series of drafts, calls, site visits/meetings lead to restoration plan ◘ EN works with land owners and agencies on access and permits ◘ Implementation occurs in years 6-7 of new license (2024-2025) ◘ Follow-up monitoring of restoration success to occur

slide-17
SLIDE 17

Lower Lake Creek

(Lower 0.3 Miles)

Lower 0.3 miles

◘ Focus on area below primary development ◘ Lower 0.1 mile of this 0.3 mile stretch ◘ Primarily focus on boulder placement to enhance habitat

  • 2,700 ft2 rearing
  • 300 ft2 spawning

◘ High level of public communication and interaction to begin Fall 2019

slide-18
SLIDE 18

Lake Creek

(Lower 0.3 Miles)

Area of Focus Goat Rocks Development

slide-19
SLIDE 19

Lower Lake Creek

(Lower 0.3 Miles)

slide-20
SLIDE 20

Lower Lake Creek

(Lower 0.3 Miles)

slide-21
SLIDE 21

Lower Lake Creek

(Upper 0.7 Miles)

Upper 0.7 miles

◘ 12,600 ft2 rearing ◘ 1,400 ft2 spawning ◘ Focus primarily on long-term wood structures designed to increase pools (rearing) and gravel retention (spawning) ◘ Supplemental gravel a consideration along with potential riparian plantings ◘ Approximately 15 wood structures will be placed in this area; may not be evenly spaced depending on identification of priority areas ◘ Likely focus area from RM 0.4 to area of significant gradient increase near RM 0.8

slide-22
SLIDE 22

Lower Lake Creek

(Upper 0.7 Miles)

Likely Area of Focus RM 1.06 Partial Barrier Thompson Road Bridge

slide-23
SLIDE 23

Lake Creek

(Upper 0.7 Miles)

slide-24
SLIDE 24

Lake Creek

(Upper 0.7 Miles)

slide-25
SLIDE 25

Energy Northwest Priorities and Potential Needs

Collaborative process with the public

◘ Consistent communication ◘ Status updates ◘ Key Contacts

Land access

◘ Surveys ◘ Restoration efforts ◘ Monitoring

slide-26
SLIDE 26

Energy Northwest Questions

Best outlets to utilize for local notifications?

◘ Shopper ◘ Flyers ◘ Other?

Identification of key contacts

◘ Goat Rocks Development ◘ Logging Company Contacts ◘ Key Packwood Interests Sign-in Sheet ◘ Personal contact info ◘ Information related to key contacts ◘ Other suggestions on appropriate notification

slide-27
SLIDE 27

Public Feedback/Next Steps

Questions/Concerns? Status Updates Additional Public Meetings

◘ Post-Resource Agencies Committee Meeting (April 2020)

General Schedule Adjourn