KYTC Partnering Conference September 11, 2012 By: Cindy M. - - PowerPoint PPT Presentation

kytc partnering conference september 11 2012 by cindy m
SMART_READER_LITE
LIVE PREVIEW

KYTC Partnering Conference September 11, 2012 By: Cindy M. - - PowerPoint PPT Presentation

LOUISVILLE-SOUTHERN INDIANA OHIO RIVER BRIDGES PROJECT UTILITY COORDINATION PRESENTATION KYTC Partnering Conference September 11, 2012 By: Cindy M. Kowalski, PMP 1 KYTC Partnering Conference 2012 Louisville-Southern Indiana Ohio River


slide-1
SLIDE 1

1

LOUISVILLE-SOUTHERN INDIANA OHIO RIVER BRIDGES PROJECT UTILITY COORDINATION PRESENTATION

KYTC Partnering Conference – September 11, 2012 By: Cindy M. Kowalski, PMP

slide-2
SLIDE 2

2

KYTC Partnering Conference 2012

Louisville-Southern Indiana Ohio River Bridges Project: How the bridge’s impacts to utilities are being handled.

slide-3
SLIDE 3

3

Presentation Agenda

  • Bridges Proj ect Overview

– Downtown Crossing – East End Crossing

  • Proj ect S

chedule

  • Two S

tates – Twenty Companies

  • High Profile Utility Impacts
  • Traditional Proj ect Utility Coordination process
  • Design Build Proj ect Utility Coordination process

– KYTC Utility Coordination for Downtown Crossing – INDOT Utility Coordination for East End Crossing

  • Questions

East End Crossing Ut ilit y Coordinat ion Meeting May 10, 2012

slide-4
SLIDE 4

4

Project Overview

Downt own Crossing Ut ilit y Coordination Meet ing May 18, 2012

slide-5
SLIDE 5

5

Project Schedule

Proj ect S chedule

– April 24, 2012 … . RFQ S election of qualifying teams – May 3, 2012 … … . Draft RFP provided to selected teams – August 1, 2012 .. Final RFP – October 2012 … .. Proposals due – Late 2012 … … … .. Developer Team selected – Early 2013 … … … ..Contract execution / Begin final design – June 30, 2017 … . East End Crossing complete – June 30, 2018 … . Downtown Crossing complete

East End Crossing Ut ilit y Coordinat ion Meeting May 10, 2012

slide-6
SLIDE 6

6

Two States / Twenty Companies

  • Downtown Bridge and Approaches -

– KY Utility Companies – 11 – IN Utility Companies - 12 – KYTC responsible for utility relocations in both states

  • East End Bridge and Approaches -

– KY Utility Companies - 6 – IN Utility Companies - 9 – INDOT responsible for utility relocations in both states

  • KYTC and INDOT met

– Agree permits to be processed in governing state – S hare policies and procedure manuals

East End Crossing Ut ilit y Coordinat ion Meeting May 10, 2012

slide-7
SLIDE 7

7

High Profile Utility Impacts

  • Downtown Bridge and Approaches
  • LG&E Transmission towers

– Vertical elevation conflict affecting two lat tice towers

  • MS

D twin 24” force main sewers

– CCTV all sanitary and combined sewers – Designed relocation of twin 24” force mains

  • S

even Fiber Optic Providers

  • Insight’ s nodes and power supply
  • City of Jeffersonville Wastewater Pump S

tation

  • Duke 138 KV Transmission Route

East End Crossing Ut ilit y Coordinat ion Meeting May 10, 2012

slide-8
SLIDE 8

8

High Profile Utility Impacts

  • East End Bridge and Approaches
  • LWC 60” transmission water main

– Failure Risk Analysis and Construction Mitigation Report – Blasting Mitigation

  • LWC Water Treatment Plant

– RBI / Pier Placement – S ludge Lagoon S tudy of Options

  • AT&T Remote Terminal
  • MS

D Pump S tation and S hadowwood Treatment Plant

– S tudy of Options

  • Level 3 Long Haul Fiber Optics

– One conflict = 5 miles of relocation

  • AT&T Controlled Temperature Vault
  • Watson Rural Water Company 20” transmission water main

East End Crossing Ut ilit y Coordinat ion Meeting May 10, 2012

slide-9
SLIDE 9

9

LWC Sludge Lagoon

slide-10
SLIDE 10

10

Traditional Project Approach

Design R/ W and Utilities Construction

slide-11
SLIDE 11

11

Design Build Project Approach

Proj ect

Utility Coordination

Construction

RFP

Design and NEP A

Design Utility Coordination

R/W

Right of Way Design Build Team State DOT

Procureme nt Phase Design-Build Phase Design Phase R/W & Utilities Authorized

slide-12
SLIDE 12

12

KYTC – Utility Coordination

During Procurement Phase

  • Reimbursement Letters
  • Authorization Letters
  • Kick –
  • ff meeting with DBT’ s
  • DBT’ s have access to Utility Companies
  • Engineering S

ervice Agreements (if requested)

– Meet with DBT’ s – Coordinate with DBT’ s – Preliminary engineering – Conceptual lay-outs (cost estimate, schedules, etc,)

slide-13
SLIDE 13

13

INDOT- Utility Coordination

During Procurement Phase

  • Reimbursement Letters
  • Authorization Letters
  • Kick –
  • ff meeting with DBT’ s
  • DBT’ s need permission to contact Utility Companies

– Advance notice required – INDOT must be included via conference call or in person

  • Utility Adj ustment Types

– Type 1 – work that can be done with 30% plans – INDOT pays – Type 2 – work that depends on final plans – DBT controls and pays – Type 3 – work that depends on final plans – Utility controls / DBT pays

East End Crossing Ut ilit y Coordinat ion Meeting May 10, 2012

slide-14
SLIDE 14

14

INDOT- Utility Coordination

During Procurement Phase (cont.)

  • One-on-One Meetings

– Discussed / Agreed on Utility Adj ustment Types – Meeting S ummaries*

  • Request for Draft Work Plan*

– Preliminary plan, schedule and cost estimate

  • Preliminary Engineering Agreements

– To prepare draft work plan – Meet with DBT – Consultant Approvals

  • Type 2 and Type 3 Agreements*
  • NTP with Type 1 Relocations

* informat ion provided t o DBT’ s

East End Crossing Ut ilit y Coordinat ion Meeting May 10, 2012

slide-15
SLIDE 15

15

KYTC - Utility Coordination

During Design-Build Phase

  • DBT responsible for Utility Coordination
  • Utility Meetings
  • Provide proj ect plans as updated
  • Assist in Utility Relocation design lay-outs
  • Prepare Agreements
  • Utility Design and Construct
  • Utility Design and DBT Construct
  • DBT Design and Construct
  • Coordinate Permit application process

Downt own Crossing Ut ilit y Coordination Meet ing May 18, 2012

slide-16
SLIDE 16

16

INDOT- Utility Coordination

During Design-Build Phase

  • DBT responsible for Utility Coordination
  • Utility Meetings
  • Provide proj ect plans as updated
  • Assist in Utility Relocation type 2 and 3 designs
  • LWC Lagoon
  • Prepare Agreements
  • Acquire utility easements, if needed
  • Coordinate Permit application process
  • Type 1 relocations complete or relief event
slide-17
SLIDE 17

17

Summary

How the Bridges Impact on Utilities is being handled:

Coordination, Coordination, More Coordination and then… . Relocation!

slide-18
SLIDE 18

18

Questions

Cindy M. Kowalski, PMP - CTS Jennifer McCleve, PE – KYTC Central Office Carl Jenkins, PE – KYTC District 5