1
LOUISVILLE-SOUTHERN INDIANA OHIO RIVER BRIDGES PROJECT UTILITY COORDINATION PRESENTATION
KYTC Partnering Conference – September 11, 2012 By: Cindy M. Kowalski, PMP
KYTC Partnering Conference September 11, 2012 By: Cindy M. - - PowerPoint PPT Presentation
LOUISVILLE-SOUTHERN INDIANA OHIO RIVER BRIDGES PROJECT UTILITY COORDINATION PRESENTATION KYTC Partnering Conference September 11, 2012 By: Cindy M. Kowalski, PMP 1 KYTC Partnering Conference 2012 Louisville-Southern Indiana Ohio River
1
LOUISVILLE-SOUTHERN INDIANA OHIO RIVER BRIDGES PROJECT UTILITY COORDINATION PRESENTATION
KYTC Partnering Conference – September 11, 2012 By: Cindy M. Kowalski, PMP
2
3
East End Crossing Ut ilit y Coordinat ion Meeting May 10, 2012
4
Downt own Crossing Ut ilit y Coordination Meet ing May 18, 2012
5
East End Crossing Ut ilit y Coordinat ion Meeting May 10, 2012
6
East End Crossing Ut ilit y Coordinat ion Meeting May 10, 2012
7
– Vertical elevation conflict affecting two lat tice towers
D twin 24” force main sewers
– CCTV all sanitary and combined sewers – Designed relocation of twin 24” force mains
even Fiber Optic Providers
tation
East End Crossing Ut ilit y Coordinat ion Meeting May 10, 2012
8
– Failure Risk Analysis and Construction Mitigation Report – Blasting Mitigation
– RBI / Pier Placement – S ludge Lagoon S tudy of Options
D Pump S tation and S hadowwood Treatment Plant
– S tudy of Options
– One conflict = 5 miles of relocation
East End Crossing Ut ilit y Coordinat ion Meeting May 10, 2012
9
10
11
Utility Coordination
Design and NEP A
Design Utility Coordination
R/W
Right of Way Design Build Team State DOT
Procureme nt Phase Design-Build Phase Design Phase R/W & Utilities Authorized
12
13
– Advance notice required – INDOT must be included via conference call or in person
– Type 1 – work that can be done with 30% plans – INDOT pays – Type 2 – work that depends on final plans – DBT controls and pays – Type 3 – work that depends on final plans – Utility controls / DBT pays
East End Crossing Ut ilit y Coordinat ion Meeting May 10, 2012
14
– Discussed / Agreed on Utility Adj ustment Types – Meeting S ummaries*
– Preliminary plan, schedule and cost estimate
– To prepare draft work plan – Meet with DBT – Consultant Approvals
East End Crossing Ut ilit y Coordinat ion Meeting May 10, 2012
15
Downt own Crossing Ut ilit y Coordination Meet ing May 18, 2012
16
17
18