KUDU POWER PROJECT NAMIBIAS FLAG SHIP POWER GENERATION PROJECT 19 - - PowerPoint PPT Presentation
KUDU POWER PROJECT NAMIBIAS FLAG SHIP POWER GENERATION PROJECT 19 - - PowerPoint PPT Presentation
KUDU POWER PROJECT NAMIBIAS FLAG SHIP POWER GENERATION PROJECT 19 SEPTEMBER 2014 Background Kudu Gas Field was discovered in 1973 by Chevron, The first attempt to commercialize the Kudu gas resource for power generation was
Background
Kudu Gas Field was discovered in 1973 by Chevron, The first attempt to commercialize the Kudu gas resource for power generation was mooted shortly after independence. A tripartite agreement between NamPower, Eskom and Shell Exploration & Production Namibia (SEPN) was signed in 1997 to develop a 750MW power station outside Oranjemund, The project has since underwent several structural development changes and faced several delays mainly due to the complexity
- f this project.
Power Station developers/partners:
NamPower 51% CEC Africa 30% Other Equity Partner: 19%
(still to be selected)
Location of power plant: Uubvlei (25km north of Oranjemund) Technology: CCGT Power Output: 800MW (nominal) Main Off-taker: NamPower Secondary off-takers: Zambia & South Africa
Upstream Namcor (54%) Tullow Oil (31%) ITOCHU (15%) Downstream 800 MW CCGT Power Station KuduPower (Pty) Ltd (NamPower + Partners) Gas Sales/Supply Agreement Power Purchase Agreements
NamPower
Domestic supply Power Export Agreements
Project infrastructure scheme
PROJECT COMMERCIAL STRUCTURE
Kudu Project Commercial Arrangements
NamPower & other equity partners Lenders
Shareholders Agreement Financing Agreements O&M Agreement
Operations and Maintenance Company OEM & EPC Contractor
EPC & LTSA Contract Gas Sales/Supply Agreement
Upstream Parties KuduPower NamPower
Power Purchase Agreement
Regional Buyers
Power Export Agreement Transmission Agreement(s) Power to Namibia
KUDU REGIONAL COMPETITIVENESS
REGIONAL COMPETITIVENESS
- Kudu tariff (2013 estimates) of US$0.10 – 0.13c/kWh is still
competitive with any regional new build coming on-stream by 2016 - 2018,
- CCGT technology is environmentally clean compared to
several planned regional new built that are largely coal- based,
- It will possibly be the first CCGT power station of this size in
the region,
- The economic spin-offs of Kudu is greater in terms of its
impact on the monetization of the gas resource in the region
9
Indicative Regional Perspective of Pricing Trends
- 2.00
4.00 6.00 8.00 10.00 12.00 14.00 USD cents/kWh
Average Electricity Price
2006 2007 2008
Forecast of Industrial Tariffs (2010 - 2020) 2 4 6 8 10 12 14 16 2 1 2 1 1 2 1 2 2 1 3 2 1 4 2 1 5 2 1 6 2 1 7 2 1 8 2 1 9 2 2 Year USc per kWh RSA Zambia
- Low Tariffs but rising to
cost reflectivity
- Annual increases of 20-
30%
- Driven by new
investments needed to meet growing demand
Source Copperbelt Energy Corporation: 2011
LATEST PROJECT UPDATE
(AS AT SEPTEMBER 2014)
JOINT DEVELOPMENT AGREEMENT (JDA)
- NamPower signed a JDA with CEC Africa in February 2014,
- A JDA Steering Committee consisting of NamPower, CEC
Africa and KuduPower has been established.
- KuduPower Board composition is being finalized,
- The third additional equity partner also expected to sign the
JDA, and will nominate its representatives to sit on the Steering Committee.
UPDATE ON POWER EXPORT AGREEMENTS
Power Export Agreements (PXA) negotiations:
- Negotiations with CEC Plc:
PXA Termsheet with CEC Plc signed in February 2014, Full PXA negotiations expected to commence in due course, CEC Plc committed to off-take about 300MW denominated in US$
- Negotiations with Eskom
Eskom has been offered 100 - 300MW (denominated in Rands with hedging). Full negotiations have not yet commenced. Transmission interconnection discussions between NamPower and Eskom are quite advanced.
UPDATE ON KUDU TENDERS:
Tender evaluation process:
- EPC
- preferred contractor selected
- MLA
- preferred bank selected
- Strategic Equity Partner-
tender evaluation completed
- Operation & Maintenance-
tender evaluation completed
KUDU PROJECT RISKS
Kudu Power Station Fuel Transmission Construction O&M Demand Forex Force Majeure Regulation
- +/- 0.2 B USD
required
- Substantial GRN
support required
- Supply
- Long term commitment
- Delays
- Costs
- Disasters
- Strikes
- GRN action
- New taxes
- Frequency
- Time
- Costs
- Volatility
- Trend
- Demand
- Exports:
- Volume
- Price
- Delay
- Availability
- Cost reflectivity
- PPA pass through
Debt NP Equity Minority Equity
Financial
slide 15
MAJOR PROJECT RISKS
The following are the major risks that have been identified:
- Foreign exchange exposure
- Construction time delays and costs
- NamPower’s export agreements for surplus power from
Kudu
- Gas price
THE ROLE OF GOVERNMENT
- NamPower's experience (along with other utilities in the
region) is that major power projects are unlikely to move quickly without a substantial commitment from governments.
- The Kudu Gas to Power Project is a complex and big project
which its commercial viability also depends largely on support from the Namibian Government in terms
- f
guarantees to Namcor and NamPower in particular as lead developers.
- In the absence of the project receiving timely Government
guarantees, the project is most likely to be further delayed.
- Political stability let to higher economic growth and
subsequently an increase in electricity demand,
- Namibia is still largely dependent on imports,
- Security of power supply still at risk,
- Surplus generation capacity in the region on the decline,
- There is considerable peak power demand challenges in the
region,
- Transmission congestion for imports still a huge challenge
- Monetising the stranded Kudu gas field will unlock &
stimulate further oil & gas exploration.
- It will provide secure and adequate generation supply,
- It will diversify Namibia’s energy mix,
- It will reduce the over dependence on imports,
- It will make Namibia to be a net exporter of electricity,
- It is one of the most efficient non-renewable electricity
generation option,
- It is environmental friendly with lower carbon emissions,
- It could generate carbon credit revenue
DIRECT & INDIRECT IMPACT FOR LUDERITZ & ORANJEMUND There are several socio-economic benefits:
- Employment
- Housing/accommodation
- Infrastructure expansion & upgrade (e.g. roads)
- Increased utilization of harbour facilities at Lüderitz
- Secondary industries that will benefit:
Tourism Cleaning services, Catering, Trade, Transportation, Maintenance, etc.
INDICATIVE PROJECT TIMELINES
- Conclusion of all agreements
Nov 2014
- Financial Close:
1st quarter 2015
- Commencement of construction: 1st quarter of 2015
- Commercial Operations Date (COD): 1st quarter 2018
For more info contact: The Kudu Project Office
- Tel. +264-61-205 2221
- Tel. +264-61-205 2214
Fax: +264-61-205 9221 E-mail: kudupower@nampower.com.na
For attention: Mr. S. Muyenga-Muyenga
Project Coordinator: Stakeholder Management & Project Promotion E-mail: muyenga.muyenga@nampower.com.na Website: www.nampower.com.na