kensington public safety building special meeting: floor plan options presentation june 02, 2020 status : currently underway, determine scope target : fire department awaiting confirmation. only, or combined public safety building


slide-1
SLIDE 1

kensington public safety building

special meeting: floor plan options presentation

june 02, 2020

  • determine scope target: fire department
  • nly, or combined public safety building
  • establish budget/reconcile scope:

prepare cost estimate for replacement; calculate 50%; value engineer scope to stay under ceiling.

  • create technical working group: 1) form a

steering committee that includes

  • perational personnel; 2) authorize steering

committee members to make decisions on behalf of departments; 3) creatively explore any remaining scenarios; 4) prepare solution options for discussion.

  • return to community with solutions. the

next outreach should demonstrate a clear, negotiated path toward optimized solution.

next steps presented 11/16/2019 & status

status: currently underway, awaiting confirmation. status: conceptual estimate and building valuation

  • complete. Conclusion: budget

will be very tight status: formed 2 steering

  • committees. Background tasks
  • completed. Item #4 is the topic
  • f this meeting.

status: pending, recommended to occur after code verification meetings with County

  • determine scope target: fire department
  • nly, or combined public safety building
  • establish budget/reconcile scope:

prepare cost estimate for replacement; calculate 50%; value engineer scope to stay under ceiling.

  • create technical working group: 1) form a

steering committee that includes

  • perational personnel; 2) authorize steering

committee members to make decisions on behalf of departments; 3) creatively explore any remaining scenarios; 4) prepare solution options for discussion.

  • return to community with solutions. the

next outreach should demonstrate a clear, negotiated path toward optimized solution.

next steps presented 11/16/2019 & status

status: currently underway, awaiting confirmation. status: conceptual estimate and building valuation

  • complete. Conclusion: budget

will be very tight status: formed 2 steering

  • committees. Background tasks
  • completed. Item #4 is the topic
  • f this meeting.

status: pending, recommended to occur after code verification meetings with County

slide-2
SLIDE 2
  • option A: fire department only (previously

reviewed)

  • option B: shared fire & police

assumed maximum available space

  • option C: shared fire & police

assumed minimum available space floor plan options for discussion existing public safety building existing public safety building

slide-3
SLIDE 3

1 2 3 4 5 6 7

UP

Fire Engine DOC Storage Casework Extractor Compressor Located Above Decon Room 89 SF WORKSHOP (129) (125 SF) 19 SF HOSE STOR. (132) (25 SF) 125 SF TURNOUT RM. (125) (125 SF) 95 SF
  • DECON. RM.

(136) (150 SF) 12 SF EMS STOR. (127) (25 SF) 13 SF EMS ALCOVE (126) (25 SF) Fire Engine 1089 SF APPARATUS BAYS (124) (968 SF) 64 SF STAFF RESTROOM (123) (60 SF) 17 SF RADIO / MAP ALCOVE (108) (20 SF) 377 SF TRAINING / DOC (110) (400 SF) 34 SF JANITOR (401) (11 SF) 73 SF LOBBY (106) (60 SF) 200 SF WATCH OFFICE (107) (200 SF) 146 SF BUSINESS MANAGER (102) (100 SF) 38 SF STORAGE (120) (100 SF) 248 SF HALLWAY (1A) (248 SF) New ADA Stair ARLINGTON AVENUE 134 SF CAPTAIN OFFICE (101) (100 SF) Copier / Printer Firefighter Engineer BAY 3 Counter & Casework Counetr & Casework (110) TRAINING / DOC (127) STAFF RESTROOM ELEVATOR

  • ption A: fire department only

level 01

1 2 3 4 5 6 7

DN UP JAN 187 SF ELEC/ COMM. / IT (404 & 405) (160 SF) 83 SF LAUNDRY (119) (80 SF) 62 SF RADIO/GEN. (121) (65 SF) 393 SF KITCHEN (112) (275 SF) 300 SF DINING (113) (250 SF) 386 SF DAY ROOM (111) (350 SF) 341 SF FITNESS ROOM (112) (400 SF) 32 SF STORAGE (120) (100 SF) 71 SF MECHANICAL (402) (71 SF) ST. 83 SF BATHROOM B (118) (70 SF) 83 SF BATHROOM B (118) (70 SF) 147 SF HALLWAY (2B) (147 SF) 45 SF RESTROOM A (117) (105 SF)

New ADA Stair 125 SF HALLWAY (2A) (125 SF) 141 SF DORM RM. A (114) (175 SF) 141 SF DORM RM. B (115) (175 SF) 141 SF DORM RM. C (116) (175 SF) NON-ADA DORM RM. DOORS W D Roof Ladder Ref. Pantry Casework District History / Museum Casework Entertainment Center Ref. Ref. 67 SF EMT WKSTN. (103) (48 SF) Bar Seating

ELEVATOR ELEV. EQUIP. LIFT

  • ption A: fire department only

level 02

  • ption B: shared, maximum available space

level 01

slide-4
SLIDE 4
  • ption B: shared, maximum available space

level 02

verification req’ verification req’

  • ption C: shared, minimum available space

level 01

  • ption C: shared, minimum available space

level 02

slide-5
SLIDE 5

renovation options b & c - area calculations

  • ption b

LEVEL 01 gross: 3,092 sf fire department: 1,535 nsf* police department: 978 nsf shared: 417 nsf** LEVEL 02 gross: 3,259 sf fire department: 3,117 nsf

** includes lobby, conference/interview, secure hallway, restroom * includes stair & two existing app. bays

  • ption c

** includes lobby, secure hallway, restroom * elevator, stair, & two (e) app. bays

LEVEL 01 gross: 3,092 sf fire department: 1,598 nsf* police department: 997 nsf shared: 332 nsf** LEVEL 02 gross: 2,392 sf fire department: 2,796 nsf

  • option A: fire department only (previously

reviewed)

  • option B: shared fire & police

assumed maximum available space

  • option C: shared fire & police

assumed minimum available space recommendations

no opinion recommend advancing both options to have a viable fall- back position.

kensington public safety building

special meeting: floor plan options presentation