KENSINGTON COMMUNITY REFERENCE GROUP
MEETING 10 15 APRIL 2020
KENSINGTON COMMUNITY REFERENCE GROUP MEETING 10 15 APRIL 2020 - - PowerPoint PPT Presentation
KENSINGTON COMMUNITY REFERENCE GROUP MEETING 10 15 APRIL 2020 COVID-19 COVID-19 Health and safety The health and safety of our workers is our key priority as we continue to deliver the Metro Tunnel Project, as is supporting social distancing
MEETING 10 15 APRIL 2020
activities
Communication and engagement to support:
Out of hours works
impacted residents
wider community
Tunnelling
impacted properties
Notifications and communications
Door knocks, meetings, briefings and events
Traffic changes during heavy rainfall
Out of hours works (OOHW)
Contractor parking on Ormond Street
Completed D-walls Remaining D-walls 12 panels 2 panels
TEMPORARY PROPPING
EXCAVATION AND GROUND SLAB WORKS
Tunnelling – Arden to Kensington (completed) TBM retrieval Cross passage ground improvement reinstatement Cross passage construction (underground works) Egress access building construction Diaphragm wall construction Capping beams Permanent propping works Tunnel entrance roof slab construction Tunnel entrance excavation and base slab construction
Program is indicative and subject to change
Timing
services 24/7 Works
commissioning works
drainage
Traffic changes
and track work
provide access to rail corridor.
Communications and Stakeholder engagement
Arden to Kensington TBM Joan
TBM Meg
Retrieval works
inside the retrieval shaft
shaft
Limit is calculated based on Unavoidable OOHW.
CYP to insert approved video of Joan cutterhead lift.
Communications to potentially impacted properties
Current Activities
Next Steps
be provided to the curator to assist in informing design concepts
TBC)
Development Plan Update
Equipment Room (SER) alongside rail corridor
Rescheduled public display – anticipated for late April/May
Next Steps
Works update