Kelsale-cum-Carlton Community Energy (Power4KcC) Presentation for - - PowerPoint PPT Presentation

kelsale cum carlton
SMART_READER_LITE
LIVE PREVIEW

Kelsale-cum-Carlton Community Energy (Power4KcC) Presentation for - - PowerPoint PPT Presentation

Kelsale-cum-Carlton Community Energy (Power4KcC) Presentation for Community Energy meeting - Walpole Geoff Fordham & Keith Dickerson Monday, 1 September 2014 This presentation The background Choosing a project The first


slide-1
SLIDE 1

Presentation for Community Energy meeting - Walpole Kelsale-cum-Carlton Community Energy (Power4KcC)

Geoff Fordham & Keith Dickerson Monday, 1 September 2014

slide-2
SLIDE 2

This presentation

2

  • The background
  • Choosing a project
  • The first project
  • The process
  • The results
  • Some reflections
slide-3
SLIDE 3

The background

  • December 2011: Local Energy

Assessment Fund (LEAF)

  • £60k for feasibility and demonstration

projects:

  • Household survey
  • Energy audits
  • Solid wall insulation demonstrations
  • Feasibility studies on wind, solar PV, biomass,

ground source heat pumps, etc

  • Parish council sub-committee formed to

execute

3

slide-4
SLIDE 4

Why Community Owned Energy?

  • Help reduce impact of rising fuel bills:
  • For community facilities and…
  • …perhaps villagers struggling with fuel

bills

  • Securing more stable supply
  • Demonstrate the potential of renewables
  • Offer potential return for investors – and…
  • …maybe some funds for village activities

4

slide-5
SLIDE 5

Why a co-op?

  • Community-owned and shareholdings open to

all – Individuals and Organisations (e.g. VHMC, Suffolk County Council)

  • Maximum shareholding - £20,000 per individual
  • All decisions ...controlled by the membership
  • Flexibility to allocate surplus to:
  • Shareholders OR
  • Community benefit OR
  • Mix of two
  • All members get one vote irrespective of value
  • f shareholding

5

slide-6
SLIDE 6

How our co-op works

  • Membership:
  • Minimum required is 1 share of £20
  • Individual investments up to 1000 shares
  • Currently 107 shareholders!
  • Board elected by membership
  • Maybe some paid admin help in future?
  • All decisions taken by membership and

executed by Board

  • AGM decides value of dividend to be issued

6

slide-7
SLIDE 7

Choosing a project

7

  • Criteria: affordable, non-controversial,

demonstrable community benefit

  • Preferred project: Kelsale primary school
  • Next best option: village hall…
  • …but Grade II* listed,
  • …highly shaded backyard,
  • …so – ground mounted in adjacent field
slide-8
SLIDE 8

The first project: Power for the Village Hall

8

slide-9
SLIDE 9

How does it work?

  • 32 Solar PV panels in field behind Village Hall
  • Cable feed to separate meters in Village Hall

and Social Club

9

slide-10
SLIDE 10

Costs and returns

  • Competitive tender - 3 bids received
  • East Green Energy won
  • 32 Phono Solar PS250M PV modules
  • …combined with 32 Enphase micro-inverters
  • Installed capacity: 8 kW
  • Annual Output: 6,862 kWh (units)
  • Total Costs: ~£17.5K including installation
  • Estimated Income (FIT + export): £1,426/year
  • Estimated CO2 savings: 3,212 kg/year
  • Return on capital: 3-4% (after depreciation,

insurance, maintenance etc)

10

slide-11
SLIDE 11

Benefits to Village Hall

  • Village Hall gets free day time electricity
  • Social Club gets half price electricity
  • Initial 3 year agreement with each
  • afterwards at discretion of AGM
  • Opportunity to join co-op
  • + get seat on Board?
  • Help with securing £15K grant (matched

funding) from SCC to:

  • improve loft insulation
  • install secondary glazing
  • install storage heaters

11

slide-12
SLIDE 12

The process and timing

  • Planning application submitted – 14 January 2014
  • SCDC approval – 22 April 2014
  • Ofgem pre-registration applied for – 28 March 2014
  • approval to use 2013/14 FIT – 19 May 2014
  • Co-op (IPS) registered with FCA – 28 March 2014
  • Interim Board of Directors – 13 April 2014
  • Share prospectus issued – 8 May 2014
  • £17,500 received – 18 July 2014 Decision to Proceed
  • Solar Arrays installed / commissioned – 18 August 2014
  • Now producing >100 kWh per week
  • Inaugural AGM – September 2014
  • to formally elect Directors
  • First AGM – Summer 2015
  • to agree first dividend

12

slide-13
SLIDE 13

Screwing in the supports

13

slide-14
SLIDE 14

Digging the trench

14

slide-15
SLIDE 15

1st array with inverters in place

15

slide-16
SLIDE 16

Enphase micro-inverter on each panel

16

slide-17
SLIDE 17

2nd array with panels in place

17

slide-18
SLIDE 18

The grand opening

18

slide-19
SLIDE 19

Some further projects…

  • 2nd phase of Solar PV for Village Hall?
  • Approval for up to 20kW from UKPN
  • Solar PV on cowshed roof at East Green?
  • Have to examine economics
  • Wind turbine at East Green?
  • Up to 50kW – economics better with larger projects
  • Biomass boiler for primary school?
  • 3-4 year payback?
  • Solar PV on pensioners' cottages?
  • Renting roof space from people who want solar PV

but can't afford it?

  • Buying in energy in bulk from the big

suppliers?

19

slide-20
SLIDE 20

Some reflections

  • Overcoming conservatism
  • Conundrum: inclusivity vs scale of project:

£250 minimum investment is standard

  • Therefore – appropriate geographic scale:

county-wide co-ops?

  • Gloucestershire
  • Hampshire
  • Leicestershire
  • Definition of co-op: new FCA interpretation
  • Role of local authorities: shareholders? (see

Localism Act)