July 26, 2011 Jerry Wray, Director Joe Rutherford, District Deputy Director Includes Coshocton Fairfield Guernsey Knox Licking Muskingum Perry 3,731 Lane


slide-1
SLIDE 1

July 26, 2011

Jerry Wray, Director Joe Rutherford, District Deputy Director

slide-2
SLIDE 2
  • Includes

Coshocton Fairfield Guernsey Knox Licking Muskingum Perry

3,731 Lane Miles of roadway

slide-3
SLIDE 3
  • Julie Gwinn, P.E. is the District Highway

Management Administrator

Dave Slatzer, P.E. is the Planning and

Engineering Administrator

Keith Geiger, P.E. is the District

Construction Engineer

slide-4
SLIDE 4
  • Michelle Croom is the Public Information

Officer

Randy Comisford is the LPA Coordinator

slide-5
SLIDE 5
  • D1, 3,288

7.7% D2, 3,271 7.7% D3 4,146 9.7% D4 4,011 9.4% D5, 3,731 8.7% D6, 4,218 9.9% D7, 4,031 9.5% D8, 3,469 8.1% D9, 3,667 8.6% D10, 3,940 8.6% D11, 3,275 9.3% D12, 1,775 4.2%

slide-6
SLIDE 6
  • COS-463 mi.

12.4% FAI-463 mi. 12.4% GUE-615 mi. 16.5% Kno-415 mi. 11.1% Lic-726 mi. 19.5% Mus-675 mi. 18.1% PER-374 mi. 10%

slide-7
SLIDE 7
  • FY 2010 – ODOT sold $2.093B in

construction projects (ODOT and Local Let) – ARRA infusion

District 5 - $64.06M total; 3.1% of Statewide

spending

1157 projects sold Statewide

District 5 - 75 projects; 6.5% of Statewide

total

slide-8
SLIDE 8
  • FY 2011 – ODOT has sold, or will sell,

$1.868B (ODOT and Local Let)

District 5 - $66.4M; 3.6% of Statewide totals

940 projects sold Statewide

District 5 - 54 Projects; 5.7% of Statewide

total

slide-9
SLIDE 9
  • FY 2012 – ODOT is currently scheduled

to sell $1.528B (ODOT and Local Let)

District 5 – Projected budget is $63.3M;

4.1% of Statewide spending

685 projects Statewide

District 5 - 47 Projects; 6.7% of total

Statewide

slide-10
SLIDE 10

!!

District 5 has awarded or will award 47

projects

FRA 33 culvert replacement included

Current estimate is $77.8M

FRA 33 culvert replacement included

slide-11
SLIDE 11

!!

Project breakdown by size

< $500k: 19 $500k - $1M: 8 $1M - $2.5M: 7 $2.5M - $5M: 11 >$5M: 2

Allows for contractors of all sizes to bid

  • n work
slide-12
SLIDE 12

!!

"#"$%

Project breakdown by major work type

Roadway/resurfacing: 24 Bridge: 12 Safety (includes maintenance projects like

guardrail, striping, etc.): 11

Balanced to improve general pavement

and bridge conditions

slide-13
SLIDE 13

!!

"&#"$%

Project breakdown by major work type

Roadway/resurfacing: $50.7MM Bridge: $7.7M Safety: $19.4MM

Balanced to improve general pavement

and bridge conditions

slide-14
SLIDE 14

!!

"#

COS-1, 2.4% FAI-3, 7.1% GUE-5, 11.9% KNO-4, 9.5% LIC-9, 19% MUS-8, 19% PER-4, 9.5% Maintenance-11 26.2%

slide-15
SLIDE 15

!!

& #

COS $200k, .3% FAI $11.6M 16.1% GUE $7.5M 10.5% KNO $4.6M 6.4% LIC $16.7M 23.2% MUS $21.4M 29.7% PER $4.9M 6.8% Maintenance $4.4M 6.1%

slide-16
SLIDE 16

!!"'

SR 60 Bridge Replacement Project

  • Approx. 2 mi. south of Warsaw

Cost: $194,979 Contractor: Bud’s, Inc. Estimated start date: 6/1/11 Estimated completion date: 9/30/11

slide-17
SLIDE 17

!!"(

  • Pickerington/Violet Twp. Sidewalk

Project

Cost: $279,991 Contractor: Trucco Construction Co. Estimated completion date: 8/31/11

slide-18
SLIDE 18

!!"(

  • Fairfield & Perry County

SR 37 Resurfacing Project

From SR 664 to New Lexington Cost: $2.571MM Contractor: The Shelly Company Estimated completion date: 10/15/11

slide-19
SLIDE 19

!!"(

  • Fairfield & Licking County

IR 70 Resurfacing Project

From Franklin County to SR 158 Nighttime Resurfacing Cost: $8 MM Start date: 7/11/11 Estimated completion date: 10/31/11

slide-20
SLIDE 20

")

Cambridge US 22/40 From 5th St. to IR 77

Cost: $3.5MM Contractor: Shelly & Sands Lighting and signal upgrades, decorative

sidewalks, pavement resurfacing

Estimated start date: 5/1/11 Estimated completion date: 10/31/11

slide-21
SLIDE 21

")

SR 285 Resurfacing From Noble County to SR 265 and Old

Washington to US 22

Estimated Cost: $1.877MM Estimated start date: 7/5/11 Estimated completion date: 10/15/11

slide-22
SLIDE 22

")

SR 265 Resurfacing From SR 147 in Belmont County, through

Noble County to SR 285

Estimated Cost: $1.993MM Estimated start date: 7/5/11 Estimated completion date: 10/15/11

slide-23
SLIDE 23

!!"*

US 36 Resurfacing From Upper Gilchrist Rd. to Coshocton

County

Cost: $3.003M Contractor: Kokosing Construction Co. Estimated start date: June Estimated completion date: 10/15/11

slide-24
SLIDE 24

!!"*

“Heart of Ohio” Trail Phase 2 From Updike Road to Bishop Road

northeast of Centerburg

Cost: $481,786 Contractor: Park Enterprise Construction Co. Estimated start date: 5/1/11 Estimated completion date: 10/15/11

slide-25
SLIDE 25

!!"*

State Route 3 Bridge Repair 2 miles north of Amity

Estimated Cost: $926k One lane of traffic to be maintained Estimated start date: 6/1/11 Estimated completion date: 10/31/11

slide-26
SLIDE 26

!!"*

State Route 95 Bridge Replacement .31 miles north of Zolman Road

Cost: $985,544 Contractor: Shelly & Sands 70 day maximum closure Detour via SR 97 and SR 13 Estimated start date: 6/1/11 Estimated completion date: 10/15/11

slide-27
SLIDE 27

!!"+%,

Village of Johnstown SR 62/37 Intersection Improvements Lengthen turn lanes, upgrade signals Contractor: Complete General Cost: $808k Estimated start date: 6/15/11 Estimated completion date: 10/15/11

slide-28
SLIDE 28

!!"+%,

Newark SR 16 Improve Cedar St. interchange Redeck 3 bridges 10 day ramp closure Estimated Cost: $2.195MM Estimated start date: 6/15/11 Estimated completion date: 9/30/12

slide-29
SLIDE 29

!!"+%,

Heath SR 79 from 30th St. to Hopewell Widen, resurface and install center median Upgrade traffic signals Estimated Cost: $4.115MM Estimated start date: 6/15/11 Estimated completion date: 10/31/12

slide-30
SLIDE 30

"+%,

Resurface SR 13 from Waterworks Rd. to

Utica

Estimated Cost: $3.847MM Estimated start date: 8/28/11 Estimated completion date: 10/31/11

slide-31
SLIDE 31

"+%,-(

  • Resurface SR 37 from I-70 to Lancaster

Corp.

Estimated Cost: $3.683MM Estimated start date: 9/01/11 Estimated completion date: 10/31/11

slide-32
SLIDE 32

"%,

Resurface SR 60 from Duncan Falls to SR

146 in Zanesville

Estimated Cost: $5.055MM Estimated start date: 7/05/11 Estimated completion date: 10/31/11

slide-33
SLIDE 33

!!"%,

  • Resurface SR 60 (Maple Avenue) from

Adair Ave. to Fairview Rd.

Estimated Cost: $3.926MM Estimated start date: 8/01/11 Estimated completion date: 10/31/11

slide-34
SLIDE 34

"%,

Resurface SR 146 from SR 586 to east

  • corp. limit of Zanesville

Cost: $2.729MM Contractor: The Shelly Company Start date: 5/01/11 Estimated completion date: 8/31/11

slide-35
SLIDE 35

"%,

Resurface I-70 from US 22/40 interchange

to Guernsey County

Nighttime resurfacing Estimated Cost: $4.6MM Estimated start date: 7/05/11 Estimated completion date: 10/31/11

slide-36
SLIDE 36

!!"

County Road 30 Bridge Replacement Approximately .2 miles south of TR19 45 day closure, detour Cost: $196,866 Contractor: Rodney C. Wilson, Inc. Estimated start date: 6/01/11 Estimated completion date: 10/31/11

slide-37
SLIDE 37

!!"

State Route 93 Bridge Rehabilitation 2 bridges in Crooksville, and 1 bridge 2 mi.

north of Crooksville

Contractor: Bridge Overlay Systems Cost: $1.038MM Estimated start date: 6/15/11 Estimated completion date: 10/15/11

slide-38
SLIDE 38

!!"

State Route 668 Resurfacing From SR 37 (Junction City) to Hocking

County

Contractor: Kokosing Construction Co. Cost: $1.9MM Estimated start date: 7/05/11 Estimated completion date: 10/15/11

slide-39
SLIDE 39

!!"

State Route 668 Bridge Replacement Just south of Junction City No detour Contractor: Complete General Cost: $935k Estimated start date: 6/15/11 Estimated completion date: 10/31/11

slide-40
SLIDE 40

!!.$

Guardrail updates, replacement Pavement Markings Raised Pavement Markers Lighting Interstate Mowing Crack Sealing Traffic Signal Upgrades Estimated Cost: $4.4MM

slide-41
SLIDE 41

!

"#

Cos-1 3% Fai-2 6% Gue-4 12% Kno-2 6% Lic-8 24% Mus-7 21% Per-2 6% Maintenance-8 24%

slide-42
SLIDE 42

!

& #

Cos $700k, 1.3% Fai $8.9M, 16.5% Gue $5.8M, 11% Kno $2.7M, 5% Lic $15M, 28% Mus $16M, 30% Per $738k, 1.4% Maintenance $3.7M, 7%

slide-43
SLIDE 43

!"'

SR 541 Bridge Replacements Two bridges near SR 93, West Lafayette Estimated Cost: $700k Estimated start date: Spring 2012

slide-44
SLIDE 44

!"(

SR 37 Bridge Repairs 1.5 miles west of Bremen Install tunnel liner Estimated Cost: $297k Estimated start date: Spring 2012

slide-45
SLIDE 45

!")

  • US 40 Bridge Replacement over I-77

Estimated Cost: $2.623M Estimated start date: Spring 2012

slide-46
SLIDE 46

!")

  • US 40 Culvert Repairs at 14.84 Mile

Marker

Just west of Old Washington

Estimated Cost: $363k Estimated start date: Spring 2012

slide-47
SLIDE 47

!")

  • SR 723 @ I-70

Replace Bridge Deck, other work Estimated Cost: $2.3MM Estimated start date: Spring 2012

slide-48
SLIDE 48

!")

  • SR 513 Bridge Replacement

Over ditch located south of Millwood

Estimated Cost: $513k Estimated start date: Spring 2012

slide-49
SLIDE 49

!"*

US 36 (Coshocton Avenue)

  • Mt. Vernon

From Bridge over Center Run to Shalimar Drive Widening Intersection, safety improvements

Estimated Cost: $2.32MM Estimated start date: Spring 2012

slide-50
SLIDE 50

!"*

SR 3 Bridge Repairs

Brown Twp. Between Amity and Jelloway

Estimated Cost: $338k Estimated start date: Spring 2012

slide-51
SLIDE 51

!"+%,

SR 158 overpass @ I-70 Widen bridge to accommodate future

widening of I-70

Estimated Cost: $7.7M Award date: 3/29/12

slide-52
SLIDE 52

!"+%,

Bridge Replacements

SR 586 @ Pleasant Valley Run $370k McIntosh Rd (Twp. Rd. 155) 1000’ west of

Headley’s Mill R. $444k

CR 311 (Hopewell) $933k

All three will begin and end in 2012

slide-53
SLIDE 53

!"+%,

Intersection improvements, site distance

increase @ Blacks/Watkins Road intersection

Estimated Constr. Cost: $382k Estimated start date: 7/15/12

slide-54
SLIDE 54

!"+%,

City of Newark Resurfacing Program

  • W. Main from 3rd to N 21st

Granville Rd. 5th to N 21st

Estimated Cost: $966k Estimated start date: Spring 2012

slide-55
SLIDE 55

!"%,

  • State Street Bridge, Phase 2

Estimated Cost: $599k Estimated start date: Spring 2012

slide-56
SLIDE 56

!"%,

  • SR 146 Bridge Replacements

.03 mi. west of Three Towers Road .74 mi. west of N. Leedom Road

Estimated Cost: $2.11MM Estimated start date: Summer 2012

slide-57
SLIDE 57

!"%,

  • SR 376 Bridge Replacement

2.45 mile market, just north of Ruraldale

Estimated Cost: $348k Estimated start date: Late Summer 2012

slide-58
SLIDE 58

!"%,

  • Dillon Park

22 Parking Lot Areas ODOT/ODNR Cooperative Maintenance

Program

Estimated Cost: $2.1MM Estimated start date: Spring 2012

slide-59
SLIDE 59

!"%,

  • I-70 Mine Subsidence Program

Address 15 subsidence locations near the

158 mile marker (east of Zanesville)

Estimated Cost: $1.96MM Estimated start date: Fall 2011/Spring 2012

slide-60
SLIDE 60

!"

SR 13 Bridge Replacement Moxahana Creek tributary just south of SR

37

Estimated Cost: $350k Estimated start date: Spring 2012

slide-61
SLIDE 61

!"

SR 757 Bridge Replacement Hopewell Twp. Between Somerset and

Glenford

Estimated Cost: $388k Estimated start date: Summer 2012

slide-62
SLIDE 62

!.$

Guardrail updates, replacement Pavement Markings Raised Pavement Markers Lighting Interstate Mowing Crack Sealing Traffic Signal Upgrades Estimated Cost: $3.73MM

slide-63
SLIDE 63

'%/

Questions?

Contact Michelle Croom, Public Information

Officer @ (740) 323-5161 or michelle.croom@dot.state.oh.us or

Joe Rutherford, District Deputy Director @

(740) 323-5202 or joe.rutherford@dot.state.oh.us