July 14, 2011 The Tollway Today Status of Congestion-Relief - - PowerPoint PPT Presentation
July 14, 2011 The Tollway Today Status of Congestion-Relief - - PowerPoint PPT Presentation
July 14, 2011 The Tollway Today Status of Congestion-Relief Program Financial health and budget Economic pressures and challenges The Tollway Tomorrow Taking care of our existing system Potential future projects The
The Tollway Today
- Status of Congestion-Relief
Program
- Financial health and budget
- Economic pressures and
challenges
The Tollway Tomorrow
- Taking care of our existing system
- Potential future projects
The Path Forward
2
3
85% Complete
at end of 2010
$5B Invested
- n time, under budget
No State or Federal Funds
Congestion-Relief Program 2004-2016
4
$192 million
for 2011 CRP projects
2011
Jane Addams Memorial Tollway (I-90) Genoa Rd. to U.S. Route 20 Roadway Rehabilitation, Resurfacing & Bridge Repairs Jane Addams Memorial Tollway (I-90) Barrington Rd. to Elgin Toll Plaza Roadway Rehabilitation, Resurfacing & Bridge Repairs Tri-State Tollway (I-94/I-294/I-80) IL-394 to 159th St., I-55 & Everett Rd. Bridge Rehabilitation I-90/I-294 Tri-Level Bridge Rehabilitation Tri-State Tollway (I-94/I-294/I-80) Balmoral Ave. Ramp Construction Systemwide Improvements Landscaping, pavement repairs, etc.
Our budget must be balanced Required financial formula protects bond
ratings and reinvests in system
1st operating budget
cuts in agency’s history (4%)
Continual drive for efficiency
5
Reinvest
$174M
Maintenance & Operations
$255M
Debt Service
$251M
Projected 2011 Budget $680M
Budget must be balanced We must budget for:
Operating costs Debt service Required deposits to the Renewal and Replacement account
Maintain a 2X coverage ratio on debt service
to protect ratings
6
Forecast vs. actual Economic impact Outside influences
7
Management audit underway Collected $5 million from Indiana toll violators Exploring new non-toll revenues Cost saving measures
8
$- $200 $400 $600 $800 $1,000 $1,200 $1,400 $1,600 $1,800 2015 2020 2025 2030 2034 ($ millions)
Total Revenue
(with Commercial Toll Increase)
($ millions) ($ millions) ($ millions)
9
$- $200 $400 $600 $800 $1,000 $1,200 $1,400 $1,600 $1,800 2015 2020 2025 2030 2034 ($ millions)
Total Revenue
(with Commercial Toll Increase)
($ millions)
Operating Expenses (3 percent growth rate)
10
$- $200 $400 $600 $800 $1,000 $1,200 $1,400 $1,600 $1,800 2015 2020 2025 2030 2034 ($ millions)
Total Revenue
(with Commercial Toll Increase)
($ millions)
5 percent growth rate Operating Expenses (3 percent growth rate)
11
$- $200 $400 $600 $800 $1,000 $1,200 $1,400 $1,600 $1,800 2015 2020 2025 2030 2034 ($ millions)
Total Revenue
(with Commercial Toll Increase)
($ millions)
Net Debt Service 5 percent growth rate Operating Expenses (3 percent growth rate)
12
Chicago area has nation’s worst road congestion Congestion costs the Chicago area between
$4 billion and $7 billion annually
CMAP projects 2.5 million more people in
Northeast Illinois by 2040
Tollway must define a 10-year plan by end of
2011
Tollway Board of Directors has identified priority
projects
13
14
Total: $6.1 Billion Through 2026
RECONSTRUCT & WIDEN Jane Addams Memorial Tollway (I-90) – $1.9 B (no transit) RECONSTRUCT Tri-State Tollway (I-94/I-294) – $1.2 B PRESERVE Reagan Memorial Tollway (I-88) – $610 M PRESERVE Veterans Memorial Tollway (I-355) – $400 M REPAIR Roads, Bridges & Maintenance Facilities – $1.39 B Other Capital Projects - $600 M
Maintenance Site Location
15
RECONSTRUCT Tri-State Tollway (I-94/I-294) – $1.2 B PRESERVE Reagan Memorial Tollway (I-88) – $610 M PRESERVE Veterans Memorial Tollway (I-355) – $400 M REPAIR Roads, Bridges & Maintenance Facilities – $1.39 B Other Capital Projects - $600 M RECONSTRUCT & WIDEN Jane Addams Memorial Tollway (I-90) – $1.9 B (no transit) TAKE CARE OF EXISTING SYSTEM NEEDS IL ROUTE 53 NORTH EXTENSION JANE ADDAMS MEMORIAL TOLLWAY (I-90) ELGIN O’HARE WEST BYPASS I-294/I-57 INTERCHANGE ILLIANA
$1.9-$4.5 Billion
Create a state-of-the-art roadway Managed lanes = customer choice Save 30 minutes Elgin to
Rosemont
Planning for transit options,
possibly express bus service now and rail later
Save $400 million if moved
up to 2012
16
$2.2-$3.6 Billion
Better links between O'Hare and surrounding
communities and businesses
Save 18 minutes on 10-mile
trip from Hanover Park to Bensenville
Creates opportunity for
65,000 total jobs by 2040
17
$240-$570 Million
New Interchange to link I-57 and
I-294
Increases economic development
- pportunities throughout
the Chicago Southland
Dramatically improve access to
local communities
Direct freight access to south
suburbs
18
$100 Million
Illinois Route 53 Extension
New Advisory Committee to
develop environmentally sound roadway concept
New, multi-modal design
approach
75% favored extension in
2009 county-wide referendum
Planning could begin in 2012
Illiana
Improve mobility for people
and goods in Will County
Stimulate economic growth
and enhanced freight mobility
Environmental impact studies
expected to take 5-6 years
Continue to support IDOT as
lead agency
19
20
Job #1 - Take care of existing system through 2026 $6.1 Billion Projected revenue $5.1 Billion Projected funding gap $1 Billion Estimated range for potential new projects $2.5 -$6.9 Billion
New Roads
- Fully rebuilt, state-of-the-art system
- Includes three CMAP GO TO 2040 Plan projects
New Jobs
- Start driving the economy
- Regional economic development growth
New Choices
- New access, interchanges and managed lanes
21
Smart investments now can
- Create more than 122,000 direct jobs
$1 billion of annual construction
- Creates more than 13,000 construction-related
jobs annually
- Sustains those jobs for more than 14 years
22
Consider your input Find a balance between available revenue
and potential projects
Continue to use Tollway’s project evaluation criteria:
23
Financial sustainability Community support Maximizing existing assets Promoting economic growth Fostering environmental responsibility Consistency with regional transportation plans
Capital Planning Forums
- July 7 at 10 a.m. at Giovanni’s Restaurant , Rockford
- July 13 at 4 p.m. at the Tinley Park Village Hall
- July 14 at 3 p.m. at the Kane County Government Center, Geneva
- July 15 at 9 a.m. at the Lake County Permit Facility, Libertyville
- July 18 at 10 a.m. at the DuPage County Government Center, Wheaton
Community Outreach
- Comments from communities and customers can be
submitted online at www.illinoistollway.com
Tollway Board Review
- Written comments from Capital Planning Forum participants
and customers will be shared with Tollway Directors
24
27
28
29
35% 6% 14% 16% 30%
Capital Expenditures
Tri-State Tollway (I-94/I-294/I-80) Jane Addams Memorial Tollway (I-90) Reagan Memorial Tollway (I-88) Veterans Memorial Tollway (I-3550 Other Systemwide
Illinois Tollway
- perates as a
system of roadways
Illinois Tollway
System serves Northern Illinois
Revenue leveraged to benefit the
system
Expansion supported by system
47% 22% 16% 15%
Revenue
31
Construction cost savings Union contract negotiated savings Employees per lane mile
32
As of 12/31 Each Year
33