Joint County Board and School Board Work Session New Elementary at - - PowerPoint PPT Presentation

joint county board and school board work session new
SMART_READER_LITE
LIVE PREVIEW

Joint County Board and School Board Work Session New Elementary at - - PowerPoint PPT Presentation

Joint County Board and School Board Work Session New Elementary at Reed Project October 17, 2017 Project Info Project included in the FY 2017-2026 CIP. Expansion to the Reed School to create a new elementary school with at least 725


slide-1
SLIDE 1

Joint County Board and School Board Work Session New Elementary at Reed Project

October 17, 2017

slide-2
SLIDE 2

Project Info

2

  • Project included in the

FY 2017-2026 CIP.

  • Expansion to the Reed School to

create a new elementary school with at least 725 seats, to be completed for the 2021-22 school year, at a maximum cost

  • f $49.0 million.
  • Project will essentially double the

existing square footage on-site to create the needed space.

slide-3
SLIDE 3

Project Info

  • The Children’s School and Integration Station will

vacate the Reed building by July 2018.

  • Reed building will be used as swing space for the

Stratford Program until construction of the new school at Wilson is complete for start of the 2019-20 school year.

  • Westover Branch Library will remain open throughout

construction.

3

slide-4
SLIDE 4

Site Development

4

slide-5
SLIDE 5

Site Development

5

slide-6
SLIDE 6

Site Development

6

slide-7
SLIDE 7

Site Development

7

slide-8
SLIDE 8

Existing Site

  • TBD

8

slide-9
SLIDE 9

Existing Site Functions

9

slide-10
SLIDE 10

Existing Utilities

10

Parkhurst Park

8” Sewer 12” Sewer 84” Storm Sewer

APS Property County Property

slide-11
SLIDE 11

Building Functions (2009)

11

Note: Teen Parenting has since moved to the Arlington Career Center. That space is now used for The Children’s School.

slide-12
SLIDE 12

Existing Site

12

slide-13
SLIDE 13

School Board Actions

  • September 7, 2017 – approved Construction Manager

at-Risk (CMR) delivery method. CMR selection is in process.

  • October 5, 2017 – approved architect/engineering

team contract and BLPC charge, appointment of chair, and membership.

– BLPC School Board Liaison: James Lander – BLPC Chair: Hans Bauman (also a PFRC member)

  • October 17, 2017 (expected) – additional BLPC

membership appointments

13

slide-14
SLIDE 14

Coordinated BLPC/PFRC Process

  • The BLPC and PFRC will hold joint meetings for most

meetings.

  • Process will build on the success of the Fleet

Elementary process and incorporate the lessons learned.

  • BLPC/PFRC leadership will meet regularly with Board

liaisons to develop meeting agendas and discuss critical issues.

  • Several members appointed to both BLPC and PFRC.

14

slide-15
SLIDE 15

BLPC Membership and Charge

  • Based on existing Policy Implementation Procedure (PIP)

50-1.2 and proposed PIP revisions.

  • Representing the following stakeholder groups:

– Parents/PTA: Ashlawn, Discovery, Glebe, McKinley, Nottingham, and Tuckahoe – Civic Associations: Highland Park Overlee Knolls, Westover Village, Tara-Leeway Heights, Leeway Overlee, Madison Manor, and Dominion Hills – Advisory Council on School Facilities and Capital Programs (FAC) – Public Facilities Review Committee (PFRC) – Student Advisory Board – Arlington Public Library staff – Elementary school and Department of Teaching and Learning staff – Department of Facilities and Operations staff

15

slide-16
SLIDE 16

BLPC Membership and Charge

  • The primary role of the BLPC is to

serve as the principal communication liaison with community stakeholders.

  • APS staff shall support the work of

the BLPC and be responsible for the educational specifications, cost control, and schedule management.

16

slide-17
SLIDE 17

BLPC Membership and Charge

  • School Board direction:

– The new school at the Reed Building will be a neighborhood elementary school with an attendance zone. – The BLPC will assist the School Board to achieve Goal 4 of the APS 2011-17 Strategic Plan 4 to Provide Optimal Learning Environments that are adaptable to future changes of use, energy efficient, environmentally sustainable, and provide adequate outdoor space for physical education and recess. – Funding available for the project is the maximum available, unless additional funding is approved by the School Board. Every effort shall be made to complete the project for less than $49 million.

17

slide-18
SLIDE 18

PFRC Membership

  • County Board appointed committee that includes core

members representing Arlington County Commissions.

  • Project specific members also appointed, including

civic association, Westover Farmers Market, and Westover retail representatives.

18

slide-19
SLIDE 19

PFRC Charge - June 18, 2014

19

  • Mission: to ensure that the highest quality of land use

planning, design, transportation planning, and other important community aspects are incorporated into civic projects as assigned to the Committee by the Arlington County Board.

  • Key responsibilities:

– Provide forum for advisory commission and committee input – Ensure highest quality of land use planning and design – Promote compliance with County Comprehensive Plan and

  • ther County planning policies

– Provide means for broad-based public participation – Provide advice to County Board and County Manager

slide-20
SLIDE 20

Project Cost

  • Design team will develop three options at concept phase which

include a minimum, mid-range, and maximum cost.

  • At concept design approval, the School Board will select which
  • ption to be further developed.
  • Apportionment of Joint Fund and Operating Fund sources are

preliminary estimates based on recent project experience and will be refined as the project proceeds through the public process.

20

FY 2017-2026 CIP Project Funding APS County Future Bonds (2018 Referendum) $38,250,000 Capital Reserve $4,000,000 Other (Operating) Funding $1,250,000 Joint Fund $2,750,000 $2,750,000 Subtotal $46,250,000 $2,750,000 Maximum Total Project Funding $49,000,000

slide-21
SLIDE 21

Project Schedule

  • Close collaboration

between BLPC, PFRC, community members, and APS/County staff is needed to maintain the planned schedule.

  • Schedule management is

an important component to efficiently use available funds and prevent cost

  • verruns.

21

slide-22
SLIDE 22

Key Project Milestones

22

Milestone Month Year

Start BLPC and PFRC Process Oct 2017 School Board Action to Approve Concept Design Mar 2018 School Board Action to Approve Schematic Design Jun 2018 Use Permit Submission Jul 2018 County Commission Meetings Oct 2018 County Board Action to Approve Use Permit Nov 2018 Building Permit Submission Dec 2018 Building Permit Approval May 2019 School Board Action to Approve Construction Contract Jun 2019 Start Phase 1 Construction‐Site Jun 2019 Start Phase 2 Construction‐Building Sep 2019 School Opening Sep 2021

slide-23
SLIDE 23

Sustainability Goals

  • Building efficiency and performance characteristics

planned to match those achieved at Discovery Elementary School as far as possible within approved project funding.

  • Facility intended to be Zero Energy:

– Base building systems provided through approved project funding – Solar photovoltaic panels provided through a Solar Power Purchase Agreement (PPA)

  • Efficiency upgrades to the existing building planned to

the maximum extent possible within approved project funding.

23

slide-24
SLIDE 24

Considerations

  • Maintain budget and schedule
  • Enhance student safety
  • Minimize vehicular impact
  • Balance building footprint and open space
  • Provide adequate parking
  • APS property/County property
  • Continuity of library operations
  • Maintain farmers market
  • Minimize disruption to neighbors and local businesses
  • Community/site activities

24

slide-25
SLIDE 25

Public Engagement Plan

  • BLPC, PFRC, and Community Meeting dates are

scheduled and posted on the APS project website: https://www.apsva.us/design-and-construction/new- elementary-school-reed/

  • All BLPC and PFRC meetings are open to the public

and will provide opportunities for public comment.

  • Provide feedback and comments:

– To APS: engage@apsva.us – To Arlington County: https://commissions.arlingtonva.us/planning- commission/public-facilities-review-committee- pfrc/school-projects/walter-reed/

  • October 25, 2017 – Joint BLPC/PFRC Kick-off

25

slide-26
SLIDE 26

Discussion

26