Joint County Board and School Board Work Session New Elementary at - - PowerPoint PPT Presentation
Joint County Board and School Board Work Session New Elementary at - - PowerPoint PPT Presentation
Joint County Board and School Board Work Session New Elementary at Reed Project October 17, 2017 Project Info Project included in the FY 2017-2026 CIP. Expansion to the Reed School to create a new elementary school with at least 725
Project Info
2
- Project included in the
FY 2017-2026 CIP.
- Expansion to the Reed School to
create a new elementary school with at least 725 seats, to be completed for the 2021-22 school year, at a maximum cost
- f $49.0 million.
- Project will essentially double the
existing square footage on-site to create the needed space.
Project Info
- The Children’s School and Integration Station will
vacate the Reed building by July 2018.
- Reed building will be used as swing space for the
Stratford Program until construction of the new school at Wilson is complete for start of the 2019-20 school year.
- Westover Branch Library will remain open throughout
construction.
3
Site Development
4
Site Development
5
Site Development
6
Site Development
7
Existing Site
- TBD
8
Existing Site Functions
9
Existing Utilities
10
Parkhurst Park
8” Sewer 12” Sewer 84” Storm Sewer
APS Property County Property
Building Functions (2009)
11
Note: Teen Parenting has since moved to the Arlington Career Center. That space is now used for The Children’s School.
Existing Site
12
School Board Actions
- September 7, 2017 – approved Construction Manager
at-Risk (CMR) delivery method. CMR selection is in process.
- October 5, 2017 – approved architect/engineering
team contract and BLPC charge, appointment of chair, and membership.
– BLPC School Board Liaison: James Lander – BLPC Chair: Hans Bauman (also a PFRC member)
- October 17, 2017 (expected) – additional BLPC
membership appointments
13
Coordinated BLPC/PFRC Process
- The BLPC and PFRC will hold joint meetings for most
meetings.
- Process will build on the success of the Fleet
Elementary process and incorporate the lessons learned.
- BLPC/PFRC leadership will meet regularly with Board
liaisons to develop meeting agendas and discuss critical issues.
- Several members appointed to both BLPC and PFRC.
14
BLPC Membership and Charge
- Based on existing Policy Implementation Procedure (PIP)
50-1.2 and proposed PIP revisions.
- Representing the following stakeholder groups:
– Parents/PTA: Ashlawn, Discovery, Glebe, McKinley, Nottingham, and Tuckahoe – Civic Associations: Highland Park Overlee Knolls, Westover Village, Tara-Leeway Heights, Leeway Overlee, Madison Manor, and Dominion Hills – Advisory Council on School Facilities and Capital Programs (FAC) – Public Facilities Review Committee (PFRC) – Student Advisory Board – Arlington Public Library staff – Elementary school and Department of Teaching and Learning staff – Department of Facilities and Operations staff
15
BLPC Membership and Charge
- The primary role of the BLPC is to
serve as the principal communication liaison with community stakeholders.
- APS staff shall support the work of
the BLPC and be responsible for the educational specifications, cost control, and schedule management.
16
BLPC Membership and Charge
- School Board direction:
– The new school at the Reed Building will be a neighborhood elementary school with an attendance zone. – The BLPC will assist the School Board to achieve Goal 4 of the APS 2011-17 Strategic Plan 4 to Provide Optimal Learning Environments that are adaptable to future changes of use, energy efficient, environmentally sustainable, and provide adequate outdoor space for physical education and recess. – Funding available for the project is the maximum available, unless additional funding is approved by the School Board. Every effort shall be made to complete the project for less than $49 million.
17
PFRC Membership
- County Board appointed committee that includes core
members representing Arlington County Commissions.
- Project specific members also appointed, including
civic association, Westover Farmers Market, and Westover retail representatives.
18
PFRC Charge - June 18, 2014
19
- Mission: to ensure that the highest quality of land use
planning, design, transportation planning, and other important community aspects are incorporated into civic projects as assigned to the Committee by the Arlington County Board.
- Key responsibilities:
– Provide forum for advisory commission and committee input – Ensure highest quality of land use planning and design – Promote compliance with County Comprehensive Plan and
- ther County planning policies
– Provide means for broad-based public participation – Provide advice to County Board and County Manager
Project Cost
- Design team will develop three options at concept phase which
include a minimum, mid-range, and maximum cost.
- At concept design approval, the School Board will select which
- ption to be further developed.
- Apportionment of Joint Fund and Operating Fund sources are
preliminary estimates based on recent project experience and will be refined as the project proceeds through the public process.
20
FY 2017-2026 CIP Project Funding APS County Future Bonds (2018 Referendum) $38,250,000 Capital Reserve $4,000,000 Other (Operating) Funding $1,250,000 Joint Fund $2,750,000 $2,750,000 Subtotal $46,250,000 $2,750,000 Maximum Total Project Funding $49,000,000
Project Schedule
- Close collaboration
between BLPC, PFRC, community members, and APS/County staff is needed to maintain the planned schedule.
- Schedule management is
an important component to efficiently use available funds and prevent cost
- verruns.
21
Key Project Milestones
22
Milestone Month Year
Start BLPC and PFRC Process Oct 2017 School Board Action to Approve Concept Design Mar 2018 School Board Action to Approve Schematic Design Jun 2018 Use Permit Submission Jul 2018 County Commission Meetings Oct 2018 County Board Action to Approve Use Permit Nov 2018 Building Permit Submission Dec 2018 Building Permit Approval May 2019 School Board Action to Approve Construction Contract Jun 2019 Start Phase 1 Construction‐Site Jun 2019 Start Phase 2 Construction‐Building Sep 2019 School Opening Sep 2021
Sustainability Goals
- Building efficiency and performance characteristics
planned to match those achieved at Discovery Elementary School as far as possible within approved project funding.
- Facility intended to be Zero Energy:
– Base building systems provided through approved project funding – Solar photovoltaic panels provided through a Solar Power Purchase Agreement (PPA)
- Efficiency upgrades to the existing building planned to
the maximum extent possible within approved project funding.
23
Considerations
- Maintain budget and schedule
- Enhance student safety
- Minimize vehicular impact
- Balance building footprint and open space
- Provide adequate parking
- APS property/County property
- Continuity of library operations
- Maintain farmers market
- Minimize disruption to neighbors and local businesses
- Community/site activities
24
Public Engagement Plan
- BLPC, PFRC, and Community Meeting dates are
scheduled and posted on the APS project website: https://www.apsva.us/design-and-construction/new- elementary-school-reed/
- All BLPC and PFRC meetings are open to the public
and will provide opportunities for public comment.
- Provide feedback and comments:
– To APS: engage@apsva.us – To Arlington County: https://commissions.arlingtonva.us/planning- commission/public-facilities-review-committee- pfrc/school-projects/walter-reed/
- October 25, 2017 – Joint BLPC/PFRC Kick-off
25
Discussion
26