Is Energize Eastside needed? 1 What is Energize Eastside? 2 - - PowerPoint PPT Presentation

is energize eastside needed
SMART_READER_LITE
LIVE PREVIEW

Is Energize Eastside needed? 1 What is Energize Eastside? 2 - - PowerPoint PPT Presentation

Is Energize Eastside needed? 1 What is Energize Eastside? 2 Energize Eastside PSEs proposed 18 -mile transmission line through residential neighborhoods Redmond Bellevue Newcastle Renton 230,000 volts Poles from


slide-1
SLIDE 1

Is Energize Eastside needed?

1

slide-2
SLIDE 2

What is Energize Eastside?

2

slide-3
SLIDE 3

Energize Eastside

  • PSE’s proposed 18-mile transmission line

through residential neighborhoods

  • Redmond
  • Bellevue
  • Newcastle
  • Renton
  • 230,000 volts
  • Poles from 85 - 130 feet high
  • Lifetime cost: $1.4 - $2.0 billion

3

slide-4
SLIDE 4

Who is Richard Lauckhart?

4

slide-5
SLIDE 5

George B. Lawrence (grandfather)

Founded International Electric Company Stewart, BC (1922)

5

slide-6
SLIDE 6

Donald W. Lauckhart (father)

Worked at Puget Power’s Shuffleton power plant Manager, Grays Harbor PUD Aberdeen, WA

6

slide-7
SLIDE 7
  • J. Richard Lauckhart

Puget Power (22 years) Vice president of power planning (4 years) Industry consultant (20 years)

7

slide-8
SLIDE 8

How did I get involved with CENSE?

8

slide-9
SLIDE 9

In April 2015…

You don’t know me, but could you look at this PSE project that is confusing us?

9

slide-10
SLIDE 10

What is a “load flow study?”

10

slide-11
SLIDE 11

Grids can get complicated. We use computer simulations to study how the grid reacts in different situations. Red lines show transmission lines not distribution lines.

11

slide-12
SLIDE 12

Load flow study

Inputs

  • Physical layout of grid
  • How much electricity is needed
  • How much electricity can be generated
  • Resistance in each wire

Outputs

  • How much electricity passes

through each part

  • Warning if any part overloads
  • Warning if voltage drops too much

12

slide-13
SLIDE 13

Load flow study for Energize Eastside

  • PSE/Quanta did a load flow study to justify Energize Eastside (2013)
  • Scenario: two critical transformers fail during heavy winter

consumption (WECC Base Case)

  • PSE added two more assumptions:
  • Triple flow to Canada (from 500 MW to 1,500 MW)
  • Six local generation plants out of service
  • Result: remaining infrastructure would overload
  • Described in “Eastside Needs Assessment”

13

slide-14
SLIDE 14

Did PSE do the study correctly?

  • Did PSE model transformers correctly?
  • Did PSE modify line resistance?
  • Did PSE make sure voltage output was okay?
  • Did PSE look at both local and regional grid outputs?

14

slide-15
SLIDE 15

Did PSE correctly model all area 230/115 KV transformers?

14 other transformers share the load.

(discovered through simulation)

15

slide-16
SLIDE 16

Our own load flow study

I asked PSE for CEII clearance. (Sept. 2015) PSE said I didn’t have a “legitimate need.” (Oct. 2015) I recruited Roger Schiffman. (Nov. 2015) We got WECC Base Cases from FERC, licensed the software, and started the simulation. (Nov. 2015)

16

slide-17
SLIDE 17

Puget Sound region

1,600 MW of local generation

WECC Base Case

500 MW to Canada 200 MW to Portland 8100 MW from Columbia River hydro, coal, wind

17

slide-18
SLIDE 18

Puget Sound region

PSE’s scenario

1,500 MW to Canada 200 MW to Portland

?

260 MW of local generation

18

slide-19
SLIDE 19

What’s going wrong?

We tried to simulate PSE’s scenario. The computer couldn’t solve it. We ran the unmodified WECC Base Case. No problems. PSE’s scenario overloads 11 transmission lines that connect the Puget Sound to power sources in central Washington.

The scenario is unworkable!

19

slide-20
SLIDE 20

100% 115% 109% 131%

Summer Normal Summer Emergency Winter Normal Winter Emergency

Relative transformer capacities

Another problem

PSE appears to be using “summer normal” capacity ratings for transformers in a “winter emergency” scenario.

20

slide-21
SLIDE 21

Forecast discrepancy

PSE used forecast growth of 2.4% per year to justify the project. PSE sent WECC a forecast of only 0.5% per year. Can this discrepancy be explained?

21

slide-22
SLIDE 22

PSE must release data

PSE must release its data to experts with appropriate clearance. We can verify how PSE solved problems in this scenario. Otherwise, we must conclude Energize Eastside is not needed.

22

slide-23
SLIDE 23

23

slide-24
SLIDE 24

Lines cross in 2058

System capacity (from transformer capacity) Customer demand (from simulation and WECC)

24

slide-25
SLIDE 25

We have time to select the best alternative. No Action Alternative

  • Best alternative for the short term (2018)
  • Meets reliability standards
  • Saves dollars and trees

25

slide-26
SLIDE 26

Alternative 2: Integrated Resource Approach

  • Can be significantly reduced in cost and scale in the

near term

  • Improves reliability in the long term
  • Batteries and other technologies become more

viable with longer timeline

  • Lowers carbon emissions

26

slide-27
SLIDE 27

Alternative 3: New 230/115 kV transformers

  • Can be significantly reduced in scale
  • No new transmission lines
  • May be cheaper than Alternative 2 (short term)

27

slide-28
SLIDE 28

New alternative: Replace Shuffleton

  • Find new location for gas generation plant to

replace Shuffleton plant

  • Profits from sale of Shuffleton could offset cost for

rate payers

  • PSE created shortfall of emergency power when

Shuffleton was sold

28

slide-29
SLIDE 29

PSE’s forecast is –

  • Not supported by data reviewed by stakeholders
  • Based on assumptions that cannot happen
  • Questionable due to mistakes (transformer capacities)
  • Apparently inconsistent (WECC vs. Energize Eastside

studies)

29

slide-30
SLIDE 30

Energize Eastside is –

  • Needlessly wasteful of ratepayer funds
  • Harmful to the Eastside and the environment
  • Not the best solution for reliability or safety
  • May be motivated to maximize investor returns

30

slide-31
SLIDE 31

Alternative solutions are –

  • Less expensive
  • Lower impact for residents and scenery
  • A better way to leverage developing technology
  • More supportive of environmental goals

31