Is Energize Eastside needed?
1
Is Energize Eastside needed? 1 What is Energize Eastside? 2 - - PowerPoint PPT Presentation
Is Energize Eastside needed? 1 What is Energize Eastside? 2 Energize Eastside PSEs proposed 18 -mile transmission line through residential neighborhoods Redmond Bellevue Newcastle Renton 230,000 volts Poles from
1
2
through residential neighborhoods
3
4
George B. Lawrence (grandfather)
Founded International Electric Company Stewart, BC (1922)
5
Donald W. Lauckhart (father)
Worked at Puget Power’s Shuffleton power plant Manager, Grays Harbor PUD Aberdeen, WA
6
Puget Power (22 years) Vice president of power planning (4 years) Industry consultant (20 years)
7
8
In April 2015…
You don’t know me, but could you look at this PSE project that is confusing us?
9
10
Grids can get complicated. We use computer simulations to study how the grid reacts in different situations. Red lines show transmission lines not distribution lines.
11
Inputs
Outputs
through each part
12
consumption (WECC Base Case)
13
14
Did PSE correctly model all area 230/115 KV transformers?
14 other transformers share the load.
(discovered through simulation)
15
Our own load flow study
I asked PSE for CEII clearance. (Sept. 2015) PSE said I didn’t have a “legitimate need.” (Oct. 2015) I recruited Roger Schiffman. (Nov. 2015) We got WECC Base Cases from FERC, licensed the software, and started the simulation. (Nov. 2015)
16
Puget Sound region
1,600 MW of local generation
WECC Base Case
500 MW to Canada 200 MW to Portland 8100 MW from Columbia River hydro, coal, wind
17
Puget Sound region
PSE’s scenario
1,500 MW to Canada 200 MW to Portland
260 MW of local generation
18
What’s going wrong?
We tried to simulate PSE’s scenario. The computer couldn’t solve it. We ran the unmodified WECC Base Case. No problems. PSE’s scenario overloads 11 transmission lines that connect the Puget Sound to power sources in central Washington.
The scenario is unworkable!
19
100% 115% 109% 131%
Summer Normal Summer Emergency Winter Normal Winter Emergency
Relative transformer capacities
PSE appears to be using “summer normal” capacity ratings for transformers in a “winter emergency” scenario.
20
Forecast discrepancy
PSE used forecast growth of 2.4% per year to justify the project. PSE sent WECC a forecast of only 0.5% per year. Can this discrepancy be explained?
21
PSE must release data
PSE must release its data to experts with appropriate clearance. We can verify how PSE solved problems in this scenario. Otherwise, we must conclude Energize Eastside is not needed.
22
23
Lines cross in 2058
System capacity (from transformer capacity) Customer demand (from simulation and WECC)
24
We have time to select the best alternative. No Action Alternative
25
Alternative 2: Integrated Resource Approach
near term
viable with longer timeline
26
Alternative 3: New 230/115 kV transformers
27
New alternative: Replace Shuffleton
replace Shuffleton plant
rate payers
Shuffleton was sold
28
PSE’s forecast is –
studies)
29
Energize Eastside is –
30
Alternative solutions are –
31