Interstate 77 Panther Interchange York County EARLY COORDINATION - - PowerPoint PPT Presentation

interstate 77 panther interchange
SMART_READER_LITE
LIVE PREVIEW

Interstate 77 Panther Interchange York County EARLY COORDINATION - - PowerPoint PPT Presentation

Interstate 77 Panther Interchange York County EARLY COORDINATION MEETING JANUARY 21, 2020 Disclaimer All information provided today is for information only, non binding, does not constitute legal or other advice, and does not amend or


slide-1
SLIDE 1

Interstate 77 Panther Interchange

York County

EARLY COORDINATION MEETING

JANUARY 21, 2020

slide-2
SLIDE 2

Disclaimer

All information provided today is for information only, non‐ binding, does not constitute legal or other advice, and does not amend or form part of the Final Request for Proposals (RFP).

slide-3
SLIDE 3

Purpose

Provide information Get feedback and answer questions

slide-4
SLIDE 4

Agenda

 Project Overview  Project Considerations  Project Schedule  Next Steps

slide-5
SLIDE 5

Project Overview

slide-6
SLIDE 6

Project Location

I‐77 in York County Approximately 1 mile south of US 21 Bypass/Cherry Rd (Exit 82) Approximately 1.5 miles north

  • f SC 122/Dave Lyle Blvd (Exit

79) Exit 82 – Cherry Rd. Proposed Interchange Exit 79 – Dave Lyle Blvd.

Future Carolina Panther Development

Eden Terrace Bridge Railroad Bridge

slide-7
SLIDE 7

Interchange Concept

slide-8
SLIDE 8

Preliminary Engineering

 Roadway and Structures

 30% Design  Survey  Pavement

 Geotechnical

 Baseline report with extensive exploration and testing plan

 Hydrology

 Drainage concept and pond sizing  Pipe inspection report

Traffic

 IJR  Conceptual MOT plans

 Utilities

 Preliminary Utility Report

slide-9
SLIDE 9

Project Considerations

OPEN FORUM

slide-10
SLIDE 10

Third Party Coordination

SCDOT/SCDOC responsible for:

 USACE permit and all mitigation associated with conceptual interchange layout  NEPA and IJR approval  Utility relocation and right of way acquisition associated with conceptual interchange layout

 Successful DB team responsible for:

 Coordination with developer constructing Panther’s facility (tie‐in to project limits, utility installation, etc.)

slide-11
SLIDE 11

Utilities

Duke Energy Overhead Transmission Line Full relocation: February 2021 Existing ‐‐‐ Approximate Existing Utilities under Paragon Way Existing Aerial Electric/Fiber

slide-12
SLIDE 12

Utilities

Duke Energy Overhead Transmission Line Full relocation: February 2021 Future Relocation

‐‐‐ Approximate

slide-13
SLIDE 13

Right of Way

slide-14
SLIDE 14

Procurement

Considering:

 Expedited procurement schedule  Two‐phase  Weighted criteria

 Cost  Technical Score  Quality Credits  SOQ Score

 Limited ATCs  Stipends for responsive, unsuccessful, shortlisted teams  Incentive for early completion

slide-15
SLIDE 15

Project Schedule

slide-16
SLIDE 16

2020 2021 2022 FEB. MAR. APR. MAY JUNE Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 USACE Permit Approval RFQ Phase NEPA/IJR Approval RFP Phase/ Public Announcement ROW Acquisition Utility Relocation NTP Final Design/ Construction Substantial Completion

slide-17
SLIDE 17

Additional Questions/ Discussion

slide-18
SLIDE 18

Feedback

PROVIDE BY JANUARY 31, 2020 EMAIL: DRAFTSKR@SCDOT.ORG