interstate 77 panther interchange
play

Interstate 77 Panther Interchange York County EARLY COORDINATION - PowerPoint PPT Presentation

Interstate 77 Panther Interchange York County EARLY COORDINATION MEETING JANUARY 21, 2020 Disclaimer All information provided today is for information only, non binding, does not constitute legal or other advice, and does not amend or


  1. Interstate 77 Panther Interchange York County EARLY COORDINATION MEETING JANUARY 21, 2020

  2. Disclaimer All information provided today is for information only, non‐ binding, does not constitute legal or other advice, and does not amend or form part of the Final Request for Proposals (RFP).

  3. Purpose Get feedback and answer Provide information questions

  4. Agenda  Project Overview  Project Considerations  Project Schedule  Next Steps

  5. Project Overview

  6. Exit 82 – Cherry Rd. Eden Terrace Bridge Project Location I‐77 in York County Proposed Approximately 1 mile south of Interchange US 21 Bypass/Cherry Rd (Exit Future 82) Carolina Panther Approximately 1.5 miles north Development Railroad Bridge of SC 122/Dave Lyle Blvd (Exit 79) Exit 79 – Dave Lyle Blvd.

  7. Interchange Concept

  8. Preliminary Engineering  Roadway and Structures  30% Design  Survey  Pavement  Geotechnical  Baseline report with extensive exploration and testing plan  Hydrology  Drainage concept and pond sizing  Pipe inspection report  Traffic  IJR  Conceptual MOT plans  Utilities  Preliminary Utility Report

  9. Project Considerations OPEN FORUM

  10.  SCDOT/SCDOC responsible for:  USACE permit and all mitigation associated with conceptual interchange layout Third Party  NEPA and IJR approval  Utility relocation and right of way acquisition Coordination associated with conceptual interchange layout  Successful DB team responsible for:  Coordination with developer constructing Panther’s facility (tie‐in to project limits, utility installation, etc.)

  11. Existing Existing Aerial Electric/Fiber Utilities Duke Energy Overhead Transmission Line Full relocation: February 2021 Existing Utilities under Paragon Way ‐‐‐ Approximate

  12. Future Relocation Utilities Duke Energy Overhead Transmission Line Full relocation: February 2021 ‐‐‐ Approximate

  13. Right of Way

  14. Considering:  Expedited procurement schedule  Two‐phase  Weighted criteria Procurement  Cost  Technical Score  Quality Credits  SOQ Score  Limited ATCs  Stipends for responsive, unsuccessful, shortlisted teams  Incentive for early completion

  15. Project Schedule

  16. 2020 2021 2022 FEB. MAR. APR. MAY JUNE Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 USACE Permit Approval RFQ Phase NEPA/IJR Approval RFP Phase/ Public Announcement ROW Acquisition Utility Relocation NTP Final Design/ Construction Substantial Completion

  17. Additional Questions/ Discussion

  18. Feedback PROVIDE BY JANUARY 31, 2020 EMAIL: DRAFTSKR@SCDOT.ORG

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend