Interface between CISC and Detector Facilities
- A. Cervera
- S. Gollapinni
CISC meeting 13/02/2019
Interface between CISC and Detector Facilities A. Cervera S. - - PowerPoint PPT Presentation
CISC meeting 13/02/2019 Interface between CISC and Detector Facilities A. Cervera S. Gollapinni Contents of interface document Introduction Detector Integration DUNE Detector Infrastructure Detector Support Structures (DSS)
CISC meeting 13/02/2019
Anselmo Cervera Villanueva, IFIC (UV-CSIC)—Valencia
2
Anselmo Cervera Villanueva, IFIC (UV-CSIC)—Valencia
3
Anselmo Cervera Villanueva, IFIC (UV-CSIC)—Valencia
gradient monitors, Individual sensors and cameras. The distribution of those systems is yet to be finalized and hence the
combined decision between CISC and the DUNE Technical Coordination. CISC will purchase the flanges.
(DSS and non-DSS) ports.
another and any extra ground connections. The cable shield grounding should be configured flexibly.
4
Anselmo Cervera Villanueva, IFIC (UV-CSIC)—Valencia
cables from Static T-gradient monitors, individual temperature sensors, cold cameras and light emitting system. The distribution of sensors/ cameras/lights and their optimal cable routing is not yet decided. The choice of ports to be used and the exact cable path should be a combined decision between CISC and the DUNE Technical Coordination. CISC will purchase the flanges.
each port will have a diameter of 20 mm
structures are under consideration: cable trays could be attached to bolts in the detector corners (joints between two walls, including floor and roof), or those bolts could be used directly attaching the appropriate individual supports (rings, etc.).
monitors will need an horizontal space of 1 m2 on top of the selected ports (motor, …), and a vertical space of at least 3.5 m (more will simplify the installation). Inspection cameras will need a space of 1.5(vertical)x2x1.5 m3 on top of the selected ports if the glove box design is used (https:// arxiv.org/pdf/0903.0441.pdf, page 5), and 2.5 (vertical) x 0.5 x 0.5 for the periscope version.
the case any of these devices are installed below the mezzanine the required vertical space is sufficient; otherwise, ports outside the mezzanine should be chosen. Need to be clarified. Precise location, clearance needed, etc
5
Anselmo Cervera Villanueva, IFIC (UV-CSIC)—Valencia
need to go within each rack, the rack space requirements for needed power supplies and crates, etc.):
power to this unit will be derived from the common rack AC power; no specific power requirements are needed. IT IS 2U IN THE CISC/DAQ INTERFACE DOC.
Ethernet switches will be required in each rack to network devices including the 1U rack monitoring box mentioned above and Slow Controls servers. The network box is expected to be attached to the inside side wall
purity monitors) that require power. Some of these systems will require crates and cooling may be needed using external fans. The Consortium is working on finalizing these details and plans to include them in a future iteration
supply thermal interlock status bits, rack protection system status bit and all device interlock status bits that are housed in a given rack.
6
Anselmo Cervera Villanueva, IFIC (UV-CSIC)—Valencia
diameter of 10 mm for 6 sensors. It is not yet decided whether those cables will be used in DUNE.
in a future draft.
cable end locations, special routing requirements, etc.): more details needed
corresponding hardware (e.g. power supply) housed in the rack.
common need and is expected to fall under the scope of facility.
readout system on the racks and the edge on the flange will be left floating. Not true, what about inline PrMs and gas analysers ?
be shielded and grounded near the point of readout in the racks. Fiber connections do not use electrical shielding for signal integrity, but if they have metallic shielding for protection, the shielding should be connected to ground, preferably at the racks.
7
Anselmo Cervera Villanueva, IFIC (UV-CSIC)—Valencia
such as power to the network box, power to slow controls rack monitoring box (typically less than a few volts) are generally covered under common rack infrastructure. For the power supplies and crates that CISC will monitor, defining power requirements is under the scope of each sub-system consortia. CISC just provides monitoring and control of the system including any monitoring of any variables related to power.
power supply that will require power). The details of power requirements for instrumentation devices is still being worked out and will be included in a future iteration of this document. THESE REQUIREMENTS SHOULD BE AVAILABLE FROM PROTODUNE
servers in the DAQ room. But, this will be addressed as part of the common infrastructure for racks and the server room. CISC will provide monitoring of fans within the CISC Servers (and others) as part of CPU hardware monitoring.
beyond a few volts, will require cooling through external rack fans (included as part of the common rack infrastructure) or internal fans provided by the power supply manufacturer themselves. For systems that will use crates, the depth of the crate decides the level of cooling needed. None of these details are finalized for instrumentation devices yet and the goal is to address them in a future iteration of this document.
8
Anselmo Cervera Villanueva, IFIC (UV-CSIC)—Valencia
corresponding cables. Following ProtoDUNE-SP design, split clamps of the appropriate diameter will be used to hold Teflon supports for cables and FR4 supports for sensors. The distribution of sensors has not been decided yet; this as well as the design and fabrication of the supports, the cable routing and the installation of sensors is the responsibility of the CISC consortium.
does not interfere with photon-detectors or their associated mechanical structure and cables.
monitors to be closer to the field cage and thus measure a more representative purity. This option is under discussion with the technical coordination team.
connected to the flange and will be left floating at the sensor side. Link to a document explaining it
the connection to the pipes should be such that no grounding loop is introduced. MOST LIKELY TO BE
9
Anselmo Cervera Villanueva, IFIC (UV-CSIC)—Valencia
surges etc.) status bit monitoring
hardware for the interlocks and related design is not under the scope of the CISC consortium
leaks (from the cryogenics system) and smoke/fire. Status of the elevators can also be provided to shifters if that information can be accessed. Additionally, monitoring the status of surrounding facilities (e.g. Majorana) will be useful since being underground there can be impact on safety at the LBNF facility
alarms:
slow controls rack monitoring box and it is expected that the rack safety system should turn off the entire rack (including the box) during conditions such as fire.
thermometers and camera systems.
safety by pipelining information into the slow controls to give one integrated view to the shifters in the control room.
10
Anselmo Cervera Villanueva, IFIC (UV-CSIC)—Valencia
gradient monitors, which will cover the entire height of the cryostat. Being the load on those structures relatively small (<100 kg) they can be fabricated in parts of less than 3 m, which can be easily transported to SURF. No special considerations needed to be taken into account to take those containers underground.
the underground areas are quite modest, since those devices are in general small. We should be more
underground area and the surface will be needed and is an important interface for CISC.
consortia components in both the detector caverns and the central utility cavern.
11
Anselmo Cervera Villanueva, IFIC (UV-CSIC)—Valencia
cryostat engineering team and are incorporated in the current design. The standard size of the cryostat penetration is sufficient. One dedicated port on the East side near mid-drift outside the field cage is provided for deployment of dynamic T-gradient monitoring system. For all other instrumentation needs, multi-purpose calibration and instrumentation ports, side flange accommodations made on the DSS and Cryogenic ports will be used. See Section 2 of this document for more details. In the coming months, cryostat penetrations requirements for DP will be worked out in detail. AGAIN, WE CAN PROBABLY REMOVE CRYOGENIC PORTS
entire height of the cryostat. The horizontal space needed there is less than 0.3x0.3 m2. Static T-gradient monitors will be installed behind the APAs, but the space needed is quite modest: 0.4x0.05 m2
and static). Although the proper 3D models and rigidity studies should still be done, most likely intermediate anchoring points will be needed. In the case of static T-gradient monitors, which sit behind the APAs, those intermediate anchoring points must necessarily be welded into the membrane. Loads are expected to be very small since the purpose of those anchoring points is just to keep the system vertical. For dynamic T-gradient monitors and purity monitors the choice of intermediate anchoring points is not that obvious: vertical cryogenic pipes and cable trays in the corners are under consideration. In the case of purity monitors, if they will be located close to the corners (which is the current plan), the cable trays in the corners or the bolts in the corners will be used to support them. TO BE UPDATED. MOST LIKELY NO NEED OF INTERMEDIATE ANCHORING POINT FOR STATIC T-GRADIENT MONITORS. DYNAMIC COULD USE SOMETHING THAT KEEPS THE DISTANCE TO THE FIELD CAGE END-WALLS
12
Anselmo Cervera Villanueva, IFIC (UV-CSIC)—Valencia
13
TPC Dynamic profiler
bottom cup spacer FC end-wall
Anselmo Cervera Villanueva, IFIC (UV-CSIC)—Valencia
CISC will indirectly interface with the Cryogenics control system to export data into slow controls process variables for archiving and status displays for the experiment operators, and to provide integrated archiving for sampled data in the archived database.
needed here or link to a DocDB document
pressure level meters from the cryogenics system. Thus CISC will interface with Liquid level expert control system to extract important information to be displayed for shifters in the control room. Explain better what those level meters are for and distinguish them from capacitive level meters
14