initial considerations
play

Initial Considerations Inception & Feasibility Design - PowerPoint PPT Presentation

Initial Considerations Inception & Feasibility Design (traditional) / Concept (package deal) Authority Approvals Determining Procurement & Pricing Structure Determining Other Risk Allocations Conditions &


  1. Initial Considerations • Inception & Feasibility • Design (traditional) / Concept (package deal) • Authority Approvals • Determining Procurement & Pricing Structure • Determining Other Risk Allocations • Conditions & Contractual Documents • Tendering

  2. Procurement & Pricing Linked • Design Responsibility? Determinative of Best Pricing Structure Norm • Turnkey/Package/Design & Build = Lump Sum Pricing • Traditional Structure = Re-measured BQ Pricing • Hybrids = Mixed Pricing Mechanism

  3. Procurement & Pricing Linked • Type of Work – Sub-Structure = Re-measured BQ – Super Structure = Lump Sum – Preliminaries = Lump Sum – Specialist Design & Construct NSCs = Lump Sum – Underground Complex & Innovative Work = Cost Reimbursable with Target Cost Incentives and Dis- Incentives

  4. Lowest Price or PQM ? Developer’s Risk – Lowest Price • Claims Orientated Contractor? • Insolvent Contractor? • Under-Perform & Delays? • Poor Workmanship? • Under-Design? • Replacement Contractor Cost?

  5. PQM • Weightage to Quality • Project Specific Proposal – Technical & Time • Past & On-Going Projects – On time or Delayed – EOT or LAD – Quality Performances (QLASSIC/CONQUAS etc.) – Safety Record (DOSH) – Green Building Certification History

  6. Lump Sum Pricing • Agreed Price/ Firm Price? • ↑↓ Quantities of Work = No Changes • ↑↓ Scope of Work = Variation • ↑ ↓Limit of Work = Variation • w/wo BQ + Drawing + Specification • BQ for Progress Payment Purposes? • BQ : Misrepresentation? Exclusion Provision? • Limit of Works = Drawing + Specification

  7. Lump Sum Pricing • One-Off Payment at End • Stage / Milestone Payment • Interim % Completed Payment • Contract Sum Analysis • Rationalization of Prices for Variations • Fluctuation Clauses – Currency – Materials (Fixed Sums)

  8. Why Lump Sum? • Competitive Pricing • Owner’s Cost Certainty or is it? • Better Scope Definition • Allocation of Risk Clearer • Faster Tender Preparation Process? • Incentive for Efficiency with Prospect of Loss? • Focuses Team on Same Target

  9. Effect of Lump Sum • Tendering Process Longer • Attracts Higher Price : Contingency Pricing • Contractor’s Risk Higher • Drawings & Specifications Certainty? • Cannot Fast Track • Project Control must be Strong • All Information Available Provided? • Attracts Claims Orientated Contractor • Increased Risk of Disputes - Variations

  10. LS: Pitfalls & Avoidance • Design finalised and certain? – Budget explosion ↑ Delay Tender? – Fast Track: Contingency Pricing in Rates – Provisional Sum Works/ Provisional PC Sum Works (PAM 2006 removed Provisional PC Sum Works?) – BQ as Schedule of Rates? 1 st Stage Tendering based on Competitive BQ? – Is the Schedule of Rates thorough?

  11. LS: Pitfalls & Avoidance • Avoid Contingency Pricing – Provide all Information in Possession but without Assurance on Veracity or Accuracy – Site Visit – Sufficient Time to Study Conditions within Site and Access to and within Site – Geo technical information but with Exclusion as to Accuracy – Deemed Knowledge protects Legal Exposure but Not Contingency Pricing

  12. LS: Pitfalls & Avoidance • Lump Sum for Geo-technical Works – Danger of Contingency Pricing if no Information or Qualified Information – Allow Contractor to carry out own soil Investigations : Not many do • Pre-qualified and selective tenderers allowed to assess geo-technical conditions (possible 2 stage) • Allowance for the tenderers that carry out their own geo-technical studies if they are later not appointed • Alternative: Tender First and then Right to Re-Price Tender if Compulsory Investigation drastically different

  13. LS: Pitfalls & Avoidance • Front End Loading on Works – Contract Sum Analysis – Rationalisation of LS Possible

  14. Re-measured Pricing • Price = Fluctuations on Quantities x Rates • BQ = Approximate Quantities • BQ = Rates Determined by Contractor • BQ = Scope of Works but Quantities can Fluctuate • Schedule of Price = Variations • Re-measured at the end : Physical or Take-offs from as-builts

  15. Re-measured Pricing • Safest Win-Win Approach • Rates can Fluctuate? • Material Price Index Fluctuation (need rationalization) • Formula increase/decrease if Quantities increase/decrease • Where Quantities Remain Uncertain – soil / substructure piling • Fast Track Project

  16. BQ: Pitfalls & Avoidance • Design finalised and certain? – Budget explosion ↑ Delay Tender? – Fast Track: Contingency Pricing in Rates – Provisional Sum Works/ Provisional PC Sum Works (PAM 2006 removed Provisional PC Sum Works?) – Allow Rate Fluctuation based on % ↑↓ • Extrapolated/Pre-Weighted Rate? • Rationalised Make- up Rate with Only Factor ↑↓ • Labour Efficiency Factor Rate ↑↓ • Margin Spread % Factor ↑↓

  17. BQ: Pitfalls & Avoidance • Mitsui Construction Co v The AG of Hong Kong – ignore contingency pricing for provisional quantities • BQ ↑↓ Preliminaries ↑↓? – Increased Quantities affects Quantity based Preliminaries : Supervision/QAQC etc. – Critical path quantities – within same time • Is the take-off for BQ accurate/precise? – Under-Quantified Items: Profit Loading – Chance of budget burst ↑ – Independent Checker Pre- Tender? Cost ↑

  18. BQ: Pitfalls & Avoidance • Are the profits front loaded? – Proper Rationalisation is Required – Rationalisation Provision in the Contract or BQ (PAM 2006 : Errors to be Rationalised) – Not Errors but Unreasonably Weighted Rates – To ensure Equal Profit Margin Spread – SO’s view of rationalisation deemed final unless proven to be unfairly end loaded

  19. BQ: Pitfalls and Avoidance • Standards of Measurement clear? – Is the Preamble to BQ thorough & clear? – Is the Malaysian SMMs made applicable? – What about other SMMs that are wider? – SMMs do not cover every area of Work! – Is there industry practice? (PAM 2006: SMM sanctioned by ISM & currently in force?) – Have “extra overs” been allowed in the BQ?

  20. BQ: Pitfalls & Avoidance • BQ Description of Works v Drawings & Specifications – ↑ Descriptions = ↑ Ambiguity/ Discrepancy (Pam 2006 = quality of work set out in BQ?) (PAM 2006 = error in description to be corrected by SO = variation) – Priority Provision? No Contra Proferentum – Duty to Identify & Raise : Tender & Before Commencement : Bound by Clarification – Duty to Rectify at Costs if not Sought Clarification

  21. BQ: Pitfalls & Avoidance • BQ: Not all items of Work Listed – Preliminaries Contingency Pricing for Works Not Listed but Shown in Drawings – Deemed Priced into other Items Listed – Inclusive Price Principle • Seems to have been abandoned by Malaysian standard Forms • Temporary works priced under preliminaries and deemed part of obligation considered sufficient

  22. BQ: Pitfalls & Avoidance – Inclusive Price Principle • What about Works that are not Mentioned or Shown but a reasonable experienced contractor would realise is Indispensably and Contingently Necessary: Deemed Priced in Rates and Items in BQ • Indispensable = work that is necessary for Final Works to comply with Contractual Requirements • Contingently = work that is necessary to complete the Final Works • Needed to cover for any missing BQ Items of Work AE Farr Ltd v Ministry of Transport (excavation of temporary work space not covered under BQ: variation)

  23. The questions to ask? • Is cost control a major consideration? • Do you wish to control the contingencies? • Is a bid competition required? • Prefer max or min owner involvement? • Do you/consultants have skill and experience –design, cost control, supervision, contract administration?

  24. The questions to ask? • Do you want single source responsibility? • Do you require the contractor to provide project funding? • Are the project design, scope and specifications clearly defined? • Are the quantities certain? • Is there minimal scope changes expected? • Is it Fast Track?

  25. The questions to ask? • Is the schedule tight? • Is the project environment volatile or stable? • Does the project involve primarily new technology? • High Quality Control Standards Required? • Contractual Remedies Provided & Can be Controlled?

  26. Pricing Turnkey/Package/D&B • How do you compare the best price where designs differ? – 2 Stage Tendering • Cost & Time • Losing Tenderers Cost? • Design Optimisation? – Design Checkers? Increases Cost & Defeats Purpose – Avoid Competition in Under-Designing

  27. O&G: FEED Contracting + LS • Front End Engineering Design – 2 Stage Construction – 1 st Stage: Feasibility, Concept, Development Opportunities, Sanctioned Budget + Schedule & Design – Specialist Contractor who Develops for Owner – Value Engineering at its Highest & Cost Efficient Development Methodology Inclusive – Best Cost & Time from Contractor’s Perspective – 2 nd Stage: FEED Contractor Project Manage - Execution

  28. FEED Needed • Innovative Design & Construction • Patented Systems Required • New Technology • But Cost is High but Returns Great • Production Sharing/Risk Sharing

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend