In the Name of Allah
October 1
In the Name of Allah October 1 Islamic Republic of Afghanistan - - PowerPoint PPT Presentation
In the Name of Allah October 1 Islamic Republic of Afghanistan Ministry of Energy and Water Status of the Power Sector in Afghanistan Past, Present, and Future October 2 Power generation and import has been increased from 291 MW to
October 1
October 2
Power generation and import has been
Installed capacity to import power from
Total 110 KV, 220 KV transmission lines
Total number of consumers has been
October 3
4
– 25 MW from 110 KV T/L to Andkhoy, Jawzjan, Saripul, and Maymana – 25 MW from 110 KV T/L to Herat and Rubat Sangi
– 120 MW through 132 KV double circuit TL to Herat and Ghorian substations – 10 MW through 20 KV single circuit to Herat – 20 MW through 20 KV double circuit to NimRoz
Hydro Natural gas Petroleum Coal Renewable Energy
October 6
Hydro power potential: 23,000 MW (large, medium,
Natural gas: 60 billion cm3 approx. Petroleum : 12 million tons Coal reserves : 100 million tons (in different
Solar and wind potential: (Mapping to be completed
Most of these foresaid reserves have not been
October 7
Rehabilitation of the existing Hydro and
Upgrading of Distributing Networks in order
Importing power from neighboring
Developing Renewable Energy resources
October 8
Completion of NEPS high voltage
Development of domestic sources of energy Installation of a gas-fired thermal power
October 9
➢ HPP Detai
ail Design ign Initiate ated and ongoing: ng: Baghdara Hydro Power Plant Kukcha & Kunar Kilaghai Kama River (starting) Fara Roud Gul Bahar
➢ HPP Detai
ail Design ign to be be initiate ated: Surobi 2 Kajakai 2 Olambagh Amu & Panj River Kala Gosh Kuner
October 10
1-CASA
May 18 11
The HVAC T/L route commences at the Datka substation in Kyrgyz and terminates at Khoudjand substation in Tajikistan
HVDC converter stations are located at Sangtuda -1 (1300 MW), Kabul (300 MW) and Peshawar (1300 MW)
Length of the T/L route (in km):
Kyrgyz – Tajikistan interconnection – 450
Tajikistan – 117
Afghanistan - 562
Pakistan – 71
October . 12
A 450 km 500 kv HVAC transmission line between
October 13
May 18 14
ADB: AFG-TMK K Regional al Interc rcon
tion Projec ect ADB: AFG-TMK K 500kVInte terc rcon
tion Pul-e-Khumri ADB: Addition itional al Hindu Kosh Crossin ing g (Salan lang Pass) Resolve ve currently tly transmis ission ion capac pacitity itity constrain traints ts USAID ID, , USFOR-A and ADB: SEPS
PS – South
East Power r System double ble circuit it only ly one to be strung Khost Bannu CASA-1000 DC 500kV
Surkhan Sangtuda
Legend
Exist 220kV Future AC 500kV CASA- 000MWDC 500kV Future AC 220kV SEPS’s 220kV Reinforcement to Pakistan
Interc rcon
tion with Pakis istan tan reinforc
ing g SEPS PS stringin ging the second circuit. it.
Afghanista tan Transmi mission
tion
Samangan Bamian Kajaki HPP 100MW Kajaki Panjsher Kunar
DABS-Afghanistan www.dabs.af
➢ HPP Construction:
➢ Thermal Plant - Construction of coal thermal
October 16
May 18 17